MTR

The Mass Transit Railway (MTR; Chinese: 港鐵; Cantonese Yale: Góngtit) is a major public transport network serving Hong Kong. Operated by the MTR Corporation Limited (MTRCL), it consists of heavy rail, light rail, and feeder bus service centred on an 11-line rapid transit network serving the urbanised areas of Hong Kong Island, Kowloon, and the New Territories. The system included 230.9 km (143.5 mi) of rail in 2018[3] with 163 stations, including 95 heavy rail stations and 68 light rail stops.[1] The MTR is one of the most profitable metro systems in the world; it had a farebox recovery ratio of 187 per cent in 2015, the world's highest. The MTR was ranked the number one metro system in the world by CNN in 2017.[5]

Mass Transit Railway (MTR)
港鐵
An MTR train on the Tung Chung line
Overview
LocaleHong Kong
Transit type
Number of lines
  • Heavy rail: 11
  • Light rail: 12
Number of stations
  • Heavy rail: 95[1]
  • Light rail: 68[1]
Daily ridership
  • Rapid transit:
    4.962 million
  • Others:
    0.702 million
(May 2019)[2]
Websitemtr.com.hk
Operation
Began operation
  • 1 October 1910
    (KCR opened)
  • 1 October 1979
    (MTR opened)
  • 2 December 2007
    (MTR and KCR operations merged)
Operator(s)MTR Corporation
Technical
System length
  • Heavy rail: 174.7 km (108.6 mi)[3]
  • Light rail: 36.2 km (22.5 mi)[3][4]
Track gauge
  • 1,435 mm (4 ft 8 12 in) standard gauge
    – East Rail, West Rail,
    Tuen Ma line, South Island line and Light Rail)
  • 1,432 mm (4 ft 8 38 in)
    almost-standard gauge
    – all other lines)
MTR network map

includes lines under construction

Mass Transit Railway (MTR)
Traditional Chinese港鐵
Simplified Chinese港铁
Hanyu PinyinGǎngtiě
Cantonese YaleGóngtit
Literal meaning"Hong Kong railway"

Under the government's rail-led transport policy,[6] the MTR system is a common mode of public transport in Hong Kong, with over five million trips made in an average weekday. It consistently achieves a 99.9 per cent on-time rate on its train journeys. As of 2018, the MTR has a 49.3 per cent market share of the franchised public transport market, making it the most popular transport option in Hong Kong.[7] The integration of the Octopus smart card fare-payment technology into the MTR system in September 1997 has further enhanced the ease of commuting on the MTR.

Construction of the MTR was prompted by a study, released in 1967, commissioned by the Hong Kong Government in order to find solutions to the increasing road congestion problem caused by the territory's fast-growing economy.[8] Construction started soon after the release of the study, and the first line opened in 1979. The MTR was immediately popular with residents of Hong Kong; as a result, subsequent lines have been built to cover more territory. There are continual debates regarding how and where to expand the MTR network.[9][10]

The MTR has served as a model for some newly built systems, particularly in urban rail transit in China.[11]

History

Initial proposals

"Preferred system" route map in 1970

During the 1960s, the government of Hong Kong saw a need to accommodate increasing road traffic as Hong Kong's economy grew rapidly. In 1966, British transportation consultants Freeman, Fox, Wilbur Smith & Associates were appointed to study the transportation system of Hong Kong.[12] The study was based on the projection of the population of Hong Kong for 1986, estimated at 6,868,000. On 1 September 1967, the consultants submitted the Hong Kong Mass Transport Study to the government, which recommended the construction of a 40-mile (64 km) rapid transit rail system in Hong Kong. The study suggested that four rail lines be developed in six stages, with a completion date set between December 1973 and December 1984.[8] Detailed locations of lines and stations were presented in the study. These four lines were the Kwun Tong line (from Western Market to Ma Yau Tong), Tsuen Wan line (from Admiralty to Tsuen Wan), Island line (from Kennedy to Chai Wan Central), and Shatin line (from Tsim Sha Tsui to Wo Liu Hang).

The study was submitted to the Legislative Council on 14 February 1968. The consultants received new data from the 1966 by-census on 6 March 1968. A short supplementary report was submitted on 22 March 1968 and amended in June 1968. The by-census indicated that the projected 1986 population was reduced by more than one million from the previous estimate to 5,647,000. The dramatic reduction affected town planning. The population distribution was largely different from the original study. The projected 1986 populations of Castle Peak New Town, Sha Tin New Town, and, to a lesser extent, Tsuen Wan New Town, were revised downward, and the plan of a new town in Tseung Kwan O was shelved. In this updated scenario, the consultants reduced the scale of the recommended system. The supplementary report stated that the originally suggested four tracks between Admiralty station and Mong Kok station should be reduced to two, and only parts of the Island line, Tsuen Wan line, and Kwun Tong line should be constructed for the initial system. The other lines would be placed in the list of extensions.[13] This report led to the final study in 1970.

In 1970, a system with four lines was laid out and planned as part of the British consultants' new report, Hong Kong Mass Transit: Further Studies. The four lines were to be the Kwun Tong line, Tsuen Wan line, Island line, and East Kowloon line.[14] However, the lines that were eventually constructed were somewhat different compared to the lines that were originally proposed by the Hong Kong Mass Transport Study.

In 1972, the Hong Kong government authorised construction of the Initial System, a 20-kilometre (12 mi) system that roughly translates to today's Kwun Tong line between Kwun Tong and Prince Edward, Tsuen Wan line between Mei Foo and Admiralty, and Island line between Sheung Wan and Admiralty. The Mass Transit Steering Committee, chaired by the Financial Secretary Philip Haddon-Cave, began negotiations with four major construction consortia in 1973.[15] The government's intention was to tender the entire project, based on the British design, as a single tender at a fixed price. A consortium from Japan, led by Mitsubishi, submitted the only proposal within the government's $5 billion price ceiling.[16] They signed an agreement to construct the system in early 1974, but in December of the same year, pulled out of the agreement for reasons stemming from fears of the oil crisis.[17]

Modified Initial System

"Modified Initial System" route map

Several weeks later, in early 1975, the Mass Transit Steering Group was replaced by the Mass Transport Provisional Authority, which held more executive powers.[18] It announced that the Initial System would be reduced to 15.6 kilometres (9.7 mi) and renamed the "Modified Initial System". Plans for a single contract were abandoned in favour of 25 engineering contracts and 10 electrical and mechanical contracts. On 7 May 1975 the Legislative Council passed legislation setting up the government-owned Mass Transit Railway Corporation (MTRC) to replace the Mass Transport Provisional Authority.[19][20]

Construction of the Modified Initial System (now part of the Kwun Tong line and Tsuen Wan line) commenced in November 1975. The northern section was completed on 30 September 1979 and was opened on 1 October 1979 by Governor Murray MacLehose.[21] Trains on this route ran from Shek Kip Mei station to Kwun Tong station, initially in a four-car configuration. The first train drivers were trained on the London Underground.[21] The route from Tsim Sha Tsui station to Shek Kip Mei station opened in December 1979.[17] The first line was designed by a consortium of consultants led by Freeman Fox and partners. On later extensions to the railway the stations were designed under the supervision of Roland Paoletti, the chief architect at MTR.[22]

In 1980, the first harbour crossing was made by an MTR train as the Kwun Tong line was extended to Chater station, since renamed Central station. Trains were extended to six cars to accommodate an increase in passenger numbers.

Line extensions

The government approved construction of the Tsuen Wan line in 1977, then known as the Tsuen Wan Extension, and works commenced in November 1978. The project added a 10.5-kilometre (6.5 mi) section to the MTR system, from Prince Edward to Tsuen Wan. The line started service on 10 May 1982 with a total cost of construction (not adjusted for inflation) of HK$4.1 billion[17] (US$526 million). The plan was modified from that in the 1970 report Hong Kong Mass Transit: Further Studies, with Kwai Chung station, Lap Sap Wan station, and a planned depot at Kwai Chung next to Lap Sap Wan station being replaced by stations at Kwai Hing and Kwai Fong and a depot at Tsuen Wan. Several stations also had names different to that during planning: So Uk station became Cheung Sha Wan, Cheung Sha Wan became Lai Chi Kok, and Lai Chi Kok became Lai Wan (later renamed as Mei Foo).

When service of this line started, the section of the Kwun Tong line from Chater to Argyle (since renamed Central and Mong Kok stations respectively) was transferred to the Tsuen Wan line. Thus, Waterloo station (since renamed Yau Ma Tei station) became the terminus of the Kwun Tong line, and both Argyle and Prince Edward stations became interchange stations. This change was made because system planners expected the traffic of the Tsuen Wan line to exceed that of the Kwun Tong line. This forecast proved to be accurate, necessitating a bypass from the northwestern New Territories to Hong Kong Island. The Tung Chung line was therefore launched in 1998 with an interchange station at Lai King for that purpose.[17]

Although land acquisitions were made for a station at Tsuen Wan West, beyond Tsuen Wan station, as part of the Tsuen Wan branch, the station was never built. This is not to be confused with the modern-day Tsuen Wan West station on West Rail line, which lies on a newly reclaimed area near the former ferry pier.

Since opening in 1982, the Tsuen Wan line is the line whose alignment has remained the same for the longest time. For example, the Kwun Tong line's alignment has changed twice since its opening—the taking over of Tsuen Wan line from Mong Kok to Central, and the taking over of Eastern Harbour Crossing section by the Tseung Kwan O line.

Government approvals were granted for construction of the Island line in December 1980. Construction commenced in October 1981. On 31 May 1985, the Island Line was opened with service between Admiralty station and Chai Wan station. Both Admiralty and Central stations became interchange stations with the Tsuen Wan line. Furthermore, each train was extended to eight cars.[17] On 23 May 1986, the Island line was extended to Sheung Wan station. Construction was delayed for one year, as government offices which were located over the station had to be moved before the construction could start.

In 1984, the government approved the construction of the Eastern Harbour Crossing, a tunnel to be used by cars and MTR trains. The Kwun Tong line was extended across the harbour on 5 August 1989 to Quarry Bay station, which became an interchange station for the Kwun Tong line and the Island line. An intermediate station, Lam Tin, started operations on 1 October 1989.[17]

Airport connection

The Airport Express and Tung Chung line started services in 1998. The decision was made in October 1989 to construct a new international airport at Chek Lap Kok on Lantau Island to replace the overcrowded Kai Tak International Airport.[23] The government invited the MTRC to build a train line, then known as the Lantau Airport Railway, to the airport. Construction started in November 1994, after the Chinese and British governments settled their financial and land disagreements.

The new line was included in the financing plans of the new Hong Kong International Airport as the airport was not considered viable without direct public transport links. Construction costs were also shared by the MTRC, which was granted many large-scale developments in the construction plans for the new stations.

The Lantau Airport Railway turned into two MTR lines, the Tung Chung line and the Airport Express. The Tung Chung line was officially opened on 21 June 1998 by Hong Kong Chief Executive Tung Chee-hwa, and service commenced the next day. The Airport Express opened for service on 6 July 1998 along with the new Hong Kong International Airport.[17]

The Airport Express also offers flight check-in facilities at Kowloon station and Hong Kong station—the in-town check-ins offer a more convenient and time-saving routine; a free shuttle bus service transports travellers from these stations to their respective hotels as well. Porters are also available to help transport luggage from and onto trains.[24] It is the second most popular means of transport to the airport after buses. In 2012, it had a 21.8 per cent of share of the traffic to and from the airport. However, this has declined from a peak of 32 per cent in 1999.[25][26]

Tseung Kwan O line

The Tseung Kwan O line was opened in 2002 to serve new housing developments

The Quarry Bay Congestion Relief Works extended the Hong Kong Island end of the Kwun Tong line from Quarry Bay to North Point via a pair of 2.1-kilometre (1.3 mi) tunnels. The project was initiated due to overcrowding at Quarry Bay and persistent passenger complaints about the five-minute walk from the Island line platforms to the Kwun Tong line platform. Construction began in September 1997 and was completed in September 2001 at a cost of HK$3.1 billion.[27][28] As with most earlier interchange stations, a cross-platform interchange arrangement was provided here in both directions.

Construction of the Tseung Kwan O line (called the Tseung Kwan O extension line in the planning stage) was approved on 18 August 1998 to serve new housing developments. Construction began on 24 April 1999 and the line officially opened in 2002. It took over the existing Kwun Tong line tracks running through the Eastern Harbour Tunnel, so that the full line stretches from Po Lam to North Point. When the line was opened, the Kwun Tong line was diverted to Tiu Keng Leng on the new line. Construction costs were partly covered by the Hong Kong Government and private developers which linked construction of the Tseung Kwan O Line to new real estate and commercial developments.[29]

Interchange stations

The interchange between the Kwun Tong Line and the Tsuen Wan Line (except Yau Ma Tei) as well as that between the Kwun Tong line and the Tseung Kwan O line, are two stations long, allowing cross-platform interchange wherein a passenger leaves a train on one side of the platform and boards trains on the other side of the platform for another line. For example, when passengers are travelling on the Kwun Tong line towards Tiu Keng Leng, getting off at Yau Tong would allow them to switch trains across the platform for the Tseung Kwan O line towards North Point. Whereas, staying on the train and reaching Tiu Keng Leng would allow them to board the Tseung Kwan O Line trains towards Po Lam/LOHAS Park. This design makes interchanging more convenient and passengers do not have the need to change to different levels. However this interchange arrangement is not available for all transferring passengers at Kowloon Tong, Central, Hong Kong, Quarry Bay, Nam Cheong (except transfer between Tuen Mun and Hong Kong bound trains), Mei Foo, Tai Wai station (only between southbound Tuen Ma line and East Rail line trains) and Sunny Bay (except transfer between Tung Chung and Disneyland Resort bound trains) stations, mainly because this service is available only when there are two continuous stations shared as interchange stations by two lines.

Two major works were undertaken to ease interchange between the Kwun Tong line and East Rail line. The modification of Kowloon Tong station started in June 2001. A new pedestrian link to Kowloon Tong Station southern concourse and a new entrance (Exit D) opened on 15 April 2004 to cope with the increase in interchange passenger flow.[30] Modification to Tsim Sha Tsui station involved upgrading station facilities and concourse layout to facilitate access from the East Tsim Sha Tsui station via its pedestrian links.[Note 1] New entrances to the subway links were opened on 19 September 2004 (Exit G) and 30 March 2005 (Exit F), with the whole scheme completed in May 2005.

Disneyland Resort line

A Disneyland Resort line train waiting to depart

The Disneyland Resort line, previously known as Penny's Bay Rail Link, provides service to the Hong Kong Disneyland Resort which was opened on 12 September 2005. Service to Sunny Bay station on the Tung Chung line started in 2005. The new line and the Disneyland Resort station opened on 1 August 2005. It is a 3.5-kilometre (2.2 mi) single-track railway that runs between Sunny Bay station and Disneyland Resort station. The Disneyland Resort station itself was designed to blend in with the ambiance of the resort. The line operates fully automated trains running every four to ten minutes without a driver. The carriages are refurbished M-train rolling stock to match the recreational and adventurous nature of the 3.5-minute journey.[31]

Airport Express extension

The AsiaWorld–Expo station is an extension of the Airport Express serving a new international exhibition centre, AsiaWorld–Expo, at Hong Kong International Airport. The station opened on 20 December 2005 along with the exhibition centre. To cope with the projected increase in patronage, Airport Express trains were lengthened to eight cars from the previous seven. Additional trains are also deployed on the Tung Chung line during major exhibitions and events.[32]

Maritime Square, one of the major properties financing the MTR

Privatisation and merger

On 5 October 2000 the operator of the MTR network, MTR Corporation (MTRCL), became Hong Kong's first rail company to be privatised, marking the beginning of the Hong Kong government's initiative to dissolve its interests in public utilities. Prior to its listing on the Hong Kong Stock Exchange, the Mass Transit Railway Corporation (MTRC) was wholly owned by the Hong Kong government. The offering involved the sale of about one billion shares, and the company now has the largest shareholder base of any company listed in Hong Kong. In June 2001, MTRCL was transferred to the Hang Seng Index.

MTRCL has often developed properties next to stations to complement its already profitable railway business. Many recently built stations were incorporated into large housing estates or shopping complexes. For example, Tsing Yi station is built next to the Maritime Square shopping centre and directly underneath the Tierra Verde housing estate.

On 11 April 2006, MTRCL signed a non-binding memorandum of understanding with the Hong Kong government, the owner of Kowloon–Canton Railway Corporation, to merge the operation of the two railway networks in Hong Kong in spite of the strong opposition by the KCRC staff.[33][34] The minority shareholders of the corporation approved the proposal at an extraordinary general meeting on 9 October 2007, allowing MTRCL to take over the operation of the KCR network and combine the fare system of the two networks on 2 December 2007.[35][36]

On 2 December 2007 the Kowloon-Canton Railway Corporation (KCRC) granted a 50-year service concession (which may be extended) of the KCR network to MTRCL, in return for making annual payments to KCRC, thereby merging the railway operations of the two corporations under MTRCL's management. At the same time MTRCL changed its Chinese name from "地下鐵路有限公司" (Subway Limited Company) to "香港鐵路有限公司" (Hong Kong Railway Limited Company), but left its English name unchanged; at the same time the system's Chinese name changed from "地鐵" ("Subway") to "港鐵" ("Hong Kong Railway"). After the merger, the MTR network included three more lines—East Rail line, West Rail line, and Ma On Shan line (now the Tuen Ma line)—as well as the light rail network and Guangdong through train to Guangzhou.

On 28 September 2008, fare zones of all urban lines, East Rail line, Tuen Ma Line and West Rail line were merged. A passenger could travel on these networks with only one ticket, except where a transfer is made between Tsim Sha Tsui and East Tsim Sha Tsui stations, where two tickets are required. Student discounts on Octopus Card were also issued.

Recent extensions

MTR system map 07-09
MTR's High-speed rail service was launched on September 23, 2018. The image shows an MTR Vibrant Express train at Guangzhou South railway station

The MTR system has been extended numerous times since the railway merger. Relevant projects include the LOHAS Park spur line (2009), the Kowloon Southern Link (2009), the West Island Line (2014), the Kwun Tong line extension (2016), the South Island line (2016) and the Tuen Ma Line Phase 1 (2020).

The LOHAS Park Spur Line is an extension of the Tseung Kwan O line, splitting off after Tseung Kwan O station. It serves the new residential development of LOHAS Park (formerly "Dream City"), a 3,550,000-square-foot (330,000 m2) estate with fifty residential towers. The project is divided into 9 to 13 phases and is about halfway complete as of 2016. These high rises sit above LOHAS Park station, which opened on 26 July 2009.

The West Island Line, first put forward to the government on 21 January 2003, is an extension of the Island line. It serves the Western District of Hong Kong Island. The construction of the West Island Line started on 10 August 2009.[37] Kennedy Town station and HKU station opened on 28 December 2014. Sai Ying Pun station opened later, on 29 March 2015, due to construction delays.

A proposal to extend the existing Kwun Tong line to Whampoa Garden was made in April 2006 and approved in March 2008 as part of the bid for the Sha Tin to Central Link.[38][39] Two new stations at Whampoa and Ho Man Tin opened on 23 October 2016.[40]

The South Island line opened on 28 December 2016[41] between Admiralty and South Horizons, linking the Southern District to the MTR for the first time. With the opening of the South Island Line, all 18 districts of Hong Kong are served by the MTR.

The first section of the Tuen Ma line, an extension of the former Ma On Shan line connecting Tai Wai via Hin Keng and Diamond Hill to Kai Tak station, opened on 14 February 2020.

Future expansions

The future MTR map once all current projects are completed
Development of Hong Kong's railways (MTR)

1) The Sha Tin to Central Link project will create two new rail corridors upon completion:

  • a) The Kai Tak to Hung Hom section connecting Tuen Ma line Phase One and West Rail line to form Tuen Ma line has been delayed. The 1st section connecting Tai Wai via Hin Keng and Diamond Hill to Kai Tak station opened on 14 February 2020.[42] A revised date for the section from Kai Tak to Hung Hom and the merger of the West Rail line into the Tuen Ma line is expected in late 2020 or early 2021. The Tuen Ma line could be further extended to Tuen Mun South station serving Tuen Mun South.
  • b) The East Rail line extension from Hung Hom to Admiralty across Victoria Harbour is expected to be completed in 2021.[32]

2) The Tuen Mun South extension on the West Rail Line is a proposed 2.4 kilometer extension to a new western terminus , Tuen Mun South, near the Tuen Mun Ferry Pier. The extension will extend southwards from the current western terminus of the West Rail Line, Tuen Mun station.

3) The Northern Link is a proposed new line which connects Tuen Ma line with the Lok Ma Chau Spur Line of East Rail line. It also has Au Tau, Ngau Tam Mei, San Tin, a future interchange station between East Rail line and Northern Link, Kwu Tung, which will become a terminus for Northern link.

4) There would be two confirmed new stations on the Tung Chung Line, Tung Chung West and Tung Chung East. Tung Chung East station would serve the Tung Chung New Town, and Tung Chung West station would serve the Yat Tung Estate.

5) There would also be a new station on the West Rail Line, called the Hung Shui Kiu station. It is currently under planning. It may be built depending on the development of the Hung Shui Kiu New Town, and the Hong Kong-Shenzhen Airport Rail Link between Hong Kong International Airport and Shenzhen Bao'an International Airport.

6) The East Kowloon line would serve the East Kowloon area to Tseung Kwan O New Town via the hilly Sau Mau Ping, The Hong Kong University of Science and Technology residential area.

7) The South Island line (West) was part of the same original proposal as the South Island Line, and would connect HKU to Shek O around the west coast of Hong Kong Island, however construction has not started as of 2021-2022.

8) The North Island line is a planned extension of the Tseung Kwan O line that will interchange at the future Tamar station with the Tung Chung line. It will alleviate traffic in the northern part of Hong Kong Island. There will be three new stations: Tamar, Exhibition Centre (which will be an interchange between the North Island line and the North South Corridor), and Causeway Bay North. Construction is expected to begin in 2021 and finish in 2026. The cost is estimated to be HK$20 billion in 2013 prices.

Infrastructure

Current map
System map of the MTR effective from 28 December 2016.

Rail network

Name and livery Commencement Next extension Termini Length
(km)[3]
Stations Running time
(mins)[3]
Depot Gauge Electrification Control
centre
Heavy/commuter rail services
East Rail line 1 October 1910
(electrification: 1982–83)
2022 Hung Hom Lo Wu 41.5 14 45 Ho Tung Lau 1,435 mm (4 ft 8 12 in) AC 25 kV Tsing Yi
Lok Ma Chau 50
West Rail line 20 December 2003 2021 Hung Hom Tuen Mun 35.7 12 38 Pat Heung
Tuen Ma line Phase 1 21 December 2004 2021 Wu Kai Sha Kai Tak 17 12 28 Tai Wai
Tung Chung line 21 June 1998 2026 Hong Kong Tung Chung 31.1 8 29 Siu Ho Wan 1,432 mm (4 ft 8 38 in) 1500 V DC
Rapid transit services
Kwun Tong line 1 October 1979 N/A Whampoa Tiu Keng Leng 17.4 17 35 Kowloon Bay 1,432 mm (4 ft 8 38 in) 1500 V DC Tsing Yi
Tsuen Wan line 17 May 1982 N/A Central Tsuen Wan 16.0 16 32 Tsuen Wan
Island line 31 May 1985 N/A Kennedy Town Chai Wan 16.3[43] 17 34 Chai Wan
Tseung Kwan O line 18 August 2002 2026 North Point Po Lam 12.3 8 15 Tseung Kwan O
LOHAS Park 20
Disneyland Resort line 1 August 2005 N/A Sunny Bay Disneyland Resort 3.3 2 5 Siu Ho Wan 1,432 mm (4 ft 8 38 in) 1500 V DC Tsing Yi /
Sunny Bay
South Island line 28 December 2016 N/A Admiralty South Horizons 7.4 5 11 Wong Chuk Hang 1,435 mm (4 ft 8 12 in) Tsing Yi
Airport rail link
Airport Express 6 July 1998 N/A Hong Kong AsiaWorld–Expo 35.3 5 28 Siu Ho Wan 1,432 mm (4 ft 8 38 in) 1500 V DC Tsing Yi
High speed rail
Hong Kong Express Rail Link 23 September 2018 N/A West Kowloon Guangzhou South 26 1 Shek Kong 1,435 mm (4 ft 8 12 in) 25,000 V (AC)
Light rail services
Light Rail
(12 routes)
18 September 1988 N/A Varies Varies 36.2 68 Varies Tuen Mun 1,435 mm (4 ft 8 12 in) 750 V DC Tuen Mun

Rolling stock

Seven types of electric multiple unit rolling stock operate on the MTR network and four generations of light rail vehicles operate on the light rail network. All utilise either 1,432 mm (4 ft 8 38 in) rail gauge (near standard gauge)[44][45] or 1,435 mm (4 ft 8 12 in) (standard gauge). Except for Airport Express trains, all trains are designed to cope with high patronage, for example, through seating arrangements, additional ventilation fans, and additional sets of extra-wide doors. These configurations allow the MTR to run at 101,000 passengers per hour per direction (p/h/d) on its busy suburban East Rail line and 85,000 p/h/d on its urban metro network.[46]

Name Line(s) No. of cars per train No. of doors per side Entered service Notes
M-stock Island, Kwun Tong, Tseung Kwan O and Tsuen Wan lines 8 5 1979–1998 modified 1998
Disneyland Resort line 4 3 modified 1998, 2005
A-stock Tung Chung line 8 5 1998
Airport Express 2 1998 One of the cars only carry luggages
K-stock Tseung Kwan O line (from 2010) 5 2002 First operated on the Kwun Tong line
Tung Chung line 2006–2007
C-stock Kwun Tong line 2011–2013
South Island line 3 2016 Driverless configuration. In three-car formation instead of eight cars. Also known as S-train.
MLR East Rail line 12 5 (or 2 on First Class) 1982–1992 Modified 1996. Only one set of doors is used on first class normally.
R-stock 9 2020 First train delivered in 2015[47][48]
SP1900 12 2001 To be reconfigured for Tuen Ma Line
West Rail line 8 5 2003, 2007, 2016 Modified SP1950 for KRS991 + KRS991 Trains
Tuen Ma line 8 2004 2 sets transferred to West Rail line
EWL C-train 8 2017
Phase I LRV All services on the light rail 1–2 3 1988 Doors on the left side only
Phase II LRV 1992
Phase III LRV 1997
Phase IV LRV 2009
KTT MTR intercity services (along the East Rail line) 12 2 (coaches) 1998 10 coaches between 2 locomotives normally
Two M-trains (Kwun Tong line)
A-stock train (Tung Chung line)
K-stock train (Tung Chung line)
SP1900 train (East Rail line)
MLR train (East Rail line)
Phase 2 light rail vehicle (Route 751)

Metro Cammell EMU (DC)

Known as M-trains, these are the oldest model of train in operation. M-Trains can be divided into different "stocks". The M-stock (or "CM-stock") of M-Train are the oldest trains on the MTR, built originally by Metro-Cammell (now Alstom) and refurbished by United Goninan.[49][50] The M-train uses sliding doors, unlike K-stocks and Grupo CAF Trains which use plug doors. They are in service on Kwun Tong line, Tsuen Wan line, Island line and Tseung Kwan O line.

The Disneyland Resort line uses driverless M-trains with their appearance overhauled to suit the atmosphere and theme of the line. Windows on each carriage and the handrails inside are made into the shape of Mickey Mouse's head, and there are bronze-made Disney characters decorating the interior of the carriages.

Adtranz-CAF EMU

The Tung Chung line and the Airport Express use CAF Trains tailored to their respective lines. Initially run in seven-car formations, they have now been lengthened to eight cars. These two variations are built jointly by Adtranz (now Bombardier Transportation) and Grupo CAF (CAF) between 1994–97. Since 2006, K-stock has also been used on the Tung Chung line.

Rotem EMU

The K-stock was built jointly by Mitsubishi Heavy Industries and Hyundai Rotem and first put into service on the Kwun Tong line.[51] Subsequently, in 2006, four additional sets joined the Tung Chung line to cope with the increasing passenger traffic.[52] K-Stock trains have come under criticism when it was first put into service due to delays and door safety issues.[53] There have been incidents where passengers have been injured by its doors and other service reliability issues have led to MTRCL "minimising the number of Korean trains for passenger service until a higher reliability of the systems concerned is achieved".[53]

CNR Changchun EMU

The contract (C6554-07E) for 10 new sets of trains was awarded to Changchun Railway Vehicles Co. Limited in October 2008 with a further 12 trains ordered in the summer of 2011. These MTR trains were delivered to Hong Kong between 2011 and 2013 to enhance train frequency on the existing lines to cater for increased patronage on the Island line, Kwun Tong line, Tsuen Wan line and Tseung Kwan O line.[54] These trains feature new 22" LCD TVs, like their counterpart trains on former-KCR lines equipped with MTR In-Train TV, offering infotainment such as news and announcements. The first of these trains entered revenue service on 7 December 2011 on the Kwun Tong line.

The South Island line uses a similar train known as the S-train. Unlike the original C-train, the pantographs are on the A cars. All cars are powered, so there are no trailer cars. The S-train is also only three cars long and are driverless, with the driver's cab removed with space for passengers. However, the S-trains can still enable manual operation in the event of an emergency.

SP1900/1950 EMU

Both East Rail line and West Rail line use the SP1900 while Tuen Ma line uses SP1950, a shorter model of the SP1900. The electrification system used on these lines is 25 kV AC, 50 Hz, as opposed to the 1.5–kV DC used on the urban lines. Should the need arise in the future, dual voltage trains such as those utilised on Oresund Bridge would be required.

These two models of rolling stock are from the former KCRC network (KCR East Rail, West Rail and Ma On Shan Rail). They did not receive major changes after the merger of the two companies except for the updated route map, the exterior company logo and such. The capability of this EMU fleet is similar to those on the urban network.

Metro Cammell EMU (AC)

The older Metro Cammell EMUs are also used on East Rail line. There are 351 cars which have been built (29 sets + 3 surplus cars) since 1982.

There are currently plans to replace these cars with new Hyundai Rotem EMUs (R-stock) between 2018–2020. This is part of the upgrade programme related to the new Shatin to Central Link.

Hyundai Rotem EMU (R-stock)

In December 2012, the MTRC announced that new contracts had been awarded to Hyundai Rotem for 37 new nine-car trains to be used on the Sha Tin to Central Link.[55]

These trains are expected to replace the Metro Cammell EMUs that currently run on the existing East Rail line. The new R-stock trains are wider than existing units and can accommodate more passengers per car; however, the length of each train will be cut from the current 12-car configuration used on the Metro Cammell and SP1900 EMUs to nine cars. This is due to space constraints imposed by new underground platforms on the Sha Tin to Central Link. MTR will also upgrade existing signalling systems used on the East Rail line which will enable trains to operate at two-minute headways on average, instead of the current three-minute interval, which the MTRC expects will be able to compensate for the loss of capacity resulting from the shorter trains.[56] However, there are concerns from local residents that this will not be effective.[57]

Light rail vehicles

Light rail rolling stock were ordered from four different manufacturers: Commonwealth Engineering (Comeng), Kawasaki Heavy Industries, United Goninan and CRRC Nanjing Puzhen. They are designed to run on the standard gauge and utilise 750 V DC delivered through overhead lines. Trains comprise one or two carriages, where the second carriage functions as only a trailer. The arrangement allows each car to carry approximately 300 passengers with 26 seats, while four sets of poach seats provide flexible riding for passengers.

The light rail trains are being modernised as part of a 20th anniversary activity. Trains will include better disabled facilities as well as a totally new interior. The MTR will refurbish 69 older trains and buy 22 new ones. The first trains have been completed and were scheduled to be put into service in November 2009.[58][59][60] The whole project is expected to be completed in 2011.[61]

Maintenance trains

In addition to the passenger electric multiple units as covered above, MTR also uses various types of work trains for maintenance purposes:

Schöma diesel locomotives as used by MTR for work trains
  • On the urban lines and Lantau Airport Railway, several different battery-electric locomotives and diesel locomotives are used to haul various work trains (including ultrasonic test vehicles and specialist wagons used for overhead wiring access, cable laying, rail transport, tunnel repair etc.), with the former being built by Brush Traction and the latter by Schöma.[62] Like the passenger trains, they are also equipped with BSI couplers, albeit without the electrical connections.[62] The locomotives were delivered in different phases:
    • The battery electrics were delivered in three different phases. The first phase comprises five units numbered L51 to L55 which entered service in 1983 and are capable of hauling a maximum trailing load of 109 tonnes on a 3% of gradient. The second phase has six units numbered L56 to L61 which entered service in 1989. They have the same performance as the phase 1 units and can be assumed to be of the same general design. The pantograph is located atop the cab roof, with no sign of an air conditioner. The third phase comprises twenty units numbered L62 to L82 which entered service in 1996; most are used on the Lantau Airport Railway, but some on the urban lines. They are more powerful than the earlier units, being able to haul 160 tonnes. Their design is also slightly different to phase 2 units, with the pantograph at the opposite end, and an air conditioner above the cab.[62]
    • The Schöma diesel fleet came before the battery electrics. Capable of hauling 100 tonnes, they are presumed to have assisted in the construction of the network and came in three different phases: phase 1 (nine units numbered L11 to L19) in 1977, phase 2 (nine units numbered L20 to 28) in 1979 and phase 3 (eight units numbered L31 to L38) in 1983. They are presumed to be capable of multiple unit operation.[62]
  • On the ex-KCR lines, diesel locomotives such as the Eurorunner that were formerly used for freight services are now used on works trains and transferring EMUs trains between depots.[63] Maintenance trains for the East Rail Line are also largely stabled at Fo Tan depot.[64]
  • In 2015, MTR procured two new SF02T-FS rail milling machines from Linsinger. Instead of rail grinding, these machines mill the rail head, providing a more accurate profile and a higher quality processed surface. However, the machines are not without flaws and one of them caught fire on the Tsuen Kwan O Line on 9 May 2016 during maintenance hours.[65]

Station facilities, amenities and services

Bilingual real-time information is provided on every platform, shown above is the PIDS for East Rail line
Most heavy-rail stations have lifts connecting the platform and the concourse

The architecture of MTR stations is less artistic, instead focusing on structural practicability. With the high level of daily passenger traffic, facilities of the MTR stations are built with durability and accessibility in mind. After extensive retrofitting, the MTR system has become, in general, disabled-friendly—the trains have dedicated wheelchair space, the stations have special floor tiles to guide the blind safely on the platforms, and there are extra wide entry and exit gates for wheelchairs as well. Portable ramp for wheelchair users are available for boarding and alighting trains. On board the rolling stock, there are also flashing system maps on select trains while Active Line Diagrams and traditional route maps are installed on the others. Infopanels as well as on MTR In-Train TV onboard trains display important messages such as next station announcements as well as operational messages.[66]

Telecommunications

3G and LTE (4G) mobile phone network is in place throughout the MTR system of stations and tunnels allowing passengers to stay connected underground. Currently, full 3G network coverage in all stations and tunnels (except underground section on East Rail line and West Rail line) for the MTR system has been provided by 3 Hong Kong, SmarTone and PCCW. Passengers will be able to use high-speed internet on their mobile phones regardless whether the train is above ground or under ground.[67] The MTR has already extended the Wi-Fi service to all of the Airport Express trains and the expansion of the service to other MTR routes is still under consideration by MTR.[68] All 93 stations on the MTR offer free Wi-Fi service to passengers with a limitation of 15 minutes per session and a maximum of five sessions per day.[69]

In late 2015 it was announced that all 400 payphones in the MTR system would be removed in early 2016. The contract with the service provider, Shinetown Telecom, was expiring, and the MTR Corporation said that no one had tendered a proposal to take over the contract.[70][71] As a result, the MTR system no longer has payphones.

Announcements

When the system opened, public announcements were made in British English and in Cantonese by train captains and station staff. In the early 1990s the announcements were standardised, pre-recorded by RTHK presenter Cheri Chan Yu-yan (Chinese: 陳如茵), who is now an assistant professor of English-language education at the University of Hong Kong, and who remains the voice of the MTR today.[72][73] Since 2004, in order to accommodate Mainland Chinese visitors under the Individual Visit Scheme, Mandarin Chinese has been added to the repertory.

Public toilets

Unlike many other metro systems around the world, "main line" MTR stations originally did not have toilet facilities available for public use. Passengers may use MTR staff toilets at all stations on request. In 2006, MTRCL said it would not consider retrofitting existing underground toilets, because of the challenge of installing new piping and toilet facilities.[74] Only stations on the Airport Express and Disneyland Resort line had access to toilet facilities. All former KCR stations (on the East Rail line, West Rail line, and Tuen Ma line), merged into the MTR network in 2007, have public toilets.

During the Legislative Council rail merger bill discussions, the MTR Corporation was criticised by legislators for their unwillingness to install toilets in main line stations.[75] MTRCL indicated that it would carry out a review of the feasibility of installing public toilets at or in the vicinity of its above-ground railway stations.[74] Discussions between the Government and MTRCL have taken into account LegCo members' request for a stronger commitment by the corporation to the provision of public toilets on new railway lines. This resulted in MTRCL agreeing to include the provision of toilets within, or adjacent to, stations in the overall design parameters for all future new railway lines, subject to planning and regulatory approval and any concerns raised by residents in the vicinity about the location of external ventilation exhausts.[76]

Toilets have since been retrofitted into several existing MTR stations, including Sheung Wan station, Ngau Tau Kok station, Quarry Bay station, Mong Kok station, Prince Edward station, and Admiralty station. In addition, newly opened stations such as those of the West Island Line have toilets. The MTR plans to install public toilets at all interchange stations by 2020.[77]

In late 2017 the MTR introduced breastfeeding rooms at 20 interchange stations. The rooms are located in back of house areas, and are available upon request to MTR staff.[78][79]

Commerce and journals

Prior to the privatisation of MTRC, MTR stations only had branches of the Hang Seng Bank, Maxim's Cakes stores, and a handful of other shops. Since then, the number and types of shops have increased at stations has increased, turning some of them into miniature shopping centres. ATMs and convenience stores are now commonplace.

The MTR has contracted with publishers for the distribution of free magazines and newspapers in MTR stations. Recruit was the first free magazine which was solely distributed in stations (before railway merger) since July 1992, but the contract was terminated in July 2002. Another recruitment magazine Jiu Jik (招職), published by South China Morning Post, replaced Recruit as the only free recruitment magazine distributed in MTR stations bi-weekly. The Metropolis Daily (都市日報), published by Metro International, is the first free newspaper distributed free in MTR stations during weekdays (except public holidays); and in 2005, there is another weekend newspaper Express Post (快線週報), distributed every Saturday except public holidays. The Metropop (都市流行), a weekly magazine featuring cultural affairs and city trends also published by Metro International, started its distribution in MTR stations every Thursday since 27 April 2006, a few months after the termination of Hui Kai Guide (去街 Guide) in 2006. MTR Stations on ex-KCR lines feature two free Chinese-language newspapers, namely am730 and Headline Daily. MTR promotes reading of these newspapers by adding special coupons and promotion offers inside the newspapers, for example, a free trip to Lok Ma Chau or a free keyring. On the Kwun Tong line, East Rail line, Tuen Ma line and West Rail line, MTR In-Train TV is available.

MTR Bus

One of the double-decker feeder buses run by KMB

At various stations of the MTR network, the MTRCL (which took over from KCR) has set up feeder buses which enhance the convenience of taking the MTR. These bus routes, which normally consist of one to two stops, terminate at housing estates and go past major landmarks. The feeder bus routes on the East Rail line are run under the MTR name but are operated by Kowloon Motor Bus.

Signalling

Compartment for new signalling equipment on an MTR train

Throughout its history, MTR has used different signalling systems for its lines, with the main Operation Control Centre for the entire network being at Tsing Yi and formerly, Fo Tan and Kam Tin for the East Rail Line, Tuen Ma Line and West Rail Line.[80]

On the pre-merger MTR network, wayside signals are simple two-aspect signals whose colours are namely red for "stop" and blue for "proceed according to ATO"; this is made possible by the use of automatic train operation (ATO) which provides the onboard equipment the permitted speeds via undercarriage antennas located underneath the cab whereas the signals having been sent by radio transmitters located between the rails. An automatic train protection (ATP) is also used to enforce safety.[81]

In 1998, transmission balise-locomotive (TBL) was implemented on the East Rail Line to monitor train safety. Subsequently, in 2002, ATO was also implemented on the East Rail Line. However, the original British-style Automatic Warning System is still retained for use by Intercity-Through Trains.[82] On the other hand, the West Rail and Tuen Ma Lines use SelTrac moving block communications-based train control (CBTC) system from Alstom of France. The SelTrac system is also used by the fully automated Disneyland Resort Line whereas the South Island Line uses the Alstom Urbalis 400 CBTC system.

As part of RailGen 2.0 implemented from 2014 onwards to improve the standards of the rail network, the signalling systems on the older lines are to be replaced with new CBTC systems; the system used for the pre-merger network will be replaced with Alstom-Thales SelTrac[83][84][85] whereas that for the East Rail Line will be replaced by Siemens Trainguard CBTC. However, the signalling upgrades encountered a serious setback in the form of a train collision outside Central station on 18 March 2019.[86]

Line Supplier Solution Commission Date Remarks
Kwun Tong, Tsuen Wan and Island Lines Alstom[87] SACEM 1996-1998 N/A
Tung Chung Line, Airport Express 1998
Tseung Kwan O Line Siemens[88] 2002 includes a section of Kwun Tong Line between Lam Tin and Tiu Keng Leng and a service tunnel formerly connecting Lam Tin to the Eastern Harbour Tunnel.
Disneyland Resort Line Alstom SelTrac LS 2005 Fully automated
East Rail Line Alstom Transmission balise-locomotive 1998 Automatic Warning System (AWS) is also used for Intercity-Through Trains.
West Rail Line and Tuen Ma Line Alstom SelTrac IS 2003, 2004 N/A
South Island Line Alstom Urbalis 400[89] 2016 Fully automated
Light Rail unknown Vehicle identification system, man-machine interface 1988 N/A
Hong Kong Express Rail Link unknown CTCS-2 and CTCS-3[90] 2018
Future
Kwun Tong, Tsuen Wan, Island, Tsuen Kwan O, Disneyland Resort, Tung Chung and Airport Express Lines Alstom, Thales Advanced SelTrac CBTC[91] TBC Implementation delayed due to a train collision on the Tsuen Wan Line in March 2019
East Rail Line Siemens Trainguard MT CBTC[92] 2021 AWS will be retained for Intercity-Through Trains.
Former
Kwun Tong, Tsuen Wan and Island Lines Westinghouse Block Work 1979 Deactivated by 1998

Head office

MTR Headquarters Building, Telford Gardens

The MTR Headquarters Building is located at Telford Plaza.[93] It is a part of the larger Telford Garden complex, which was developed as part of a partnership between MTR and private development companies.[94]

Telford Plaza held an exhibition dedicated to the history of MTR in April 2014.[95]

Fares and tickets

After the rail merger, there are three different fare classes on the MTR: Adult, Students and Concessionary. Only children below the age of 12 and senior citizens 65 years or older are eligible for the concessionary rate on all lines. Full-time Hong Kong students between the ages of 12 and 25 qualify for the concessionary rate using a personalized Octopus Card on all lines except on Airport Express, or travel to or from cross-border stations (Lo Wu/Lok Ma Chau).[96] Children below the age of 3 travel free (unless they exceed the height range).

The fare of MTR between any two particular stations is not calculated using a particular formula, and must be looked up from the fare table. Fares for the Airport Express Line are significantly higher. Services to checkpoint termini are also more expensive than ordinary fares. Adult fares range from HK$3.6 to $52.6 (US$0.46–6.74). Concessionary fares are usually half the adult fare, and range from HK$1.50 to $27.00. Student fares are the same as child and elderly fare on the urban lines, but are the same as the Adult fares for journeys to or from checkpoint termini, and range from HK$1.50 to $51.00. The fare is subject to adjustment in June every year.

Prior to May 2009, MTR did not provide concessionary fares for the disabled. Legislators such as social welfare constituency legislator Fernando Cheung Chiu-hung and those from Hong Kong's Association for Democracy and People's Livelihood had for years demanded that such concessions be put in place.[97][98] In May 2009, MTR eventually agreed to offer the disabled concessionary fares with HK$2 million sponsorship from Transport and Housing Bureau and under the condition that Legislative Council amends the Disability Discrimination Ordinance.[99]

Single journey tickets can be purchased at vending machines while tourist passes, Octopus cards and other special tickets must be purchased at the ticket counter. Credit cards are only accepted to purchase Airport Express tickets and tourist Octopus cards from automatic vending machines located within Hong Kong airport.

Octopus cards

The Octopus card is a rechargeable contactless smart card used in an electronic payment system in Hong Kong developed by Australian company ERG Group. It was launched in September 1997 for use on the MTR (and KCR, now operated by MTR) and now is the most widely used electronic cash system for transactions in Hong Kong as many retailers (including supermarkets, car parks and fast food outlets) are fitted with readers.[100] The technology used was Sony's Felica line of smartcard. The Octopus card uses radio frequency identification (RFID) technology so that users need only hold the card in front of the reader, without taking it out of handbags and wallets.

Except for the Airport Express, MTR fares are slightly lower when using an Octopus card compared to using single journey tickets. For example, the cost of the three-minute journey from Admiralty to Tsim Sha Tsui across the Victoria Harbour is (as of January 2018) HK$9.7 using the Octopus card, compared with HK$10.5 for a single-journey ticket. Also, in order to have fare discounts and promotions, say Monthly Pass[101] and MTR Club Bonus Points Scheme,[102] passengers are required to hold an Octopus Card.

Tourist pass

The Tourist Day Pass gives tourists unlimited MTR rides for one day (with the exception of MTR Bus routes, the First Class of the East Rail line, the Airport Express, as well as journeys to and from Lo Wu, Lok Ma Chau and Racecourse stations). Each pass costs HK$55 and are available at all the MTR Customer Service Centres. Tourist Day Pass must be used within 30 days upon the day of issue.[103] The Airport Express Tourist Octopus Cards are also available. Cardholders may enjoy three days of unlimited rides on the MTR (except Airport Express, East Rail line First Class, Lo Wu and Lok Ma Chau stations) refundable deposit of HK$50 and choice of either a single (HK$220) or round trip (HK$300) on the Airport Express.[104]

Other fares

A touchless smart card system is used for single journey tickets. These tickets are pre-paid for between pre-determined stations, and are good for only one trip. There are no return tickets, except on the Airport Express. As of mid-2013, less than 5 per cent of MTR customers travelled on single journey tickets.[105]

Fares for the Airport Express are substantially different from main line fares. Apart from single tickets, same-day return tickets (same price as a single), and one-month return tickets are also available.

A one-day pass can be used for unlimited travel to and from Hong Kong Disneyland within the same day, and costs HK$50. This pass can be purchased from any MTR Customer Service Centres or Airport Express Customer Service Centres.[31]

Ticket recommendation

The Ticket Suggestion function is developed by MTR along with Route Suggestion on MTR website. Based on user's journey and travel pattern, it can recommend the most fare-saving ticket type for daily and non-daily commuters.[106]

Apart from official application, third parties, such as MTR Service Update, have been developed their own ticket recommendation, claiming to be more user-friendly and fare-saving. The Checkfare of MTR Service Update can recommend user whether to interchange at Tsim Sha Tsui/ East Tsim Sha Tsui, in order to receive more discount.[107]

Performance

Rapid Transit Ridership
Yearridership
(million)
±%
2008 1,309    
2009 1,323+1.1%
2010 1,410+6.6%
2011 1,482+5.1%
2012 1,553+4.8%
2013 1,600+3.0%
2014 1,676+4.8%
2015 1,707+1.8%
2016 1,716+0.5%
Source: [108]

Since the merger in 2007, MTR has consistently achieved a 99.9 per cent on-time rate, meaning 999 of every 1,000 passengers arrives at their destination within 5 minutes of scheduled time. In 2013, out of the 5.2 million passengers the MTR averaged each workday, 5.195 million passengers were considered to have arrived "on time".[109] This makes MTR one of the most efficient rapid transit systems on the planet.[110] MTR must report all delays of more than eight minutes to the government. There were 143 reportable incidents in 2013.[109] MTR is fined HK$1 million for having delays of 31 minutes to an hour, with higher fines for longer delays.[111]

Regulations and safety

According to the Mass Transit Railway By-laws, eating, drinking, or smoking are not allowed in the paid area of stations or in trains. Offenders will be fined up to HK$5000.[112]

Various campaigns and activities are taken to help ensure that the MTR is a safe system to travel on. Poster campaigns displaying information on topics such as escalator safety are a common sight in all MTR stations, and announcements are made regularly as safety reminders to travelling passengers. Bylaws were also introduced to deter potentially dangerous actions on the MTR, such as the ban on flammable goods on the MTR and rushing into trains when the doors are closing. Penalties ranging from fines to imprisonment have been imposed for such offences.[113]

Police officers patrol the trains and stations, and police posts are available at some stations. The Hong Kong Police Force has a Railway District responsible for the MTR. Closed-circuit television cameras are installed in stations and on some of the newer trains.[114]

The entire Tung Chung line and Airport Express, as well as the stations added by the Tseung Kwan O Line, has platform screen doors (PSDs), ordered from Swiss glass door manufacturer Kaba Gilgen AG,[115][116] installed upon construction. So does the entire West Rail line (except Hung Hom station), inherited from KCR. These doors make platforms safer by preventing people from falling onto the rails, even though MTRCL did not heavily promote it directly. However, the primary motivation was to separate the stations from the tunnels, hence allowing substantial energy savings on station air-conditioning and tunnel ventilation.[117] Automatic platform gates (APGs) have also been installed at the Sunny Bay and Disneyland Resort stations. Their heights are half of the PSDs and only prevent people from falling onto the rails. MTR has finished installing the APGs on all of the above-ground stations of the MTR except on the East Rail line; they will be installed there as part of the Sha Tin to Central Link project.[118]

In June 2000, MTRCL proceeded with its plans to retrofit 2,960 pairs of platform screen doors at all 30 underground stations on the Kwun Tong line, Tsuen Wan line, and Island Line in a six-year programme. The programme made MTR the world's first railway to undertake the retrofitting of PSDs on a passenger-carrying system already in operation. A prototype design was first introduced at Choi Hung station in the 3rd quarter of 2001. The whole installation scheme was completed in October 2005, ahead of the forecast completion date in 2006. MTRCL said that part of the cost had to be assumed by passengers.[119] HK$0.10 per passenger trip was levied on Octopus card users to help fund the HK$2 billion retrofit programme. This levy was ended in 2013 after raising more than HK$1 billion.[120]

Visual identity

The MTR visual identity, which includes logo, vehicle livery, signage, route maps and passenger information, was updated in 1995–1998 by Lloyd Northover, the British design consultancy founded by John Lloyd and Jim Northover.

Social outreach

Live art performances in the subway connecting Hong Kong station and Central station

Art promotion

With the objective "not only bring MTR passengers more time for life, but also more time for art", the Art in MTR Initiative has been a success since its reception in 1998, where the Airport Express Artwork Programme was the pioneer project. Thereafter, live performances, art exhibitions, display of artwork by established and emerging artists, students and young children have been brought into the MTR stations. MTRCL have even made art part of the station architecture when building new stations or renovating existing ones. Artworks are exhibited in different forms on the network, including "arttube", open art gallery, community art galleries, roving art, living art, and art in station architecture.[121]

MTR Hong Kong Race Walking

MTR and Hong Kong Amateur Athletic Association have jointly hosted MTR Hong Kong Race Walking annually in spring since 2005. The race walking competition aims at promoting healthy living in Hong Kong. The race begins and ends on the ground above Central MTR station, namely Chater Garden, Chater Road, Ice House Street and Des Voeux Road Central in Central.[122][123] There is a fun walk apart from the regular competition. The event attracted over 800 participants in 2005 and 1,500 in 2012.[124] The event is attended not only by Hongkongers, but also athletes from various countries. The race raises fund for Better Health for a Better Hong Kong, a Hospital Authority project for the working population.[125][126]

Controversies

Destruction of conservation area in Yuen Long

The MTR Corporation came under fire in June 2011 after their work on the cross-border high-speed railway line encroached on a conservation area in Pat Heung, Yuen Long. 34 trees were felled and an entire slope was concreted over in the conservation area. The Environmental Protection Department issued summonses to the corporation for offences under the Environmental Impact Assessment Ordinance. In September 2011, a fine of HK$15,000 was imposed by the court. The MTR Corporation admitted that 34 trees were felled by mistake; all were common native woodland species and no rare tree species were affected. The corporation said owing to a technical misalignment of relevant drawings, the plan submitted to the Environmental Protection Department did not include the part of the Conservation Area which was included in the gazettal plan of their works. The corporation became aware that part of the approved tree removal works may have encroached onto the Conservation Area during construction, and proactively reported the situation to the government. Evaluation and measures have been taken to prevent similar incidents from happening again.[127][128][129]

Tree falling and failure to preserve indigenous species

The MTR Corporation came under fire again in September 2011 after felling dozens of trees in Admiralty as part of construction work for the South Island line. Green activists denounced the tree felling as "unprofessional", and Ken So Kwok-yin, chief executive of the Conservancy Association and a certified tree arborist, said that the explanations offered by the MTR Corporation as to why the trees were felled were "unacceptable". The MTR Corporation is felling approximately 4,000 trees for the construction of the South Island line, raising concerns from environmental groups and the public about its commitment to protecting Hong Kong's natural environment.[130]

Limits on oversized luggage

Mainland Chinese parallel traders outside Sheung Shui station

The corporation has limits on the size of items allowed on trains. The MTR system is facing pressure from increasing numbers of parallel traders who carry oversized baggage onto trains for resale in China. The corporation has been criticised for allowing parallel traders to board trains with massive bags, causing undue congestion and inconvenience to residents of the North District.[131]

Furthermore, the corporation accused of double standards in enforcement when images of cross-border smugglers pushing overladen trollies appeared on social network sites on a regular basis, whilst local students carrying large musical instruments were reported to have been stopped and issued with written warnings.[132][133] Leading musicians joined in the criticism of MTR's unreasonable stance on large instruments; some citizens invited players of cellos and other large instruments to congregate on 3 October 2015 with their equipment at Tai Wai station, where the majority of these instances occurred.[133]

Following the public uproar, MTR issued a press release in the early hours acknowledging discontent and announcing a one-month review of the policy on oversized items to see whether there was room for fine-tuning that would not compromise on passenger safety. The corporation said that staff would continue executing existing policy until any revisions are made.[134]

October 2018 disruption

On 16 October 2018, four MTR lines suffered delays simultaneously, an unprecedented disruption to railway services.[135] MTR stated that initial investigations showed that the problems were related to the computers that control the signalling system, and an in-depth investigation would be carried out.[136]

Cathay Pacific advertisement

In May 2019, the MTR Corporation and the Airport Authority Hong Kong reportedly refused to display a Cathay Pacific advertisement featuring two men holding hands due to its LGBT message.[137]

Gang attack at Yuen Long station

On 21 July 2019, a mob of men dressed in white and carrying wooden sticks and metal pipes entered the MTR's Yuen Long station and assaulted people indiscriminately. The attack is largely believed to have been carried out by pro-Beijing paid thugs. One pregnant woman was hurt and found lying on the floor, and journalists were also attacked. The mob entered the paid area and attacked commuters aboard a train, which was unable to depart. Over 40 people were sent to hospital.[138][139] After the incident, pro-Beijing legislator Junius Ho was accused of supporting the attack.[140]

Attack on protesters at Prince Edward Station on 31 August 2019

On 31 August 2019, during the anti-extradition bill protests, Special Tactical Squad officers of the Hong Kong Police Force entered Prince Edward station and attacked people inside. They fired tear gas inside the station and trains, violating guidelines on the use of such products in enclosed spaces.[141] Bystanders were caught in the operation and it has generally been deemed a brutal attempt to stop the protests.[142] Widespread rumours of civilian deaths at the station circulated after discrepancies were noted regarding the number of injuries. The MTR refused to provide CCTV footage filmed during the incident, helping to perpetuate these rumours.

Citizens trying to stop the gate from closing at Kwun Tong Station on 24 August 2019, when a protest has just started nearby. They were also demanding the senior management of MTR to come out and provide a valid reason for the closure of stations.

Halting Services during the 2019–20 Hong Kong protests

On multiple occasions during the 2019–20 Hong Kong protests, MTR has sealed off stations close to locations of protest before their starting time. Supporters of the protests have thus criticised MTR of intentionally impeding the public from attending protests and unnecessarily affecting civilians, giving MTR the nickname “CCP railway” (Chinese: 黨鐵; lit. 'Party iron') [143].

Following a clash between police and protestors in the Yuen Long station on 21 August 2019, the Chinese state media People’s Daily published a commentary accusing MTR of “conspiring with protestors” by “arranging special free trains for rioters to escape”. In response to the accusation, MTR issued a statement declaring that it will close stations under emergency situations in the future [144]. After that, MTR has on multiple occasions closed off stations close to ongoing protests, for example closing the Lam Tin station, Kwun Tong station and Ngau Tau Kok station on 24 August 2020 before the starting time of a permitted demonstration in Kwun Tong [145]. Similar incidents of varying scale have occurred multiple times later [146] [147] [148], leading to the criticisms that MTR is cooperating with the government to prevent citizens from attending protests [149].

Arranging special train for riot police

On 24 August 2019, MTR arranged a special train exclusively to carry riot police to Kowloon Bay station, which was closed to the public at that time due to the demonstration nearby at Kwun Tong.[150] This has led to criticisms that MTR is assisting the government in oppressing the freedom of assembly and the freedom of expressions in Hong Kong.[151][152]

gollark: In most cases you have to unlock the bootloader.
gollark: And you might not be able to restore it in any case.
gollark: Rooting wipes your device, in general.
gollark: That would only work if at some future time it did exist.
gollark: A minor obstacle.

See also

Notes

  1. Tsim Sha Tsui station and East Tsim Sha Tsui station are two separate stations, so one single journey ticket cannot be used for interchange between them. It is only possible to interchange with an Octopus card, or get a second ticket. Passengers with only one ticket can interchange at Kowloon Tong station (Kwun Tong and East Rail lines), then interchange at Hung Hom (for West Rail line) or Mong Kok (for Tsuen Wan line).

References

  1. "MTR – Services and Facilities – MTR Train Services". MTR Corporation. 2014. Retrieved 24 May 2015.
  2. "MTR Patronage Updates". MTR Corporation Limited. 2019. Retrieved 1 July 2019. Note that: 1) The "daily average" of MTR lines from this link actually means the "weekday average". The real daily average of MTR lines equals to the "monthly total" divided by the number of days in that month. 2) The rapid transit includes "domestic service", "Airport Express" and "cross-boundary". 3) "Others" includes "Intercity, light rail, and bus" and "HSR".
  3. "Business Overview" (PDF). MTR Corporation. 2018. p. 5.
  4. "MTR Press Release" (PDF). MTR Corporation Limited. 2012. Retrieved 11 March 2013.
  5. Kok, Lee Min (29 October 2015). "Dubbed 'the best in class': 6 things about Hong Kong's MTR rail system". The Straits Times. Retrieved 27 February 2018.
  6. Merging Hong Kong's Railways, Civic Exchange, 2004
  7. "2018 Annual Report" (PDF). MTR Corporation. p. 32.
  8. Freeman, Fox, Wilbur Smith & Associates (1967). Hong Kong Mass Transport Study (Report).CS1 maint: multiple names: authors list (link)
  9. "Government has reached understanding with MTRCL on the terms for merging the MTR and KCR systems". Environmental, Transport and Works Bureau of HKSAR. 11 April 2006. Archived from the original on 8 April 2007. Retrieved 8 March 2007.
  10. "Possible Merger of MTR and KCR Systems". Environmental, Transport and Works Bureau of HKSAR. 6 November 2006. Archived from the original on 6 February 2007. Retrieved 5 March 2007.
  11. "Consultancy Services – The Client List". MTR Corporation. Retrieved 8 August 2013.
  12. Rail Mass Transit for Developing Countries: Proceedings of the Conference Organized by the Institution of Civil Engineers, and Held in London on 9-10 October 1989, Thomas Telford, 1990, page 141
  13. Freeman, Fox, Wilbur Smith & Associates (1968). Hong Kong Mass Transport Study Supplementary Report (Report).CS1 maint: multiple names: authors list (link)
  14. Freeman, Fox, Wilbur Smith & Associates (1970). Hong Kong Mass Transport Further Study (Report).CS1 maint: multiple names: authors list (link)
  15. "Talks on underground railway begin today". South China Morning Post. Reuters. 30 August 1973. p. 20.
  16. Loke, Peter (12 December 1973). "Govt to begin tube talks with Japanese". South China Morning Post. p. 1.
  17. "The History". Hong Kong Mass Transit InfoCenter. 27 October 2003. Archived from the original on 7 October 2007. Retrieved 8 March 2007.
  18. "Executive powers for tube Authority". South China Morning Post. 9 February 1974. p. 7.
  19. "Mass transit: 'Ayes' have it". South China Morning Post. 8 May 1975. p. 1.
  20. "Tube: the last legal hurdle is removed". South China Morning Post. 8 May 1975. p. 4.
  21. "Mass transit railway is all set to roll". South China Morning Post. 24 September 1979. p. 18.
  22. "Hong Kong – A city on the move". Royal Institute of British Architects. Archived from the original on 24 February 2008. Retrieved 12 October 2007.
  23. "The Airport Railway Project". Heavy Iron Station. Archived from the original on 11 March 2007. Retrieved 19 March 2006.
  24. "Complimentary service exclusively for Airport Express Passengers". MTR Corporation Limited. Archived from the original on 23 April 2006. Retrieved 17 April 2006.
  25. Yeung, Rikkie (2008). Moving Millions: The Commercial Success and Political Controversies of Hong Kong's Railways. Hong Kong: Hong Kong University Press. ISBN 978-962-209-963-0.
  26. "Annual Report 2006" (PDF). MTR Corporation Limited. 2006. p. 21. Retrieved 18 July 2007.
  27. Chan, Felix (16 April 2001). "Interchange to reduce congestion". South China Morning Post.
  28. "Quarry Bay Congestion Relief Works". Hong Kong Mass Transit InfoCenter. 27 October 2003. Archived from the original on 7 October 2007. Retrieved 8 March 2007.
  29. "Tseung Kwan O Extension". Hong Kong Mass Transit InfoCenter. 27 October 2003. Archived from the original on 7 October 2007. Retrieved 8 March 2007.
  30. "Recently Completed Projects". MTR Corporation Limited. Archived from the original on 11 March 2007. Retrieved 8 March 2007.
  31. "MTR Disneyland Resort Line". MTR Corporation Limited. Archived from the original on 10 March 2007. Retrieved 8 March 2007.
  32. "Projects in Progress (Hong Kong)". MTR Corporation Limited. Archived from the original on 8 March 2007. Retrieved 8 March 2007.
  33. "MTR Corporation Signs Memorandum of Understanding with The Government on Terms of Proposed Rail Merger" (PDF). MTR Corporation Limited. 11 April 2006. Retrieved 8 March 2007.
  34. "KCRC welcomes Government's announcement on way forward for rail merger" (PDF). Kowloon-Canton Railway Corporation. 11 April 2006. Archived from the original (PDF) on 1 December 2007. Retrieved 8 March 2007.
  35. "Rail merger proposal approved by shareholders (兩鐵合併獲股東表決通過)" (in Chinese). Ming Pao Instant News. 9 October 2007. Archived from the original on 11 October 2007. Retrieved 9 October 2007.
  36. "Poll Result of the Extraordinary General Meeting held on 9 October 2007" (PDF). MTR Corporation. Hong Kong Stock Exchange. 9 October 2007. Retrieved 9 October 2007.
  37. "Construction of MTR West Island Line Project Commenced" (PDF). MTR Corporation. 10 August 2009.
  38. "set of presentation materials on "Report on the scheme design of Shatin to Central Link:" provided by the Kowloon-Canton Railway Corporation (Chinese version only) [CB(1)1015/03-04(01)]" (PDF). Legislative Council. KCR. Retrieved 3 October 2016.
  39. "Legislative Council Panel on Transport Subcommittee on matters relating to railways" (PDF). Environment, Transport and Works Bureau. Retrieved 3 October 2016.
  40. "港鐵觀塘延線下月廿三日通車". Commercial Radio Hong Kong. 21 September 2016.
  41. "West Island Line & South Island Line". MTR Corporation Limited. Archived from the original on 15 March 2007. Retrieved 8 March 2007.
  42. "Island Line". Highways Department The Government of the Hong Kong Special Administrative Region. 14 April 2015. Retrieved 25 May 2015.
  43. "香港鐵路(MTR)". 2427junction.com.
  44. Allen, Geoffrey Freeman, Jane's World Railways, 1987–88, Jane's Information Group, 1987 (ISBN 9780710608482)
  45. "LCQ19: MTR trains' carrying capacity and services". Legislative Council. 12 January 2011.
  46. "Hyundai Rotem to deliver first SCL train this September". www.railway-technology.com. 31 July 2015. Retrieved 4 October 2016.
  47. "2nd MTR shipment successful delivery". Pioneer Logistics Group. 19 December 2015. Archived from the original on 5 October 2016. Retrieved 4 October 2016.
  48. "Metro in Hong Kong". ALSTOM Transport. Archived from the original on 25 March 2006. Retrieved 16 March 2006.
  49. "United Group Limited secures $40 million Hong Kong rail maintenance contract". United Goninan Limited. January 2002. Archived from the original on 15 March 2004. Retrieved 8 March 2007.
  50. "MTRC TKE C651 EMU, Hong Kong". Rotem Company. Archived from the original on 12 March 2007. Retrieved 8 March 2007.
  51. "New trains ordered for Tung Chung Line, Hong Kong". Rotem Company. Archived from the original on 12 March 2007. Retrieved 2 April 2007.
  52. "Review of MTRC Services and Incidents" (PDF). Hong Kong Legislative Council. Retrieved 6 November 2007.
  53. "Ten New Trains for MTR Service Enhancement" (PDF). MTR Corporation Limited. Retrieved 17 November 2008.
  54. "New Trains and Signalling System for the future Shatin to Central Link" (PDF). MTR Corp. Ltd. 14 December 2012. Retrieved 4 October 2016.
  55. "東鐵換37韓製列車 短3卡 加密班次「補數」". 明報. 24 May 2016. Retrieved 4 October 2016.
  56. Tse, Bruce (30 November 2015). "東鐵線將減三卡車 真係可以加班次抵銷影響?". Retrieved 4 October 2016.
  57. DVV Media UK. "China South rolls out Hong Kong light rail cars". Railway Gazette.
  58. [HD] MTR Light Rail: Lrv Phase IV 1112 Link Up With 1111 Trial Run In Depot. YouTube. 6 January 2013.
  59. {LR} Part 1 of LRV Phase IV no.1111 on Route 751. YouTube. 8 January 2010.
  60. "Light Rail Marks 20 years of Service With Vehicle Modernisation Programme" (PDF). MTR Corporation Limited. 2008. Retrieved 13 August 2008.
  61. Marcus Wong. "The MTR's other fleet of trains". Checkerboard Hill.
  62. Marcus Wong. "Delivering the KCRC fleet of ER20 diesel locomotives". Checkerboard Hill.
  63. Marcus Wong. "Maintenance trains on the MTR East Rail Line". Checkerboard Hill.
  64. Marcus Wong. "Rail milling machines on the MTR". Checkerboard Hill.
  65. "MTR Facilities For Passengers With Disabilities". MTR. Archived from the original on 3 October 2009. Retrieved 24 October 2009.
  66. "First 3G Operator to Connect to Four Major MTR line". 3G.co.uk. 7 June 2005. Archived from the original on 17 February 2012. Retrieved 7 June 2007.
  67. "Passengers Enjoy On-Board Internet Access as Airport Express Trains Go Wi-Fi" (PDF). MTR. 19 January 2009. Retrieved 19 January 2009.
  68. "Connect to the world with free Wi-Fi at every MTR station". MTR Corporation. Retrieved 2 August 2016.
  69. Cheng, Kris (29 December 2015). "'The end of an era': MTR says goodbye to hundreds of station payphones". Hong Kong Free Press.
  70. "All 400 payphones in MTR stations to be removed amid low usage". Hong Kong Economic Journal. 29 December 2015.
  71. Ball, Steve (19 April 1994). "Know the voice, now here's the face". South China Morning Post. p. 3.
  72. Yu, Alan (7 March 2015). "Mind the gap... Meet the woman behind those MTR announcements". South China Morning Post.
  73. "Bills Committee on Rail Merger Bill, Administration's Response to the Follow-up to Bills Committee Meetings" (PDF). Hong Kong Legislative Council. Retrieved 6 November 2007.
  74. "Legco gets rail merger back on track". The Standard. 9 June 2007. Archived from the original on 9 January 2008. Retrieved 6 November 2007.
  75. "Provision of Public Toilets in MTR Railway Stations" (PDF). Hong Kong Legislative Council Panel. Retrieved 7 November 2007.
  76. "Additional Public Toilets". Network Improvements. MTR Corporation. Retrieved 14 September 2015.
  77. Ng, Ellie (22 December 2017). "Hong Kong MTR introduces new breastfeeding rooms in 20 subway stations". Hong Kong Free Press.
  78. "Breastfeeding areas". MTR Corporation. Retrieved 27 December 2017.
  79. "OCC Migration". MTR Corporation Limited.
  80. Marcus Wong. "Railway signalling on the MTR underground". Checkerboard Hill.
  81. MTR East Rail Line: an intro. Checkerboard Hill.
  82. 港鐵正式批出三十三億元更新訊號系統合約,港鐵新聞稿,3 March 2015
  83. 阿爾斯通和泰雷兹為香港七條地鐵綫路提供先進的CBTC信號系统,阿爾斯通新聞稿,26 January 2015
  84. Thales and Alstom to supply advanced CBTC signalling system to Hong Kong’s seven metro lines,Thales Group,26 January 2015
  85. https://www.reuters.com/article/us-mtr-corp-train-accident-idUSKCN1QZ03K
  86. 市區綫訊號系統置換工程 Urban Lines ATC replacement,YouTube。
  87. Siemens: Hong Kong (China) Tseung Kwan O Line
  88. Alstom supplied solutions to the newly opened Hong Kong’s first driverless metro,Alstom Press Centre,2016-12-28
  89. 高鐵香港段訊號系統 Signalling system of eXpress Rail Link,YouTube。
  90. 訊號系統的核心,包括自動列車控制系統(Automatic Train Control)以及「聯鎖機制」(Interlocking)。自動列車控制系統的壽命一般為 20 年不等,因此不同的行車綫在增加運力的同時,亦會分批改用全新,且以通訊為本方式運作的行車訊號:……,MTR Service Update。
  91. Siemens automates metro for Hongkong,Siemens Global Website(2012年12月21日)
  92. "Contact Us." MTR. Retrieved on October 10, 2016. "MTR Headquarters Building, Telford Plaza, 33 Wai Yip Street, Kowloon Bay"
  93. Xue, Charlie Q. L. Hong Kong Architecture 1945–2015: From Colonial to Global. Springer, June 13, 2016. ISBN 9811010048, 9789811010040. p. 142-143. 6.2 Experiment in the 1980s
  94. Lee, Ada (10 April 2014). "Veterans remember small beginnings of MTR". South China Morning Post. Retrieved 10 October 2016. - Print title: "MTR 'courtesy girl' still manning station 35 years on"
  95. "MTR Student Fare Concessions To Be Available Network-wide in New Promotion Offer" (PDF). MTR Corporation Limited. Retrieved 15 August 2008.
  96. "Social Inclusion without Corporate Social Responsibilities?". 立法會張超雄議員 Limited. Archived from the original on 26 October 2007. Retrieved 6 November 2007.
  97. "Subcommittee to Study the Transport Needs of and Provision of Concessionary Public Transport Fares for Persons with Disabilities" (PDF). Hong Kong Legislative Council Limited. Retrieved 6 November 2007.
  98. "港鐵傷殘半價 政府貼200萬 11萬人料年底受惠 九巴擬傚法 (lit. Disabled 50% discount by MTR. Government subsidises HK$2 million. May benefit 110 thousand comunters. KMB considers to follow.". Ming Pao. 22 May 2009. Archived from the original on 27 May 2009. Retrieved 5 August 2009.
  99. "Our History". Octopus Holdings Limited. Archived from the original on 27 December 2012. Retrieved 8 March 2007.
  100. "Monthly Pass Extra". MTR. Retrieved 26 October 2017.
  101. "Bonus Points Scheme 15 September to 14 December 2017". MTR. Retrieved 26 October 2017.
  102. "Tourist Tickets". MTR Corporation. Retrieved 18 September 2015.
  103. "Airport Express Travel Pass". MTR Corporation. Retrieved 18 September 2015.
  104. Lee, Ada (29 August 2013). "Smart cards to replace single-trip tickets on MTR". South China Morning Post.
  105. ""TICKET SUGGESTION" FUNCTION". MTR. Retrieved 26 October 2017.
  106. "Checkfare". MTR Service Update. Retrieved 26 October 2017.
  107. "MTR Patronage Updates". MTR Corporation Limited. 2014. Retrieved 13 June 2015.
    Note that:
    1) Annual ridership is derived from the sum of each month's "monthly total" for each year
    2) The ridership includes "MTR lines", "Airport Express" and "cross-boundary".
    3) "Intercity, light rail, and bus" are excluded from the counts.
    4) Data is available as early as year 2000, however only count ridership from the pre-merger MTR urban network and not the ex-KCR network. Therefore it is not shown here.
  108. "CB(1)980/13-14(05) Administration's paper on follow-ups on the service suspension of Tseung Kwan O Line and part of Kwun Tong line on 16 December 2013, and report on subsequent major incidents on East Rail line and light rail" (PDF). Legislative Council of Hong Kong. 25 February 2014. Retrieved 27 April 2014.
  109. Lucas, Clay (26 June 2006). "Train operator at 99.9% efficiency". The Age. Retrieved 27 April 2014.
  110. Eddie Luk (28 April 2014). "MTR blasted for warning delay". The Standard. Archived from the original on 17 October 2015. Retrieved 7 April 2015.
  111. "Mass Transit Railway By-Laws" (PDF). Mass Transit Railway. Retrieved 18 February 2015.
  112. "Mass Transit Railway By-laws". Bilingual Laws Information System, Department of Justice of HKSAR. 30 June 2000. Retrieved 8 March 2007.
  113. López, M.J.J. (1996). Crime Prevention Guidelines for the Construction & Management of Metro Systems (Report). Den Haag: RCM-advies.
  114. "Automatic Platform Screen Doors for public transportation 29/8/2008" (PDF). Kaba Gilgen AG. 2002. p. 7. Archived from the original (PDF) on 15 June 2007. Retrieved 9 March 2007.
  115. "Investor's Handbook 2002/2003" (PDF). Kaba Holding AG. September 2002. p. 72. Archived from the original (PDF) on 5 June 2007. Retrieved 8 March 2007.
  116. "Platform Screen Door (2002/8)". MTR Corporation Limited. Archived from the original on 11 March 2007. Retrieved 8 March 2007.
  117. "MTR – Shatin to Central Link – Construction – Related Works on East Rail line and Ma On Shan Line". MTR Corporation. Archived from the original on 22 March 2014. Retrieved 22 March 2014.
  118. "LCQ16:Retrofitting of PSDs at MTR stations to be completed by 2006". HKSAR Government Information Centre. 5 January 2005. Retrieved 8 March 2007.
  119. Siu, Phila; Ada Lee (20 June 2013). "MTR to drop 10c Octopus levy for screen doors". South China Morning Post. Retrieved 7 January 2014.
  120. "art in mtr". MTR Corporation Limited. Archived from the original on 22 February 2007. Retrieved 8 March 2007.
  121. "MTR HONG KONG Race Walking 2007". MTR Corporation. 2006. Archived from the original on 28 February 2007. Retrieved 12 March 2007.
  122. "Race information (2007)". Hong Kong Amateur Athletic Association (HKAAA). Archived from the original on 2 March 2007. Retrieved 12 March 2007.
  123. "Race Information (2006)". Hong Kong Amateur Athletic Association (HKAAA). Archived from the original on 8 February 2006. Retrieved 12 March 2007.
  124. "The City Walks for Fun". MTR Corporation. 2006. Archived from the original on 18 April 2007. Retrieved 12 March 2007.
  125. "Race Walking to Make Debut in Hong Kong". China.org.cn. 24 January 2005. Retrieved 12 March 2007.
  126. Cheung Chi-fai, "MTR 'out of line' on tunnel – Corporation and its contractor face charges under environmental laws after conservation area is cleared to make way for a construction site", The South China Morning Post, 14 June 2011.
  127. Joyce Ng, "MTR 'let of lightly' for tree-felling", Page CITY 1, The South China Morning Post, 20 September 2011.
  128. "港鐵保育區斬樹罰款1.5萬", Page A12, Ming Pao, 20 September 2011.
  129. Cheung Chi-fai, "MTR tree felling angers greens – South Island Line clearance should have saved more indigenous species, say conservationists", The South China Morning Post, 5 September 2011.
  130. "改閘機 加圍欄 禁逗留月台
    港鐵三招打擊水貨客 – 蘋果日報 – 要聞港聞"
    . Apple Daily (in Chinese). 2 March 2009.
  131. "Hong Kong student threatened with fine for carrying cello on train". The Strad. 24 September 2015.
  132. "Musicians plan protest after MTR evicts student carrying a cello". Hong Kong Economic Journal. 25 September 2015.
  133. "【樂器風波】港鐵漏夜發聲明 終願檢討乘客攜物件規定". Apple Daily 蘋果日報.
  134. Cheng, Kris (16 October 2018). "MTRC to offer commuters half-price fares on selected day as compensation for Tuesday travel chaos". Hong Kong Free Press.
  135. Su, Xinqi (17 October 2018). "Rogue computers acted alone to cause Hong Kong rail failure and MTR Corp's top engineer doesn't know why". South China Morning Post.
  136. Lee, Danny (20 May 2019). "Cathay Pacific's LGBT ad banned from Hong Kong airport and MTR". South China Morning Post. Retrieved 21 May 2019.
  137. "Yuen Long MTR Station closed after violent attacks". RTHK. 21 July 2019. Retrieved 21 July 2019.
  138. 林, 祖偉 (22 July 2019). "香港元朗白衣人暴襲記者平民引眾怒,警方否認縱容勾結「黑社會」" (in Chinese). BBC Chinese. Retrieved 22 July 2019.
  139. 【無警時份】何君堯向元朗白衣人鼓掌豎拇指:你哋係我嘅英雄. "real time news" section. Apple Daily (in Chinese). Hong Kong: Next Digital. 21 July 2019. Retrieved 21 July 2019.
  140. "Pepper-balls, tear gas shot at Prince Edward protest". RTHK. Retrieved 5 January 2020.
  141. "Hong Kong: Rampaging police must be investigated". Amnesty International. Retrieved 5 January 2020.
  142. Creery, Jennifer. "Explainer: 'The Communist Party's Railway' – How Hong Kong's once-respected MTR fell afoul of protesters". Hong Kong Free Press. Retrieved 13 June 2020.
  143. Chan, Holmes (23 August 2019). "Hong Kong's MTR threatens to halt trains during station protests, as state media deems firm an 'accomplice to rioters'". Hong Kong Free Press. Retrieved 13 June 2020.
  144. "Hong Kong MTR shuts 4 stations around legal protest in Kwun Tong following China pressure". Hong Kong Free Press. 24 August 2019. Retrieved 13 June 2020.
  145. "MTR closing some stations because of protests". Radio Television Hong Kong. 25 August 2019. Retrieved 13 June 2020.
  146. Chan, Holmes (6 October 2019). "Over half of MTR stations remain closed as Hong Kong protesters call for '3-million-strong' march". Hong Kong Free Press. Retrieved 13 June 2020.
  147. "Yuen Long MTR station to shut at 2pm ahead of protest commemorating July 21 attack". Coconuts Hong Kong. 21 October 2019. Retrieved 13 June 2020.
  148. "持續大規模關閉車站 港鐵已成中共黨鐵?". 新唐人亞太電視台 (in Chinese). 12 October 2019. Retrieved 13 June 2020.
  149. "MTR runs train along closed line just for police". Radio Television Hong Kong. 24 August 2020. Retrieved 18 June 2020.
  150. "香港示威者指港鐵已成為當局打壓工具". 美國之音 (in Chinese). Retrieved 18 June 2020.
  151. "譚文豪:港鐵淪政權打壓港人集會自由打手". 信報 (in Chinese). 24 August 2020. Retrieved 18 June 2020.

KML is from Wikidata
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.