Payra Power Plant

The Payra Power Plant is a proposed 1,320 megawatt coal-fired power station to be built in Kalapara Upazila of Patuakhali District in southern Bangladesh.[1][2] It is a joint venture between the North-West Power Generation Company Bangladesh Limited (NWPGCL) and China National Machinery Import and Export Corporation (CMC).[3]

History

On 19 March 2015, a deal was signed between NWPGCL and the CMC to set up the Payra Power Plant.[4] The joint venture was named Bangladesh-China Power Company Limited (BCPCL).[4] On 29 March 2016, BCPCL signed an engineering, procurement and construction (EPC) contract with consortium of NEPC &CECC for the installation of the power plant.[5]

About

The plant will consist of two units, each with a capacity of 660 MW.[6] The estimated cost is around US$1.56 billion.[7] The plant will be built on an area of 397-hectare.[8] The first unit will come into commercial operation on December 2019.

gollark: Your service files won't work the same, but the actual code should even work on exotic OSes like Windows.
gollark: Technically, it isn't right now, probably.
gollark: Also platform-specific.
gollark: Signals? Sounds uncool.
gollark: I was thinking HTTP, but people would complain.

See also

References

  1. Aminur Rahman Rasel (12 October 2015), "Payra coal power plant to be commissioned in 2019", Dhaka Tribune
  2. "Deal inked with China for mega power plant", The Independent, Dhaka, 30 March 2016
  3. "1320MW Payra Power Plant's EPC signed - Energy Bangla". 2016-03-29. Retrieved 2016-07-14.
  4. "Deal on Payra power plant today". The Daily Star. BSS. 28 March 2016. Retrieved 2016-07-14.
  5. "Chinese consortium signs deal to construct Bangladesh's 1.56-bln-USD power plant". Xinhua. 30 March 2016. Retrieved 2016-07-15.
  6. "Bangladesh-China JV to construct $1.56 bln power plant in southern Bangladesh". Reuters. 2016-03-30. Retrieved 2016-07-14.
  7. "Sino-Bangla JV signs deal to build Payra power plant". The Financial Express. Dhaka. 30 March 2016. Retrieved 2016-07-15.
  8. Aminur Rahman Rasel (28 March 2016). "Payra 1,320MW coal-based plant deal to be inked today". Dhaka Tribune. Retrieved 2016-07-15.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.