Bundesautobahn 94

Bundesautobahn 94 (translates from German as Federal Motorway 94, short form Autobahn 94, abbreviated as BAB 94 or A 94) is an autobahn in southern Germany. When completed, it will connect Munich with Passau. Currently, only the parts Munich-Burghausen, and a small section in Malching have been built. Between Burghausen and Simbach am Inn, there is a 14 kilometer, two-lane section that is signed as Bundesstraße 12. Provisions for an upgrade to A 94 exist here.

A94
Bundesautobahn 94
Route information
Length70 km (40 mi)
85 km planned
Location
StatesBavaria
Highway system
A93A95

The route between Forstinning and Heldenstein was the subject of a decades-long debate.

History

In the original plans for the A 94, the section between Simbach and Passau was not planned. Instead, the A 94 was supposed to cross the Inn to the Austrian border, at which point it would continue through the Innviertel to Ried im Innkreis and connect to the Austrian A 8 towards Vienna. This path would have decreased travel time from Munich to Vienna compared to the route via Salzburg. Provisions for such a routing were built in Simbach and in Ried. However, since Austria didn't want to burden the Innviertel with traffic, the plan was given up on the Austrian side. After this, on the German side, the plans were changed so that the A 94 connected with the A 3 at Pocking/Neuhaus am Inn. This makes an eventual northern extension to the Czech border possible.

At one point, a route from Mühldorf to Pfarrkirchen to Pocking was planned. Under this plan, today's A 94 section from Mühldorf to Simbach would have been given the designation A 942.

Exit list

() München-Steinhausen B2 R
Tunnel Seitentunnel Einsteinstraße 420 m
() München-Vogelweideplatz

(1) München-Steinhausen
(2) München-Zamborf
(3) München-Daglfing
Bahnbrücke 60 m
(4) München-Am Moosfeld
(5) München-Riem
(6) Feldkirchen-West
(7) Feldkirchen-Ost
(8) München-Ost 4-way interchange A99 E45 E52
(9a) Parsdorf
(9b) Markt Schwaben
(10) Anzing
(11) Forstinning
(12) Hohenlinden B12
Rest area Holzfeld/Auwiesen
(13) Pastetten
Isentalbrücke 590 m
(14) Lengdorf
Lappachtalbrücke 280 m
(15) Dorfen B15
Rest area
Goldachtalbrücke
Rimbachtalbrücke
Talbrücke Ornauer Bach
(16) Obertaufkirchen
(17) Heldenstein
Tunnel Einhausug Wimpasing 680 m
(18) Waldkraiburg/Ampfing
(19) Mühldorf-West
(20) Mühldorf-Nord B299
(21) Töging
Aubachbrücke 80 m
(22) Altötting B299
Isenbrücke 120 m
(23) Neuötting B588
Innbrücke 470 m
(24) Neuötting-Ost
Alzbrücke 90 m
(25) Burghausen B20
End of the motorway

B12
Innbrücke 330 m
Türkenbackbrück 110 m
Stammham B20
parking area
Braunau-Neustadt B148 (Austria)
Simbach-West
Erlach
Mühlau
parking area
Diversion
Ering-Nord local diversion
Diversion
Ering-Ost local diversion
Diversion
Ering/Müinchham local diversion
Diversion
Malching local diversion

B12
End of the motorway
(-) provisional connection
(30) Malching
(-) provisional connection

Tunnel Einhausung 450 m (planned)
Kirchham (planned)
Talbrücke Kößlarner Bach 220 m (planned)
Pocking-West / Bad Füssing (planned)
(planned)
Pocking-Mitte (planned)
Tunnel Wilddurchlass 50 m (planned)
Pocking-Nord / Ruhstorf (planned)
Kreuz Pocking (planned) A3

E56 B512

gollark: A clear hallucination.
gollark: They are gods, they can MAKE food with godness.
gollark: What a very sensible policy.
gollark: I know that for purposes only. How are these related anyway?
gollark: Also campanologist (bell-ringer) in English.


This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.