The Brandon Shores Generating Station is an electric generating station located on Fort Smallwood Road north of Orchard Beach in Anne Arundel County, Maryland, near Glen Burnie, and is operated by Raven Power Holdings, Inc. Brandon Shores consists of two Babcock & Wilcox coal-fired boilers and two General Electric steam turbines with a combined nominal generating capacity of 1370 MWe.[1] Unit 1 went into operation in May 1984 and Unit 2 in May 1991.[2]

Brandon Shores Generating Station
Brandon Shores Generating Station viewed from the south
CountryUnited States
LocationAnne Arundel County, Maryland
Coordinates39°10′53″N 76°32′16″W
StatusOperational
Commission dateUnit 1: May, 1984
Unit 2: May, 1991
Owner(s)Talen Energy
Thermal power station
Primary fuelBituminous coal
Cooling sourceChesapeake Bay
Power generation
Units operational2
Nameplate capacity1370 MWe
External links
Website
CommonsRelated media on Commons

The station shares a 483-acre (195 ha) site adjacent to the Patapsco River with the Herbert A. Wagner Generating Station. The Brandon Shores plant dominates the site with its 700-foot (210 m) exhaust and 400-foot (120 m) flue-gas desulfurization (FGD) system stacks.

Coal delivery

The Brandon Shores and Wagner Generating Stations consume approximately 4.8 million tons of coal annually.[2] Coal for both stations is delivered by barge. Although there is a railroad spur into the site, it is unused and would require improvements to restore it to an operational state.

Renovation

In order to meet Maryland requirements for reductions of nitrogen oxides, sulfur dioxide and mercury, the plant was substantially renovated between 2007 and 2010. A new 400 feet (120 m) twin FGD stack was built to replace the existing 700 feet (210 m) stacks, which have been capped and are inoperative. Flue gas from the boilers is routed through the emissions control system that sprays the exhaust with a limestone slurry and collects gypsum for use in wallboard and fly ash for use in concrete. The system uses treated municipal wastewater[3] from the Anne Arundel County Cox Creek wastewater treatment plant as the source of water for making the limestone slurry.[2]

2012 sale

The plant was originally constructed by a predecessor company of Constellation Energy, which was later purchased by Exelon in 2012. On August 9, 2012, Exelon announced that it had reached an agreement, subject to regulatory approvals, for the sale of the Charles P. Crane, Brandon Shores, and Herbert A. Wagner Generating Stations to Raven Power Holdings LLC, a newly formed portfolio company of Riverstone Holdings LLC, for approximately $400 million.[4] Exelon had committed to divest the plants as condition for regulatory approval of its merger with Constellation Energy to alleviate concerns regarding potential market power in the regional wholesale electricity market. The sale was completed on November 30, 2012.

Dispatch of electricity

The electrical output of Brandon Shores Generating Station is dispatched by the PJM Interconnection regional transmission organization.

gollark: ```osmarks@procyon ~> lsblkNAME MAJ:MIN RM SIZE RO TYPE MOUNTPOINTmmcblk0 179:0 0 7.3G 0 disk ├─mmcblk0p1 179:1 0 2M 0 part ├─mmcblk0p2 179:2 0 2M 0 part ├─mmcblk0p3 179:3 0 1M 0 part ├─mmcblk0p4 179:4 0 1M 0 part ├─mmcblk0p5 179:5 0 1M 0 part ├─mmcblk0p6 179:6 0 1M 0 part ├─mmcblk0p7 179:7 0 4M 0 part ├─mmcblk0p8 179:8 0 8M 0 part ├─mmcblk0p9 179:9 0 8M 0 part ├─mmcblk0p10 179:10 0 4M 0 part ├─mmcblk0p11 179:11 0 1M 0 part ├─mmcblk0p12 179:12 0 1M 0 part ├─mmcblk0p13 179:13 0 1M 0 part ├─mmcblk0p14 179:14 0 1M 0 part ├─mmcblk0p15 179:15 0 1M 0 part ├─mmcblk0p16 179:16 0 2M 0 part ├─mmcblk0p17 179:17 0 20M 0 part ├─mmcblk0p18 179:18 0 5M 0 part ├─mmcblk0p19 179:19 0 1M 0 part ├─mmcblk0p20 179:20 0 16M 0 part ├─mmcblk0p21 179:21 0 16M 0 part ├─mmcblk0p22 179:22 0 200M 0 part ├─mmcblk0p23 179:23 0 1.5G 0 part │ ├─mmcblk0p23p1 254:0 0 94M 0 part /boot│ └─mmcblk0p23p2 254:1 0 1.4G 0 part /├─mmcblk0p24 179:24 0 150M 0 part ├─mmcblk0p25 179:25 0 9M 0 part └─mmcblk0p26 179:26 0 5.4G 0 part mmcblk0boot0 179:32 0 4M 1 disk mmcblk0boot1 179:64 0 4M 1 disk mmcblk0rpmb 179:96 0 4M 0 disk ```android_partition_scheme_irl
gollark: The GTech™ ones, with infinite processing power but somewhat limited memory.
gollark: Oh, I mostly use an infinitely powerful computer.
gollark: Yes, I assume it's wine badness.
gollark: Hmm, under wine it just pagefaults, fun.

See also

References

  1. "Existing Electric Generating Units in the United States, 2006" (Excel). Energy Information Administration, U.S. Department of Energy. 2006. Retrieved 2008-07-14.
  2. "Environmental Review of Proposed Air Pollution Control Project at Brandon Shores" (PDF). Maryland Department of Natural Resources. February 5, 2007. Archived from the original (pdf) on March 7, 2013. Retrieved 2008-12-30.
  3. Peltier, Robert (2010). "Brandon Shores Generating Station, Pasadena, Maryland". Power. 154 (10): 30–32. ISSN 0032-5929.