Srisailam Dam

The Srisailam Dam is constructed across the Krishna River in Kurnool district, Andhra Pradesh near Srisailam temple town and is the 2nd largest capacity working hydroelectric station in the country.[4]

Srisailam Dam
Location of Srisailam Dam in Andhra Pradesh
LocationSri Sailam, Kurnool district, Andhra Pradesh, India
Coordinates16°05′13″N 78°53′50″E
PurposeHydroelectric, Irrigation & Water supply
Construction began1960
Opening date1981
Construction cost₹10 billion [1]
Owner(s)Government of Andhra Pradesh
Dam and spillways
Type of damGravity & Masonry dam
ImpoundsKrishna River
Height145.10 m (476 ft)[2][3]
Length512 m (1,680 ft)
Spillway capacity38369 cumecs
Reservoir
CreatesSrisailam Reservoir (Neelam Sanjeevareddy Sagar)
Total capacity216 Tmcft
Catchment area206,040 km2 (79,550 sq mi)
Surface area616 km2 (238 sq mi)
Power Station
Operator(s)APGENCO
Turbines6 × 150 MW (200,000 hp) reversible Francis-type (left bank)

plant_operator = APGENCO

7 × 110 MW (150,000 hp) Francis type (right bank)
Installed capacity1,670 MW (2,240,000 hp)

The dam was constructed in a deep gorge in the Nallamala Hills in between Kurnool and Mahabubnagar districts, 300 m (980 ft) above sea level. It is 512 m (1,680 ft) long, 145 metres (476 ft) maximum height and has 12 radial crest gates. It has a reservoir of 616 square kilometres (238 sq mi). Project has an estimated live capacity to hold 178.74 Tmcft at its full reservoir level of 885 feet (270 m) MSL. The minimum draw down level (MDDL) of the reservoir is at 705 feet (215 m) MSL from its river sluice gates and corresponding dead storage is 3.42 Tmcft.[5] The left bank underground power station houses 6 × 150 megawatts (200,000 hp) reversible Francis-pump turbines for pumped-storage operation (each Turbine can pump 200 cumecs) and the right bank semi under ground power station houses 7 × 110 megawatts (150,000 hp) Francis-turbine generators.

Tail pond dam /weir located 14 km downstream of Srisailam dam is under advanced stage of construction to hold the water released by the hydro turbines and later pump back into the Srisailam reservoir by operating the turbines in pump mode.[6] The weir portion got breached in November 2015 unable to withstand the normal water release from the hydro power stations.[7] Tail pond weir was completed during the year 2017 and pumping mode operation is being done even the downstream Nagarjuna Sagar reservoir water level is below 531.5 feet (162 m) MSL. The tail pond has nearly 1 tmcft live storage capacity.[8]

Srisailam Dam

Project history

Srisailam Dam Backwaters of Krishna River

The Srisailam project began in 1960, initially as a power project. After several delays, the main dam was finally completed twenty years later in 1980 July 26. In the meantime the project was converted into a multipurpose facility with a generating capacity of 770 megawatts (1,030,000 hp) by its second stage which was completed in 1987. The dam is to provide water for an estimated 2,000 square kilometres (770 sq mi). Under the right bank branch canal 790 square kilometres (310 sq mi) in Kurnool and Kadapa districts will have assured irrigation. From the initial modest estimate of 384.7 million for a power project the total cost of the multipurpose project was estimated to cross 10 billion in its enlarged form. The dam has alone cost 4.04 billion together with the installation of four generating sets of 110 MW each. The right bank branch canal is estimated to cost 4.49 billion and the initial investment of 1.4 billion has been provided by the World Bank. The projected cost-benefit ratio of the project has been worked out at 1:1.91 at 10% interest on capital outlay.. In 1998 a coffer dam was over topped by flooding. The power house required repairs and did not generate power for a year. On 2 October 2009, Srisailam dam experienced a record inflow which threatened the dam.[9]

Irrigation schemes

Srisailam right main canal (SRMC) is constructed with 44,000 cusecs capacity at Srisailam reservoir level of 269.22 metres (883 ft) MSL to feed Veligodu reservoir (16.95 tmcft), Brahmamsagar Reservoir (17.74 tmcft), Alaganoor reservoir (2.97 tmcft), Gorakallu reservoir (12.44 tmcft), Owk reservoir (4.15 tmcft), Gandikota Reservoir (26.86 tmcft), Mylavaram reservoir (9.98 tmcft), Somasila reservoir (78 tmcft) and Kandeleru reservoir (68 tmcft) with nearly 235 Tmcft total storage capacity.[10] This canal also supplies water to Telugu Ganga project which supplies Krishna river water to Chennai city for its drinking purpose.[11] This main canal by feeding water to K. C. Canal, Srisailam right bank canal, Telugu Ganga canal and Galeru Nagari canal irrigates vast area in Kurnool, Kadapa, Chittoor and Nellore districts.

Handri-Neeva lift canal by drawing water from the Srisailam reservoir, supplies drinking water in all the districts of Rayalaseema

Veligonda reservoir receives water by gravity through tunnels to irrigate lands in Nellore, Kadapa and Prakasam districts.

Kalwakurthy lift irrigation scheme by drawing water from the Srisailam reservoir, supplies irrigation water in Mahbubnagar and Nalgonda districts

Srisailam left bank canal receives water by gravity through tunnels to irrigate lands in Nalgonda district. Tunnel is not complete and water was never provided.

Dam Maintenance and Safety

Systematic Neglect and absence of diversion of funds is evident in maintenance of the dam and lack of any modernization attempts of the Powerhouse. The officers report a shortage of maintenance staff[12].

Safety concerns to the 2nd largest Hydroelectric project in the country have been raised over the years[13] [14]and have been assessed false subsequently[15]. In 2009, the dam, designed for a maximum flood of 19 lakh cusecs, endured a flood of 25.5 lakh cusecs. According to a survey conducted in summer of 2018, the scouring resulted in the formation of a huge pit in the apron downstream the dam. And a structure protecting the ‘toe’ and foundation of the main dam has weakened. Efforts are not yet made to repair and maintain the dam.[16]

Power generation optimization

At present the initial inflows into Srisailam reservoir are stored excessively without using for power generation. The flood water fills the remaining empty Srisailam reservoir quickly and most of the flood water overflows into downstream Nagarjunasagar reservoir without being used for power generation.[17] The endeavor shall be to fill the Nagarjunasagar reservoir fully with the uniform water released through the power generating units.

gollark: To what?
gollark: Ħ¡, not Ħi.
gollark: Ħ¡
gollark: Yes you do.
gollark: Not *just* factories, you need all the buildings in that list (with scale/density options) and more.

See also

References

  1. "Sri Sailam Dam cost". Andhraspider.com. 8 May 2007. Retrieved 6 January 2019.
  2. "India: National Register of Large Dams 2009" (PDF). Central Water Commission. Archived from the original (PDF) on 21 July 2011. Retrieved 10 July 2011.
  3. Jauhari, V.P. (2005). Sustaining river linking. New Delhi, India: Mittal Publications. p. 84. ISBN 817099991X.
  4. "Srisailam (N.S.R.S.P) Dam D00557". Retrieved 22 September 2015.
  5. "Neelam Sanjeeva Reddy Srisailam Project". Retrieved 22 September 2017.
  6. "Srisailam Tail pond Dam". Retrieved 22 December 2015.
  7. "Srisailam Tail pond Dam leaked". Retrieved 22 December 2015.
  8. "Srisailam dam tail pond level and storage capacity" (PDF). Retrieved 22 September 2015.
  9. Managing historic flood in the Krishna river basin in the year 2009
  10. "AP Reservoirs real time data". Retrieved 22 July 2018.
  11. "Telugu Ganga project". Retrieved 22 September 2015.
  12. Rao, G. Venkataramana (20 November 2019). "'Srisailam dam in need of urgent maintenance'". The Hindu. ISSN 0971-751X. Retrieved 23 July 2020.
  13. Rao, G. Venkataramana (16 November 2019). "Experts worried about safety of Srisailam dam". The Hindu. ISSN 0971-751X. Retrieved 22 July 2020.
  14. Pulipaka, AuthorBalu. "Srisailam dam safety under lens". Telangana Today. Retrieved 22 July 2020.
  15. Reporter, Staff (22 November 2019). "No threat to Srisailam dam, asserts Minister". The Hindu. ISSN 0971-751X. Retrieved 22 July 2020.
  16. Rao, G. Venkataramana (16 November 2019). "Experts worried about safety of Srisailam dam". The Hindu. ISSN 0971-751X. Retrieved 22 July 2020.
  17. Optimisation of power generation from Srisailam Hydroelectric Power Station
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.