Kakrapar Atomic Power Station

Kakrapar Atomic Power Station is a nuclear power station in India, which lies in the proximity of surat and Tapi in the state of Gujarat.

Kakrapar Atomic Power Station
CountryIndia
Coordinates21°14′19″N 73°21′00″E
StatusOperational
Construction began1984
Commission date6 May 1993
Operator(s)Nuclear Power Corporation of India
Nuclear power station
Reactor typePHWR
Power generation
Units operational2 × 220 MW
Units under const.2 × 700 MW
Nameplate capacity440 MW
Capacity factor60.9% (average)
Annual net output3.72 TWh
External links
Website www.npcil.nic.in/main/ProjectOperationDisplay.aspx?ReactorID=86 

Phase I

Phase I consists of two 220 MW pressurised water reactor with heavy water as moderator (PHWR). KAPS-1 went critical on 3 September 1992 and began commercial electricity production a few months later on 6 May 1993. KAPS-2 went critical on 8 January 1995 and began commercial production on 1 September 1995. In January 2003, CANDU Owners Group (COG) declared KAPS as the best performing pressurised heavy water reactor.[1]

KAPS-2 was shut down after a coolant channel leak in July 2015 and a similar issue forced the shutdown of KAPS-1 in March 2016. After a replacement of coolant channels and feeder tubes, KAPS-2 attained criticality in September 2018. Maintenance on KAPS-1 was completed ahead of schedule and was brought to operation on 19 May 2019.[2]

The construction costs were originally estimated to be ₹382.52 crore; the plant was finally finished at a price of ₹1,335 crore.

Phase II

In 2007 the Indian government approved outline plans to build two indigenously-designed IPHWR-700 reactors, with two sister reactors a little later at Rajasthan Atomic Power Station. In 2009 approval was confirmed, and site preparation was completed by August 2010. First concrete for Kakrapar 3 and 4 was in November 2010 and March 2011 respectively with operation originally expected by early and late 2018 respectively.[3][4]

The project over-ran largely due to tuning of the IPHWR-700 design and slow delivery of supplies.[3] Operation is now expected by October 2020 and September 2021 respectively. Unit 3 achieved first criticality on 22 July 2020.[4]

Units

UnitTypeGross MWConstruction startOperation startNotes
Phase I
Kakrapar 1PHWR2201 December 19846 May 1993 [5]
Kakrapar 2PHWR2201 April 19851 September 1995 [6]
Phase II
Kakrapar 3IPHWR-70070022 November 20102020[7] [8]
Kakrapar 4IPHWR-700700March 20112021 [4]
PHWR under Construction at Kakrapar Gujarat India

Incidents

  • 1998 KAPS-1 was switched off because of a leakage in the cooling loop for 66 days.
  • 10 March 2004 the (at the time of) supply for the control rods were irreparably damaged during maintenance work. In response, poisons were added to the system and the reactor was shut off.
  • On 22 August 2006 it was reported by village inhabitants the area around the power station had been penetrated. A search by the police did not result in any findings.
  • On 11 March 2016, KAPS-1 automatically shut down due to a leak of heavy coolant water, leaving both reactors non-operational.[9][10] The leak was plugged ten days later.[11] Corrosion and cracks were found on the coolant channel and similar corrosion spots were found in KAPS-2 which had been non-operational since July 2015 after a coolant channel leak.[12][13] KAPS-2 attained criticality on 17 September 2018 after a replacement of its coolant channels and feeder tubes. KAPS-1 became operational ahead of schedule on 19 May 2019[2]
gollark: I know that that's not really the right definition and that advantages like hiring 1259012758 very smart people to build models and HFT still work, but I think it's *basically* true.
gollark: I feel like we've argued about this before and you didn't say anything very convincing.
gollark: If they could do consistently *worse* than the market than their thing would actually be worth a lot.
gollark: The positions of the planets are very public.
gollark: I forgot the accurate statement but basically just "you can't beat the market on publicly available information".

See also

References

  1. Kurian, Vinson (26 March 2003). "Indian N-reactors set new global benchmark". The Hindu Business Line. Retrieved 16 February 2017.
  2. "KAPS-1 connected to grid" (PDF). NPCIL. Retrieved 24 May 2019.
  3. "Bright prospects for India's future fleet". Nuclear Engineering International. 16 August 2017. Retrieved 23 July 2020.
  4. "Kakrapar 3 achieves first criticality". World Nuclear News. 22 July 2020. Retrieved 23 July 2020.
  5. "Nuclear Power Reactor Details - KAKRAPAR-1". Power Reactor Information System. International Atomic Energy Agency (IAEA). 23 November 2010. Retrieved 23 November 2010.
  6. "Nuclear Power Reactor Details - KAKRAPAR-2". PRIS. (IAEA). 23 November 2010. Retrieved 23 November 2010.
  7. https://indianexpress.com/article/explained/kakrapar-atomic-power-project-third-unit-achieves-first-criticality-india-nuclear-mission-6518946/
  8. http://loksabhaph.nic.in/Questions/QResult15.aspx?qref=4238&lsno=17
  9. Harikumar, S. (11 March 2016). "Shutdown of Unit-1 of KAPS Nuclear Power Plant following an incident leakage from Coolant System" (PDF). aerb.gov.in. Retrieved 16 February 2017.
  10. "More than 100 hours later, Kakrapar nuclear leak not fixed". 16 March 2016. Retrieved 18 April 2016 via Rediff.com.
  11. "Kakrapar Nuclear Reactors to Get New Coolant Channels". News18. Indo-Asian News Service. 1 February 2017.
  12. Fernandes, Snehal (19 March 2017). "A year after KAPS-1 heavy water leak, corrosion spots found: AERB". Hindustan Times.
  13. Balan, Premal (11 March 2017). "Ahmedabad: No power from Kakrapar plant for at least a year". The Times of India.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.