Hunterston A nuclear power station

Hunterston A nuclear power station was a Magnox power station located at Hunterston in Ayrshire, Scotland, adjacent to Hunterston B and is currently being decommissioned.

Hunterston A nuclear power station
The Hunterston A Magnox reactor buildings
CountryScotland
LocationNorth Ayrshire
Coordinates55°43′20″N 4°53′24″W
StatusDecommissioned
Construction began1957 - 1964
Commission date1964
Decommission date31 March 1990
Owner(s)SSEB
(1964-1990)
Scottish Nuclear
(1990-1996)
Magnox Electric
(1996-2005)
Nuclear Decommissioning Authority
(2005-present)
Operator(s)
Nuclear power station
Reactor typeMagnox
Reactor supplierGEC
Power generation
Units operationalSix 60 MW C. A. Parsons and Company
Units decommissioned2 x 150 MWe
External links
Websitenda.gov.uk/sites/hunterstona

History

Construction of the power station, which was undertaken by a consortium of GEC and Simon Carves,[1] began in 1957 and the facility was opened by Queen Elizabeth, the Queen Mother on 22 September 1964. Hunterston A had two Magnox reactors capable of generating 180 MWe each.[2] The reactors were supplied by GEC and the turbines by C.A. Parsons & Company.[2] The main civil engineering contractor was Mowlem.[2]

The Magnox reactors used natural uranium fuel (in magnox alloy 'cans') within a graphite core, and were cooled by carbon dioxide gas. Each reactor, which consisted of more than 3000 fuel channels, was enclosed in a steel pressure vessel. Eight boilers, known as Steam Raising Units, were located around each reactor. An outer building, mainly of glass, provided weather protection. The six 60 MW generators were located in an adjoining turbine hall.

The Hunterston A reactor design was unique in that each was raised up to a height of over 10 metres to enable refuelling to take place from underneath. This meant that gravity assisted the process of used fuel removal, and avoided the need for lifting machinery to be inserted into the active core for on-load refuelling.[3]

In later years of operation the reactors were derated to 150 MWe each. This was to slow the corrosion of steel components which, at the original higher temperatures, could have compromised reactor life.

The construction of Cruachan Power Station, a pumped-storage hydroelectric dam and power station, was linked to that of Hunterston A, to store its surplus night-time generated electricity.[4]

Shutdown and decommissioning

Hunterston A closed in 1990, with Reactor 2 shutting down on 31 December 1989 and Reactor 1 on 31 March 1990, immediately prior to the splitting of SSEB into Scottish Power and Scottish Nuclear.

Defuelling, removal of most buildings and a care and maintenance phase is planned until 2072. Demolition of reactor buildings and final site clearance is planned for 2072 to 2080 [5]

Ownership

From construction to closure in March 1990, the power station was owned and operated by South of Scotland Electricity Board. As part of the privatisation of the Scottish electricity generators, Hunterston A was transferred, with the adjacent Hunterston B, to the new state owned company Scottish Nuclear. In 1996 upon privatisation of the UK nuclear industry, the site was transferred, this time on its own to the state-owned Magnox Electric. In April 2005, the NDA took over ownership and place the site with its Site Licence company, Magnox North Ltd.

gollark: I kind of want a copy of this malware now.
gollark: Fun fact: The S in IoT stands for "security".
gollark: It really tells you something about their quality control.
gollark: If someone *is* installing malware, they might eventually install *functional* malware.
gollark: Did someone ping me?

See also

References

  1. UK Consortia NEI Magazine, August 2009
  2. Nuclear Power Plants in the UK - Scotland and Wales Archived 2009-07-19 at the Portuguese Web Archive
  3. Magnox North: site history
  4. James Freeman (19 May 2003). "Mountain of power to get £18.5m facelift". The Herald. Retrieved 26 April 2014.
  5. "The 2010 UK Radioactive Waste Inventory: Main Report" (PDF). Nuclear Decommissioning Agency/Department of Energy & Climate Change. February 2011. Archived from the original (PDF) on 25 March 2012. Retrieved 22 May 2012.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.