Satpura Thermal Power Station
Satpura Thermal Power Plant is located at Sarni town near Ghoradongri Railway station in Betul district of Madhya Pradesh, India. The power plant is one of the coal based power plants of MPPGCL
Satpura Thermal Power Station | |
---|---|
Location of Satpura Thermal Power Station | |
Country | India |
Location | Sarni, Betul, Madhya Pradesh |
Coordinates | 22°6′40″N 78°10′24″E |
Status | Operational |
Commission date | 1967 |
Operator(s) | MPPGCL |
Thermal power station | |
Primary fuel | Coal |
Tertiary fuel | FURNACE OIL/HSD |
Power generation | |
Units operational | 6 |
Nameplate capacity | 1330 MW |
www.mppgenco.nic.in |
Power plant
Satpura Thermal Power Station has an installed capacity of 1330 MW. The First unit was commissioned in October 1967.[1] The Water for the plant has been procured from nearby Tawa Dam Lake area, which spread in 2,893 acres (11.71 km2). The coal for the plant has been procured by Rail/Road/Belt from Western Coal Fields. There are two more units of 250 MW are in stps.
Installed capacity
Stage | Unit Number | Installed Capacity (MW) | Date of Commissioning | Status | TG set Provider[2] | Boiler Provider[3] |
---|---|---|---|---|---|---|
First | 1 | 62.5 | 1967 October | Decommissioned | GE, USA | The Babcock & Wilcox Company (B&W), USA |
First | 2 | 62.5 | 1968 March | Decommissioned 2013 December | GE, USA | The Babcock & Wilcox Company (B&W), USA |
First | 3 | 62.5 | 1968 May | Decommissioned 2012 October | GE, USA | The Babcock & Wilcox Company (B&W), USA |
First | 4 | 62.5 | 1968 July | Decommissioned 2013 December | GE, USA | The Babcock & Wilcox Company (B&W), USA |
First | 5 | 62.5 | 1970 April | Decommissioned 2013 February | GE, USA | The Babcock & Wilcox Company (B&W), USA |
Second | 6 | 200 | 1979 July | Running | BHEL, India | BHEL, India |
Second | 7 | 210 | 1980 September | Running | BHEL, India | BHEL, India |
THIRD | 8 | 210 | 1983 January | Running | BHEL, India | BHEL, India |
THIRD | 9 | 210 | 1984 February | Running | BHEL, India | BHEL, India |
FOURTH | 10 | 250 | 2013 August | Running | BHEL, India | BHEL, India |
FOURTH | 11 | 250 | 2014 March | Running | BHEL, India | BHEL, India |
FIFTH | 12 | 660 | BY 2020 | PROPOSED | BHEL, INDIA | BHEL, INDIA |
gollark: Besides, no libraries would use them.
gollark: As I said, C's metaprogramming isn't good enough to patch shiny new features in in a pleasant way.
gollark: I don't think C has those? Or at least nice ones.
gollark: It's not good. People don't consistently get it right and it's annoying.
gollark: Yes, it's Turing-complete*, but that doesn't mean I want to write```cint32_t_iterator_of_some_kind thing = make_iterator();while (int32_t x = get_element(thing)) { // do thing with x}free_iterator(thing)```* not actually Turing-complete, due to weird spec quirks
See also
References
- "Satpura Thermal Power Plant". M.P.Power Generation Company Limited.
- http://mppgenco.nic.in/stps-sarni.htm#
- http://mppgenco.nic.in/stps-sarni.htm#
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.