The Rosewood Line (Line 11) is a proposed line of the Delhi Metro Is scheduled to be completed in 2025.

Rosewood Line
रोज़वुड (Line 11)
Overview
TypeRapid transit
SystemDelhi Metro
StatusUnderconstruction
LocaleDelhi
TerminiTughlakabad
Terminal 1-IGI Airport
Stations16 , Elevated: 8, Underground: 8
Operation
Opened2024 (Phase 4)
OwnerDelhi Metro
Operator(s)Delhi Metro Rail Corporation
CharacterUnderground and Elevated
Rolling stockHyundai-ROTEM Standard gauge
Technical
Line length28.3 km
Track length28.3 km
Track gaugeHyundai-ROTEM Standard gauge
Electrification25 kV, 50 Hz AC through overhead catenary

This 20.20 kms Line Section consist total 16 stations (Tughlakabad - Terminal 1-IGI Airport metro station) including 8 Elevated & 8 Underground level. This Line is the part of Phase 4 Project of Delhi Metro.

Stations

The stations proposed for the Rosewood Line are:[1]

Purple Line
No. Station Name Phase Opening Interchange

Connection

Station Layout Platform Level Type Depot Connection Depot Layout
EnglishHindi
1 Terminal 1-IGI Airport metro station टर्मिनल 1 इन्दिरा गाँधी अंतर्राष्ट्रीय हवाई अड्डा 4 2024  Magenta Line 

 IGI Airport   Feeder Bus 

Underground Island None None
2 Delhi Aerocity दिल्ली एयरोसिटी 4 2024  Orange Line 

 IGI Airport   Feeder Bus 

Underground Island None None
3 Mahipalpur महिपालपुर 4 2024  Feeder Bus  Elevated Side None None
4 Vasant Kunj वसंत कुंज 4 2024  Feeder Bus  Elevated Side Vasant Kunj Depot At Grade
5 Masudpur मसूदपुर 4 2024  Feeder Bus  Elevated Side None None
6 Kishangarh Sanjay Van किशनगढ़ संजय वन 4 2024  Feeder Bus  Elevated Side None None
7 Mehrauli महरौली 4 2024  Bus Terminal  Underground Island None None
8 Lado Sarai लाडो सरांय 4 2024  Feeder Bus  Underground Island None None
9 Saket साकेत 4 2024  Yellow Line   Feeder Bus  Underground Island None None
10 Saket G Block साकेत जी ब्लॉक 4 2024  Bus Terminal  Elevated Side None None
11 Ambedkar Nagar अम्बेडकर नगर 4 2024  Bus Terminal  Elevated Side None None
12 Khanpur खानपुर 4 2024  Feeder Bus  Elevated Side None None
13 Sangam Viharसंगम विहार 4 2024  Feeder Bus  Elevated Side None None
14 Tughlakabad Fort तुगलकाबाद किला 4 2024  Feeder Bus  Underground Island None None
15 Tughlakabad Railway Colonyतुगलकाबाद रेलवे कॉलोनी 4 2024  Bus Terminal  Underground Island None None
16 Tughlakabad तुगलकाबाद 4 2024  Violet Line   Indian Railways 

 Bus Terminal 

Underground Island None None

Train Info

# Rosewood Line
1 Rakes Hyundai Rotem BEML
2 Train Length 9
3 Train Gauge 4 ft 8 12 in (1,435 mm) Standard Gauge
4 Electrification 25 kV, 50 Hz AC through Overhead Catenary

OHE

5 Train's Maximum Speed 100 Km/hr
6 Train Operation Delhi Metro
gollark: I think that technically makes it not a *regular* regular expression.
gollark: My thing works by building a weirdly structured finite-state machine which matches permutations of "regex", then converting it to a different flat one usable by the `greenery` library, then using it to very slowly convert that into a regex.
gollark: I made a regex which matches all anagrams of regex: `e(e(g(rx|xr)|r(gx|xg)|x(gr|rg))|g(e(rx|xr)|r(ex|xe)|x(er|re))|r(e(gx|xg)|g(ex|xe)|x(eg|ge))|x(e(gr|rg)|g(er|re)|r(eg|ge)))|g(e(e(rx|xr)|r(ex|xe)|x(er|re))|r(e(ex|xe)|xe{2})|x(e(er|re)|re{2}))|r(e(e(gx|xg)|g(ex|xe)|x(eg|ge))|g(e(ex|xe)|xe{2})|x(e(eg|ge)|ge{2}))|x(e(e(gr|rg)|g(er|re)|r(eg|ge))|g(e(er|re)|re{2})|r(e(eg|ge)|ge{2}))`.
gollark: Depends on the database you're using and what the driver code does. In general no.
gollark: ... what?

References

  1. "Metro Network Phase I, II, III & NCR" (pdf). Delhi Metro Rail Corporation Ltd (DMRC). February 2015. Retrieved 28 June 2015.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.