Batang Ai Dam
The Batang Ai Dam is a concrete-face rock-fill dam in Batang Ai National Park in Sarawak, Malaysia. The power station comprises four 25 MW turbines, totalling the installed capacity to 100 MW. The station is operated by Sarawak Electricity Supply Corporation. Preparations for the dam began as early as 1975, before the design was published in 1977. Construction started 1982 with the river diversion work and the last turbine completed in 1985. The Batang Ai project, a relatively modest dam financed by the Asian Development Bank, caused the displacement of approximately 3,000 people from 26 longhouses. (These people have since been accommodated in the Batang Ai Resettlement Scheme to cultivate cocoa and rubber but the programme has not been successful.
Batang Ai Dam | |
---|---|
Location of Batang Ai Dam in Malaysia | |
Coordinates | 01°08′50″N 111°52′26″E |
Construction began | 1982 |
Opening date | 1985 |
Dam and spillways | |
Impounds | Batang Ai River |
Height | 85 m (279 ft) |
Length | 810 m (2,660 ft) |
Spillway capacity | 2,438 m3/s (86,097 cu ft/s) |
Reservoir | |
Creates | Batang Ai Reservoir |
Total capacity | 2,870,000,000 m3 (2,326,747 acre⋅ft) |
Inactive capacity | 1,630,000,000 m3 (1,321,463 acre⋅ft)[1] |
Catchment area | 1,200 km2 (460 sq mi) |
Surface area | 85 km2 (33 sq mi) |
Power Station | |
Operator(s) | Sarawak Energy |
Turbines | 4 × 25 MW Francis-type[2] |
Installed capacity | 100 MW |
References
- "Hydroelectric Power Dams in Sarawak". Sarawak Integrated Water Resources Master Management Plan. Archived from the original on 2012-07-03. Retrieved 7 May 2012.
- "Batang Ai Dam Hydroelectric Power Plant". Global Energy Observatory. Retrieved 7 May 2012.
Notes
- Economic Panning Unit (1996), Bakun – Green Energy For The Future, Kuala Lumpur, Malaysia: Percetakan Nasional Bhd. Page 14 Table 2-1 Batang Ai Dam.
- Kaur, Amarhit. "A History of Forestry in Sarawak." Modern Asian Studies 32.1 (1998): 117–47.