21st-century modernisation of the Great Western main line

Network Rail plans to spend £5 billion on modernising the Great Western main line, its South Wales branch and other associated lines. The modernisation plans were announced at separate times but their development time-scales overlap in the 2010s. The work includes electrification, resignalling, new rolling stock and station upgrades. According to Network Rail, the modernisation started in June 2010 and was due to end in 2017.[1] As of December 2019, electrification was complete as far west as Cardiff Central, and also from Reading to Newbury.

The station at Goring & Streatley with the new footbridge and electrification in progress

The project has been subject to repeated delays.[2] In November 2016 the government announced that several major elements of the electrification programme would be indefinitely deferred because costs had tripled. The five sections that are delayed are:[2][3]

  • Oxford to Didcot Parkway
  • Bristol Parkway to Bristol Temple Meads
  • Thingley Junction, near Chippenham, to Bath Spa and Bristol Temple Meads
  • Thames Valley branches to Henley and Windsor[4][5]
  • Swansea to Cardiff.[6]

Under the Intercity Express Programme (IEP), 21 electric Class 800 trains were ordered as replacements for the ageing InterCity 125 diesels. In May 2016, owing to delays in the modernisation project, it was confirmed that the new trains would be converted to 'bi-mode', meaning they can run on diesel fuel and electric overhead wire.[7]

Historical background

At the start of the 21st century, the Great Western main line and the Midland Main Line were the last of the major main line routes in the UK using diesel as the main source of locomotive power.[8] When the announcement was made in July 2009 to electrify the Great Western (along with the Liverpool-Manchester line), it represented the first big rail electrification project in the UK for 20 years.[9] The South Wales Main Line section of the GWML is set to be the first electrified cross-country railway line in Wales.

The plan to upgrade the rolling stock on the Great Western was included in the IEP announced in 2007, a Department for Transport (DfT) led initiative to replace the ageing fleet of InterCity 125 and InterCity 225 train sets then in use on much of the UK rail network.

Electrification

Electrification work at Cardiff Central on the South Wales Main Line

Status

Passenger timetables introduced electric running from Paddington to Didcot in January 2018,[10] and to Swindon and as far west as Bristol Parkway in January 2019. The same month saw electric services between Reading and Newbury.[11][12] Electric running to Newport commenced in December 2019 and to Cardiff in January 2020.[13] Work continues between Swindon and Chippenham.

Earlier work

Prior to 2009, the only electrified portion of the Great Western was between London Paddington and Airport Junction (west of Hayes and Harlington). This portion is equipped with a 25 kV AC overhead system which was implemented in 1997 in readiness for the Heathrow Express service commencing in early 1998. Electrification was extended from Airport Junction to Maidenhead under the Crossrail scheme.[14] Further electrification west of Maidenhead was announced by the DfT separately, though the work west of Airport Junction (to take Crossrail to Maidenhead) and west of Maidenhead is likely to be undertaken as one scheme.[15]

July 2009 announcement

The UK government first considered electrifying the Great Western between London Paddington and Bristol Temple Meads in a first phase, then electrifying the rest of the line between Swindon to Swansea at a later date. However, in July 2009, the Department of Transport under the then Labour Government (in the run-up to the 2010 general election), announced that there would be a £1bn programme to electrify the whole of the Great Western from London to Swansea as well as to Bristol Temple Meads.[16] The Labour government claimed that the investment would pay for itself over a 40-year period.[17][18]

The scheme announced by the government on 23 July 2009 stated that "work will begin immediately on the electrification of the Great Western main line between London, Reading, Oxford, Newbury, Bristol, Cardiff and Swansea, to be completed within eight years" (2016/2017).[14] The proposed electrified route included:[14]

  • the Great Western main line between London Paddington and Bristol Temple Meads via Swindon, Chippenham, and Bath Spa;
  • the South Wales Main Line from Swindon to Swansea via the Severn Tunnel;
  • the connecting line from Bristol Parkway to Bristol Temple Meads;
  • the section of the Cherwell Valley Line connecting Didcot Parkway with Oxford; and
  • the section of the Reading to Taunton line connecting Reading with Newbury.

Estimates showed that the Hitachi Super Express trains could reduce journey times from London Paddington to Swansea by 19 minutes.[14]

In an effort to minimise disruption during the electrification works, Network Rail developed new "factory engineering trains" to facilitate the process of installing overhead lines. There are three types of train: the first train will be used to install pylons, followed by a train to hang the wires and finally a train which will check the installation. The system was expected to be able to install 1.5 kilometres (0.93 mi) of electrification in an eight-hour shift.[19] The vehicles were supplied by German firm Windhoff.[20]

In its initial survey, Network Rail identified 113 structures – mainly bridges and tunnels – which required modernisation.[19] In subsequent surveys this increased to 137.[21] The largest structure, the Severn Tunnel, has good clearances and is relatively easy to electrify.[21]

Review and announcements after May 2010 general election

After the 2010 UK general election in May 2010, the Conservative–Liberal Democrat coalition placed all major government capital expenditure, including the Great Western electrification scheme on hold pending a return-on-investment review.[22] In November 2010, Transport Secretary Philip Hammond gave the go-ahead for the lines from Oxford via Didcot to London and Newbury to London to be electrified in the next six years. Extension from Didcot to Swindon, Bath, Bristol and to South Wales would be dependent on a further assessment due in 2011 of the costs and implementation requirements of the IEP.[23]

On 1 March 2011, Hammond announced that rail electrification from Didcot Parkway to Bristol Temple Meads and Cardiff Central would go ahead. The section linking Bristol Parkway and Bristol Temple Meads would also be electrified.[24]

In March 2012, Amey plc was awarded a £700 million contract to undertake the electrification works.[25]

In July 2012, the UK Government announced that the final portion of the Great Western from Cardiff to Swansea would be electrified.[26] In addition, as part of the Electric Spine project, the line between Reading and Basingstoke would also be electrified at 25 kV AC OHL. The overhead electrification of the branches to Henley, Marlow and Windsor were also added to the scope of the project.[27] However, the Marlow electrification has been postponed for the foreseeable future due to difficulties at Bourne End.

A High Output Plant System train

The new NR Series 1 overhead line equipment, designed and manufactured by Furrer+Frey, is a TSI compliant OLE design specified to allow multiple pantograph operation at 140 mph operation and is being installed using Amey plc's High Output Plant System (HOPS) and other conventional techniques. This is designed to allow Adjacent Line Operation (ALO) where works can be carried out while trains operate on adjacent tracks. The HOPS has five sections, each of which handles a different aspect of the installation – these can be coupled together to work as one unit, or separated to work independently. The train will be maintained at the High Output Operations Base (HOOB) in Swindon, on the site of former sidings. HOPS will mix and lay 30 m3 (1,100 cu ft) of concrete per night, and all equipment and personnel will arrive at the site on board.[28]

The HOPS train was operational by 2014, but had not reached full productivity due to teething problems.[29] By 2015, completion of the electrification project had been delayed, reportedly 1 year behind schedule, with completion expected in 2017. Costs of the electrification were reported to have tripled from an estimated £640M to £1.74bn.[30]

Reviews after May 2015 general election

2015

In June 2015, the International Railway Journal reported: "Britain's secretary of state for transport, Mr Patrick McLoughlin has asked Sir Peter Hendy to review Network Rail's 2014–2019 capital investment programme, known as CP5, and report back in the autumn".[31] The report stated that costs had tripled from the £874M original estimate to £2.8bn, and was £1.2bn higher than the estimate made a year ago.[32] The main part of the programme will go ahead as planned and should be delivered by March 2019, but the Cardiff to Swansea section will be delayed, to some time between 2019 and 2024.[33]

Revised dates for the completion of electrification work were published in early 2016, with electrification to Cardiff via Bristol Parkway, and the connection to Newbury planned by December 2018; the branch to Oxford from Didcot by June 2019; and the branch to Bristol Temple Meads from Wootton Bassett sometime between February 2019 and April 2020.[34]

2016

In November 2016, the government announced that electrification work on the sections from Oxford to Didcot Parkway, Bristol Parkway to Bristol Temple Meads, Thingley Junction (near Chippenham) to Bath Spa and Bristol Temple Meads, and branches lines to Henley and Windsor had been indefinitely deferred. For Oxford and Bristol, the deferral was due to imminent resignalling and remodelling of the existing track layout.[2]

2017

In July 2017, it was announced that the Cardiff-Swansea electrification project had been cancelled and that bi-mode trains would be used on the route.[35]

Resignalling

Example of an existing colour light signal at Bristol Temple Meads station

Current systems

The Great Western main line is currently equipped with colour light signalling common to the rest of the United Kingdom. At the time of the Ladbroke Grove rail crash (1999), the ATP (Automatic Train Protection) warning system was under trial. In response to that incident, it became a requirement for all First Great Western trains to be fitted with ATP.[36]

Future systems

When the Department for Transport first released the train specification for the new trains for the IEP in November 2007, it was stated that the Great Western main line would be upgraded to ETCS level 2 and ERTMS Level 2 in-cab signalling.[37] Some or all of the resignalling work will be carried out alongside the electrification work.[14] Signalling Solutions is to resignal the 12 miles from Paddington to West Drayton, including the Airport branch, as part of the Crossrail project.[38]

Future control

Thames Valley

In November 2008, Westinghouse (subsequently known as Invensys Rail, and now part of Siemens Rail Automation) was awarded a £20M contract for a 30-month programme of signalling enabling work.[39] Over a series of 12 commissionings, Invensys Rail will re-lock the existing Reading Station and Spur interlockings to three new WESTLOCK Interlocking units, re-control the remaining 18 relay interlockings and move signalling and telecommunications control from Reading Station to the new Thames Valley Signalling Centre at Didcot. The work culminates in a final commissioning, scheduled for 5 December 2010 and paves the way for future stages of the remodelling programme.[40]

The Thames valley signalling centre will eventually replace older signalling control in the entire English Western region. The London area is due to switch over at the end of 2011, followed by the old Slough PSB (Power Signal Box) area. Attention will then be given to abolishing Oxford, Swindon A, Bristol PSBs and the 1990s Swindon B IECC. This will be followed by the elimination of the 1980s PSBs at Westbury and Exeter, and the 1970s Plymouth PSB, the 1960s PSB at Gloucester as well as substantial semaphore signalling in Cornwall.[41]

South Wales

The first phase of a £400M, ten-year resignalling scheme in South Wales by Network Rail was carried out on a 22-mile (35 km) stretch between Port Talbot and Bridgend (termed Port Talbot East) in 2006 and 2007. The works provided a new turnback facility in both directions at Port Talbot Parkway if required.[42] The renewals replaced an old British Railways Western Region NX panel installation, dating from 1963. Railway technology has evolved somewhat since 1963 and the renewals will make some signalling facilities redundant.[43] Further signalling renewals are programmed for the Newport area (which will be implemented in two phases), Cardiff and Port Talbot West.[43]

The first phase of the Newport Area remodelling and resignalling began in 2009 and is expected to be completed by the end of 2010. The first phase covers the stretch of line between Patchway and Marshfield to the west of Newport.[44] A new South Wales Control Centre, built on the eastern end of Canton Depot in Cardiff, opened in Spring 2009. The signals implemented in Newport Area resignalling phase 1 will be the first to have control transferred to the South Wales Control Centre and once Phase 2 of the Newport Area resignalling is complete in 2011, the Newport signalbox will be closed. Control will pass to the South Wales Control Centre for other parts of the south Wales network as resignalling progresses.[44]

Rolling stock

Long distance inter-city services

The new Hitachi 800 bi-mode diesel-electric 125mph trains

Services from London Paddington to south west England and south Wales were served by Class 43 "InterCity 125" train sets, until 18 May 2019. The Intercity 125 trains were built between 1975 and 1982 and due to their age are to be replaced by new Hitachi Super Express train sets. The "Intercity 125" trains, now operating in shortened sets from Bristol and Cardiff, are one of the fastest trains on the Great Western, operating at 125 mph (201 km/h); the only faster services in the UK are on High Speed One from Eurostar and Southeastern with their Class 373s, Class 374s and Class 395s (London to Folkestone/Channel Tunnel), which operate at 186 mph (299 km/h), 186 mph (299 km/h) and 140 mph (225 km/h) respectively; the Class 390 'Pendolinos' on the West Coast Main Line and the InterCity 225 trains on the East Coast Main Line which are both capable of 140 mph (225 km/h), restricted only by line speed. The new Super Express trains will have a top speed of 125 mph (201 km/h) but will be capable of 140 mph (225 km/h) with minor modifications. The upgrading of the signalling on the Great Western to in-cab signalling is one pre-requisite to allow the new trains to run at the higher speed. In the 2010 GWML RUS, Network Rail stated that linespeeds in excess of 125 mph (201 km/h) west of Reading would be "reviewed in line with electrification and resignalling opportunities as ERTMS becomes deployed across the RUS area" after Control Period 4 (2014–2019).[45]

The initial new Hitachi Super Express trains planned for the Great Western inter-city services will be Class 800 electro-diesel bi-mode trains capable of running on lines with and without overhead wires. This is because of the deferment of the electrification project.[4] Despite the initial limit of 125 mph, the increased acceleration and operational efficiency are expected to decrease the journey time from London to Bristol Temple Meads by 22 minutes.[46] The new Super Express trains will bring an estimated 15% increased capacity during the morning peak hours.[14] The bi-mode trains will allow inter-city services to operate from London directly to locations in South Wales and southwest England, to which electrification does not extend under the current electrification proposals, like Carmarthen, Worcester, Gloucester, Cheltenham and the regions to the southwest of Bristol and Newbury. A portion of the fleet will be Class 802 trains, a more powerful variant of the Class 800 which will cope better with the gradients in Devon and Cornwall.[47]

New servicing facilities for the new fleet of Inter-City Express trains will be developed at the London North Pole Depot, the Filton Triangle rail depot in Stoke Gifford and at Maliphant sidings in Swansea.[48]

Thames Valley commuter services

Thames Valley commuter services from London Paddington to Reading and to Oxford are currently served by a combination of Class 165 "Network Turbo" and Class 166 "Network Express Turbo" three-car DMUs which are capable of operating at 90 mph (145 km/h).[49] These trains will be replaced by the new 45 Class 387 four-car 110 mph (177 km/h) trains currently used on Thameslink as an interim fleet. The Class 365 Networker trains, electric versions of the class 165/166s, operated currently by Govia Thameslink Railway will not now cascade from Great Northern to the Thames Valley as originally planned. The plans were dependent on sufficient Class 700 and Class 377s, replacing 365s and 387s on the Thameslink Great Northern network. The Network Turbo/Network Express Turbo trains would then be transferred for use for services in the Bristol and South West area (see Bristol Metro scheme below).[14][50]

Crossrail

The western section of Crossrail, to be known as the Elizabeth Line when opened in 2021, runs in part on the Great Western line. It will have 70 Class 345 trains which are formed of 9 carriages and can carry 1,500 passengers. These electric multiple units can achieve speeds of up to 90 mph (140 km/h) on the surface sections of the route and up to 60 mph (97 km/h) in the tunnels.[51] These trains are being built by Bombardier Transportation at their Derby Litchurch Lane Works.

Station renovation and enhancements

Several stations along the Great Western are undergoing redevelopment or have recently been upgraded to cope with growing passenger numbers and to ease rail traffic congestion.

Bristol Temple Meads

Bristol Temple Meads will be expanded into Digby Wyatt's 1870s extension to the original train shed,[52] built by Isambard Kingdom Brunel in 1840 as the terminus for the Great Western main line. This part of the 'Old Station' building is currently in use as a car park, but will be remodelled as terminating platforms for services to London Paddington.[53][54] To achieve rail access to the existing old platforms the Bristol power box, opened in 1970 and controlling 114 route miles of track, will need to be decommissioned and demolished.[55]

Bristol Parkway

Bristol Parkway had a new third platform (Platform 4) completed in 2007 to provide a new platform for trains departing to London and Birmingham and to make services more reliable between London and south Wales.[56] A new fourth platform has been built on the south side of the station.[57]

Reading

On 10 September 2008, Network Rail unveiled a £400M regeneration and reconfiguration of Reading station and surrounding track, incorporating an overpass to the west of the station; with freight and passenger trains able to transit from the Reading to Taunton Line and Reading to Basingstoke Line to the 'slow' lines via an underpass beneath the 'fast' lines, replacing the conventional at-grade crossing of the 'fast' lines via points, with the aim of alleviating delays due to slow-moving freight service passing through the station. By 2014 the total cost had risen to more than £800M.[58][59]

As well as the reconfiguration of the track, the terminal platforms for services to/from London Waterloo will be altered and the Cow Lane bridge under the tracks has been made two-way and now includes a cycle path. There will be improvements that will provide capacity for at least four extra trains in each direction every hour.[60]

London to Penzance trains were diverted to run from London Waterloo in December 2010 while a new bridge was put into position at Reading. This allowed additional tracks to be laid on the north side of the station.

The station received:

  • Five new platforms to ease overcrowding
  • A new foot-bridge between platforms
  • New escalators and lifts
  • A new northern entrance for the station, to serve the north side of the town and Caversham, and provide a link through the station between Reading town centre and the Thames.

These plans provide for the future Crossrail and possible Airtrack services at Reading station, building a railway that will be fit for at least the next thirty years. Also, the improvements will allow six new freight trains each day – this could take around 300 lorries a day off the roads.

While much of the work was carried out in 2010, trains to Devon and Cornwall ran from London Waterloo instead of Paddington, using the South Western Main Line via Basingstoke then the West of England Main Line and Wessex Main Lines. Trains to Bristol, South Wales and Cheltenham were diverted via the Chiltern Main Line (from London to Banbury) where they reversed and returned via Oxford to Didcot Parkway, South Oxfordshire to re-adopt the Great Western main line.

As of February 2015, the regeneration and modernisation of Reading Station is complete. The station now has 15 platforms, each serving their own specialist destination and purpose. The new platforms allow more frequent trains to run through Reading and allow more passengers to join longer trains. The entire Reading Redevelopment project will be completed by 2017.

Didcot Parkway

An improvement programme for the forecourt of Didcot Parkway began in September 2012 and ran for two years.[61] Features included:

  • Larger taxi rank with covered waiting area
  • Dedicated drop-off and pick-up area
  • Short-stay waiting bays
  • Disabled parking with step-free access
  • Secure cycle parking and motorcycle parking
  • Pedestrian piazza with seating and a glazed atrium and walkways
  • Extra bus stops with electronic real-time information
  • An improved East Car Park
  • Better security with CCTV and new lighting
  • New drainage to alleviate flooding
  • Completion of a cycle route serving the station

In 2018, a new multi-storey car park started to be built at Didcot Parkway, over the west long stay carpark. It should be completed in the autumn of 2018 providing 1800 spaces, to reflect the station's role as a Park and ride facility for the surrounding area.[62]

Newport

In 2009, an upgrade to Newport station was started to enable the station to cope with the expected passenger traffic associated with the 2010 Ryder Cup. A new passenger bridge and two new terminal buildings were constructed, with each platform being served by a lift. The new bridge is clad in ethylene tetrafluoroethylene (ETFE), the material which protects the Eden Project in Cornwall, despite which the roof initially gave problems with leaking.[63] The new development at the station includes a new multi-story car park and a new bus station will be developed outside, replacing the existing Newport bus station. The new north and south concourses opened on 13 September 2010.[64] The development was criticised by Rail Magazine columnist Barry Doe for being at the wrong end of the station, having a leaking roof, a lack of seating and generally poor design.[65]

Cardiff Central

Extra platform capacity at Cardiff Central will be introduced in the form of a new bay platform (platform 5)[66] for services between Cardiff and Maesteg along the GWML and one new through platform to the south of the station (platform 8) for the Cardiff urban services to cater for up to 16 trains per hour.[67] This will bring the number of platforms from 7 to 10. Redevelopment of Cardiff Central bus station outside the railway station commenced in 2008.

London Paddington

Between 2009 and 2015,[68] a new Crossrail station was to be built under London Paddington, serving as a connection to National Rail services and London Underground. Services were due to start in 2018.[69]

Network Rail had planned to demolish the arched section to the north-east of Paddington station, known as Span 4. Span 4 was an extension completed in 1916 and the roof had since become dangerous. An internal blanket was erected in the 1990s to protect people from falling glass. Span 4 was to be replaced by an office block over the rails but it was later decided that the structure would be restored.[70] The restoration of Span 4 took place between 2009 and 2010, and it re-opened in late 2011, looking notably brighter than the other three spans of the station.[71]

Port Talbot Parkway

Work on modernising Port Talbot Parkway station began in Autumn 2014. The old ticket office was demolished and a new footbridge built over the platforms. The footbridge will features a new ticket office and step free access to the platforms provided by lifts.[72]

Severn Tunnel Junction

Severn Tunnel Junction serves as a Park and Ride station for commuters from southern Monmouthshire to Bristol, Newport and Cardiff and there is a local action group – the Severn Tunnel Action Group (STAG) – who are campaigning to enhance the Junction's status as a transport hub for the southern Monmouthshire area.[73] As of January 2010, Network Rail have remodelled the tracks around the station, re-opened Platform 4 and modernised the parking and passenger facilities. The junction where the Gloucester to Newport Line joins the South Wales Main Line has been moved west of the station and now joins the main line with high-speed turnouts.[44]

Swansea

A £7.6M modernisation of Swansea station began in 2011 and was completed in June 2012.[74] The renovation work included enlargement of the concourse, cleaning of the front of the station with a new entrance, replacement of the partition wall between concourse and platforms with a glazed wall, a new café and more shops.[75]

Developments on associated lines

Crossrail

Construction of the Crossrail Portal at Royal Oak, the Great Western main line in the right, July 2011

Crossrail is a major rail scheme, under construction since 2009, to provide a new east-west railway connection under Central London. The western portion of the line will connect with the Great Western main line to the west of Paddington. With electrification of the Great Western extended westwards past Reading, the Department of Transport stated that Crossrail will terminate at Reading.[14] Some of the suburban services using the GWML into London Paddington will be transferred to Crossrail, which will free up capacity at the surface level station at Paddington.[14]

Connection to Heathrow Airport: Western Rail Access Programme

The Western Rail Access Programme is a scheme under development by the DfT, Network Rail and local authorities near Heathrow Airport to develop a direct rail link to the airport from the west. At present passengers travelling from the west of Airport Junction need to change trains at either Hayes and Harlington or Paddington which are to the east of the junction.[76][77] The proposed link will consist of a 5 km (3 mi) tunnel connecting a new junction between Langley and Iver stations to Terminal 5.[78] The new link will enable direct rail services between Reading and the airport.

With the confirmed electrification of the Great Western main line west of Airport Junction, local authorities in the Thames Valley identified a case to be made for introducing a service to Heathrow Airport from Reading via the Great Western, which would also serve Maidenhead and Slough.[14]

On 12 July 2012, Transport Secretary Justine Greening announced that a new rail link connecting Slough and Heathrow had been given the go-ahead and would be operational by 2021.[79]

MetroWest

MetroWest is a project to improve the rail services in Greater Bristol. It was first proposed at First Great Western's Stakeholder Event in March 2008. On 5 July 2012, the UK government and councils in and around Bristol agreed a City Deal whereby Bristol would have more funding for investment in the area. As a result of the City Deal, around £100M is expected to be invested in rail services under the Greater Bristol Metro scheme.[80] As part of the work, the Cross Country Route between Bristol Parkway and Bristol Temple Meads, commonly known as Filton Bank, will be expanded from two to four tracks.[81]

South Wales Metro

The South Wales Metro is a proposed integration of heavy rail (South Wales Main Line and Valley Lines) and development of light rail and bus-based public transport services and systems in South East Wales around the hub of Cardiff Central. The first phase was approved for development in October 2013.[82]

Swindon–Kemble redoubling

The Golden Valley Line serves as a diversionary line for several other lines in the area as well as serving its normal traffic. It will be a major diversionary route during the electrification of the Great Western main line. The line between Swindon and Kemble was reduced to a single track in 1968, limiting its capacity. In his March 2011 Budget, the Chancellor George Osborne approved a project to re-double this section of line, after several years of campaigning by local politicians.[83] The scheme was completed in August 2014.[84]

Further electrification in south Wales

During his announcement on Great Western electrification in March 2011, transport secretary Phillip Hammond stated that a good business case existed for the electrification of several south Wales commuter lines.[85] In July 2012, the UK Government announced that the south Wales commuter lines would be electrified. The lines which would be electrified are: all Valleys & Cardiff Local Routes, the Ebbw Valley Railway and the Maesteg Line.[86]

Controversies

On infrastructure

Some press reports state that passengers face six years of disruption from the electrification work. Over 100 bridges and tunnels require demolition or modification to accommodate the new overhead lines.[87]

The Goring Gap Railway Action Group (formed in March 2015) has complained that there has been insufficient consultation between Network Rail and residents of Goring-on-Thames about the visual impact of the overhead line supports.[88]

The footbridge at Pilning, South Gloucestershire, was demolished in 2016 because it was too low for electrification and the low passenger numbers did not justify a replacement.[89][90][91][92] The removal of the footbridge meant that the station's westbound platform was no longer accessible and thus was closed. Campaigners alleged that the removal amounted to a closure by stealth, with Network Rail apologising for not consulting residents or conforming to their code of best practice.[92][93][94] Geoff Marshall and Vicki Pipe visited Pilning in 2017 as part of their All the Stations project, attracting local media attention to the station's status.[95][96][97] There was subsequently a campaign for Pilning to receive the footbridge from Angel Road, following that station's closure in May 2019, but Network Rail stated that there was no financial justification for replacing the bridge.[98][99][100] Local rail group Friends of Suburban Bristol Railways claim that Network Rail saved £658,000 by removing the bridge, and that a replacement would cost in the region of £5m–7m.[101]

On rolling stock

The announcement of electrification of the Great Western led to the Government changing their plans to purchase a new fleet of diesel trains consisting of 202 locomotives and 1,300 train carriages.[102] The RMT union called for assurances that the plans will not have an adverse impact on jobs at the UK's only train maker Bombardier.[17]

In February 2010, it was announced that the IEP (for long distance express services) was suspended pending an independent report, with a decision on its viability to be given after the 2010 UK general election.[103][104][105][106] In 2012 the contract to provide Intercity Express bi-mode trains was awarded to Hitachi.

Details of progress with infrastructure

Although the enabling work on the trackbed, platforms and bridges is now complete, the installation of the electrification equipment has been delayed on the sections between Chippenham, Bath Spa and Bristol Temple Meads and between Bristol Temple Meads and Bristol Parkway.

SectorLocationTypeProgressCompletion/Target DateDetails
Chippenham
Chippenham-BathBathTrack LevelComplete2015To clear Sydney Gardens bridges, Bath.
Bath
Bath-BristolBellotts overbridgeBridgeComplete2017Demolished, rebuilt. AKA Somerset & Dorset Intersect Bridge. Part of the Two Tunnels cycleway.
Bath-BristolKeynsham overbridgeTrack LevelComplete2016 AprClearance.
Bristol Temple MeadsRoyal Mail ConveyorRemovalCompleteN/KClearance.
Filton Bank
Lawrence Hill-Filton Abbey WoodLawrence Hill-Filton Abbey WoodTrackbedCompleteN/KTrackbed preparation and addition of two tracks, returning Filton Bank to a 4-track route.
Lawrence Hill-Filton Abbey WoodStapleton Road Station FootbridgeFootbridgeCompleteN/KReplace low footbridge
Lawrence Hill-Filton Abbey WoodMidland Railway BridgeOverbridgeComplete2016 MayProtect public from cables. The higher bridge sides now have a mural.
Lawrence Hill-Filton Abbey WoodEaston Road BridgeOverbridgeCompleteN/KReplace footbridge
Lawrence Hill-Filton Abbey WoodBonnington Walk roadbridgeOverbridgeCompleteN/KProtect public from cables

See also

References

  1. Network Rail (June 2011). "Modernising the Great Western" (PDF). Archived from the original (PDF) on 13 April 2013. Retrieved 24 August 2016.CS1 maint: ref=harv (link)
  2. "Great Western electrification: Intercity line work 'deferred'". BBC News. 8 November 2016. Retrieved 10 November 2016.
  3. Paul Maynard (8 November 2016). "Written statement to Parliament, Rail update: rail investment in the Great Western route". gov.uk. Retrieved 8 November 2016.
  4. correspondent, Gwyn Topham Transport (21 October 2015). "Cost of Great Western mainline electrification project triples to £2.8bn" via www.theguardian.com.
  5. UK, DVV Media. "Great Western electrification projects deferred".
  6. Barry, Sion (20 July 2017). "UK Government scraps rail electrification plans to Swansea".
  7. Wilkinson, Michael (8 November 2016). "£3bn plans to electrify Great Western rail route to be delayed by six years". The Telegraph. Retrieved 28 December 2016.
  8. "UKPA: Rail electrification work announced".
  9. "£1.1bn investment to electrify rail". shares.ie. Archived from the original on 21 July 2011.
  10. "GWR Electrostar fleet enters service after electrification completed". Railway Technology Magazine. 2 January 2018. Retrieved 12 April 2019.
  11. Briginshaw, David (31 December 2018). "Great Western electric operation extends west". International Railway Journal. Retrieved 12 April 2019.
  12. "Electrification of Great Western Mainline to Swindon completed". BBC News: England. 1 November 2018. Retrieved 12 April 2019.
  13. "Major projects update: January". Network Rail. 30 January 2020. Retrieved 31 January 2020.
  14. "DfT Rail Electrification paper" (PDF). GOV.UK. July 2009. Archived from the original (PDF) on 16 May 2010.
  15. Network Rail 2011, pp. 9,13.
  16. "Chance to make public transport attractive". Wales Online. 12 August 2009.
  17. "£1bn plan to electrify rail line". BBC News. 23 July 2009.
  18. "Electrified rail network: the benefits". The Daily Telegraph. 23 July 2009.
  19. "'Minimum rail disruption' pledged". BBC News. 23 July 2009.
  20. "Windhoff to build Network Rail's electrification factory train". Railway Gazette International. 5 December 2011.
  21. Peter Dearman (28 April 2011). "Electrification: delivering the transformation". Global Rail News. Retrieved 10 March 2014.
  22. "Electrification must passcost test before go-ahead – Cameron". ThisIsBristol.co.uk. Archived from the original on 25 April 2010. Retrieved 1 April 2012.
  23. "Railways to get £8bn investment". BBC News. 25 November 2010. Archived from the original on 26 November 2010. Retrieved 1 April 2012.
  24. "Great Western electrification and IEP to go ahead". Cardiff News. 7 May 2011. Archived from the original on 20 August 2011. Retrieved 1 April 2012.
  25. "Amey awarded Great Western electrification contract". Railway Gazette International. 27 March 2012.
  26. Woodman, Peter (16 July 2012). "£4.2bn of new rail schemes unveiled". The Independent. Retrieved 1 December 2015.
  27. UK, DVV Media. "Electrification programme central to UK government's £9·4bn rail strategy".
  28. "HOPS & HOOB". Hub. Amey plc: 10. April 2014.
  29. "'Whenever you introduce a new technology, there is a learning curve'". www.railtechnologymagazine.com. 1 September 2014. Retrieved 8 April 2015.
  30. "Great Western electrification scheme 'one year behind schedule". BBC News. 24 February 2015. Retrieved 8 April 2015.
  31. Briginshaw, David (25 June 2015). "New Network Rail chairman to review troubled investment plan". International Railway Journal. Retrieved 1 December 2015.
  32. Tanya Powley, Gill Plimmer (25 November 2015). "Rail upgrade needs extra £2.5bn". Financial Times. Retrieved 14 December 2015.
  33. "Rail electrification between Cardiff and Swansea delayed". BBC. 25 November 2015. Retrieved 14 December 2015.
  34. "GWML electrification dates revealed", www.railtechnologymagazine.com, 22 January 2016
  35. "Sheffield, Swansea and Windermere electrification cancelled". Railway Gazette. 20 July 2017. Retrieved 21 July 2017.
  36. "Driver blamed for Southall crash". BBC News. 24 February 2000.
  37. "Network Rail Train Infrastructure Interface Specification" (PDF). Department for Transport. Archived from the original (PDF) on 22 November 2009. Retrieved 14 September 2009.
  38. Nigel Harris, ed. (1–14 June 2011). "GWML signalling contract signed". RAIL (671): 17.
  39. "World infrastructure market November 2008". Railway Gazette International. 20 November 2008.
  40. "Westinghouse awarded Reading Contract". Invensys Rail. 21 October 2008. Retrieved 1 April 2012.
  41. "NR rail control centres article". Rail News. Archived from the original on 24 July 2011.
  42. "Wales RUS 2008" (PDF). Network Rail. p. 55. Archived from the original (PDF) on 7 June 2011. Retrieved 14 September 2009.
  43. "South Wales – £400 Million of Signalling Investment". RailwayPeople.com.
  44. "Severn Tunnel Junction: From sleepy halt to centre of high-speed city connections". Rail News. 4 February 2009. Retrieved 1 December 2015.
  45. "Great Western Route Utilisation Strategy" (PDF). Network Rail. March 2010. Archived from the original (PDF) on 1 September 2012.
  46. "Government gives green light for more state-of-the-art intercity trains - GOV.UK". www.gov.uk.
  47. "Vision of the future arrives at Paddington to celebrate the Great Western Railway' 175th anniversary - Rail.co.uk". www.rail.co.uk.
  48. "Hitachi Super Express Trains - Railway Technology".
  49. "Inter-city electrification planning to start immediately". Railway Gazette International. 23 July 2009.
  50. "Britain's Transport Infrastructure – Rail Electrification" (PDF). Department for Transport. Archived from the original (PDF) on 23 January 2017.
  51. "Crossrail Rolling Stock". Crossrail. February 2012. Retrieved 12 April 2018.
  52. "Temple Meads (old) station". Engineering Timelines. Retrieved 1 April 2012.
  53. "Brunel's Passenger Shed to be used for Bristol to London electric line". This is Bristol. 29 March 2012. Archived from the original on 31 March 2012. Retrieved 1 April 2012.
  54. "Bristol museum could revert to rail platform". BBC. 28 March 2012. Retrieved 1 April 2012.
  55. "Bristol Railway Archive, Bristol Powerbox". Bristol Railway Archive. Retrieved 9 May 2012.
  56. "Bristol Parkway Platform 4". Network Rail. Archived from the original on 15 December 2007. Retrieved 1 April 2012.
  57. "Network Rail Route Plans 2009: Route 13 – Great Western Main Line" (pdf). networkrail.co.uk. Retrieved 1 April 2012.
  58. "Station's £400m revamp unveiled". BBC News Berkshire. Retrieved 1 April 2012.
  59. "Network Rail - Page not found". www.networkrail.co.uk.
  60. "Reading station area redevelopment". Network Rail.
  61. "Didcot Station - Latest Developments - South Oxfordshire District Council". Southoxon.gov.uk. Retrieved 2 July 2013.
  62. "Great Western Rail Franchise: Public Consultation" (PDF). Department for Transport. November 2017. p. 12. Retrieved 12 April 2018.
  63. Clark, Rhodri (July 2011). "Newport station roof leaks". Modern Railways. Ian Allan Publishing: 12.
  64. "'Lasting benefits' from £22m Newport station upgrade". Archived from the original on 17 September 2010. Retrieved 1 April 2012.
  65. Doe, Barry (4 May 2011). "The Fare Dealer". RAIL. Bauer Media (668): 51.
  66. Wales Route Utilisation Strategy Archived 7 June 2011 at the Wayback Machine Page 91: an additional (bay) platform at Cardiff Central for Maesteg/GWML services, notionally Platform 5
  67. Wales Route Utilisation Strategy Archived 7 June 2011 at the Wayback Machine Page 91: creation of four through platforms for Valleys services at Queen Street and Cardiff Central stations, to cater for up to 16 trains per hour capability through the central corridor
  68. "Orders of the Day — Crossrail Bill". TheyWorkForYou.com. 19 July 2005. Retrieved 1 April 2012.
  69. "London Crossrail gets the go-ahead". Railway Gazette International. 5 October 2007.
  70. "Paddington Span Four saved". Sapling.info. Retrieved 1 April 2012.
  71. "Paddington – Station roof restoration project". Network Rail. 27 February 2010. Archived from the original on 19 November 2009. Retrieved 1 April 2012.
  72. "Port Talbot Parkway (PTA)". National Rail Enquiries. 19 July 2017. Retrieved 19 July 2017.
  73. "STAG – Severn Tunnel Action Group". saveseverntunnel.co.uk. Archived from the original on 24 February 2012. Retrieved 1 April 2012.
  74. "UK opens upgraded Swansea railway station - Railway Technology". 12 June 2012.
  75. "Transformation of Swansea station unveiled" (Press release). Network Rail. 8 February 2010. Archived from the original on 14 March 2012. Retrieved 1 April 2012.
  76. "Latest updates – Network Rail". www.networkrail.co.uk.
  77. (www.waters-creative.co.uk), Waters Creative Ltd. "WESTERN RAIL LINK TO HEATHROW".
  78. "Underground link for direct Heathrow access - TunnelTalk". www.tunneltalk.com.
  79. "£500m Heathrow link to cut times on Great Western line". BBC. 12 July 2012. Retrieved 13 July 2012.
  80. Ribbeck, Michael (6 July 2012). "£100 million Bristol Metro train network by 2016". The Post, Bristol. Northcliffe Media. Archived from the original on 8 July 2012. Retrieved 6 July 2012.
  81. "Green light for long-awaited rail improvements". Bristol Evening Post. Northcliffe Media. 17 July 2012. Archived from the original on 26 September 2013. Retrieved 18 July 2012.
  82. "Plans show the potential of metro network". ITV Wales. 11 October 2013. Retrieved 11 November 2013.
  83. "Chancellor approves Kemble to Swindon railway upgrade". BBC News Gloucestershire. 23 March 2011. Retrieved 1 April 2012.
  84. "£45m rail doubling from Kemble completed". Wiltshire Gazette & Herald. 27 August 2014. Retrieved 27 August 2014.
  85. "Intercity Express and Rail Electrification". Department for Transport. 1 March 2011. Retrieved 1 December 2015.
  86. "Rail electrification to Swansea and south Wales valleys welcomed". BBC News. 16 July 2012. Retrieved 1 December 2015.
  87. "Six years of disruption under £1bn upgrade of Great Western Mainline". Times Online.
  88. "About the Railway Action Group (RAG)". Save the Goring Gap. Retrieved 1 December 2015.
  89. Sims, Aaron (30 June 2016). "Rail platform and footbridge set for closure in Pilning". South Cotswolds Gazette. Newsquest. Retrieved 2 August 2018.
  90. "Diversity Impact Assessment - Great Western Electrification Programme Pilning Station Footbridge" (PDF). Network Rail. February 2016. Archived from the original (PDF) on 3 August 2018. Retrieved 2 August 2018.
  91. Sims, Aaron (20 August 2016). "Campaigners speak out against closure of Pilning railway station platform and footbridge". South Cotswolds Gazette. Newsquest. Retrieved 2 August 2018.
  92. "Pilning Station" (PDF). FoSBR Newsletter. No. 92. Friends of Suburban Bristol Railways. October 2016. pp. 1–4. Retrieved 15 October 2019.
  93. Dixon, Rob (November 2016). "Pilning footbridge demolished" (PDF). Friends of Suburban Bristol Railways. Retrieved 2 August 2018.
  94. "Meeting Notes from meeting with representatives of Network Rail, GWR and Pilning & Severn Beach parish council" (PDF). Pilning & Severn Beach Parish Council minutes. Pilning. 22 September 2016. p. 6. Retrieved 27 October 2019.
  95. Pipe, Vicki; Marshall, Geoff (2018). The Railway Adventures: Places, Trains, People and Stations. September Publishing. pp. 15, 125–127. ISBN 978-1-910463-87-1.
  96. Marshall, Geoff; Pipe, Vicki (2 July 2017). "Pilning - Bonus Video". All the Stations. Retrieved 2 August 2018 via YouTube.
  97. "'All The Stations' challenge calls at the West Country's least-used station". ITV News. ITV plc. 25 June 2017. Retrieved 13 October 2019.
  98. Proposed closure of Angel Road station: Summary of the responses (PDF) (Report). Department for Transport. 2018. p. 3. Retrieved 15 October 2019.
  99. Taylor, Olga (June 2019). "News from Pilning Station – March 2019" (PDF). FoSBR Newsletter. No. 100. Friends of Suburban Bristol Railways. pp. 14–16. Retrieved 15 October 2019.
  100. Langman, Mark (Western Route Managing Director, Network Rail) (6 March 2019). "Rail services for the Pilning community, South Gloucestershire". Letter to Jack Lopresti MP. Retrieved 15 October 2019.
  101. Taylor, Olga (January 2017). "Pilning Station - a further update" (PDF). FoSBR Newsletter. No. 93. Friends of Suburban Bristol Railways. pp. 15–17. Retrieved 15 October 2019.
  102. "Rolling stock strategy torn up for electrification". Transport Briefing.
  103. Upgraded InterCity train plan on hold until after the election Sarah Arnott, 27 February 2010, www.independent.co.uk
  104. Robert Lea (27 February 2010). "Plans for new intercity fleet hit the buffers". The Times. Archived from the original on 11 June 2011. Retrieved 1 April 2012.
  105. Intercity trains upgrade postponed Dan Milmo, 26 February 2010, www.guardian.co.uk
  106. "Intercity train upgrade postponed until after election". BBC News. 26 February 2010. Retrieved 1 April 2012.

This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.