Smith–Putnam wind turbine
The Smith–Putnam wind turbine[2] was the world's first megawatt-size wind turbine. In 1941 it was connected to the local electrical distribution system on Grandpa's Knob in Castleton, Vermont, US. It was designed by Palmer Cosslett Putnam and manufactured by the S. Morgan Smith Company. The 1.25 MW turbine operated for 1100 hours before a blade failed at a known weak point, which had not been reinforced due to wartime material shortages. It would be the largest wind turbine ever built until 1979.[3]
Description
The turbine had two blades, 175 feet (53 m) in diameter, on the down-wind side of a 120-foot (36 m) steel lattice tower. Each blade was approximately 8 feet (2.4 m) wide and 66 feet (20 m) long, and weighed eight tons. The blades were built on steel spars and covered with a stainless steel skin. The blade spars were hinged at their root attachment to the hub, allowing them to assume a slight cone shape. The generator was a 1250 kW 600 RPM synchronous generator made by General Electric, producing 2,400 V at 60 cycles. The generator and rotor hub were mounted on a pintle beam, which allowed the rotor to capture wind from varying directions. The pitch of the blades was controlled by hydraulic cylinders to maintain constant speed. [4]
Origins
Palmer Putnam became interested in production of electric power from wind after observing high winds at Cape Cod. Putnam was aware of the Balaklava 100 kW turbine and desired to improve on its performance.[5] By 1937 he had enlisted General Electric, and the Central Vermont Public Service Corporation. General Electric provided a generator, and Central Vermont Public Services Corporation was interested in an energy supply that could displace purchased power for meeting peak loads.[6] Only 23 months elapsed between first discussions and production of power.[7]
Palmer concluded that the most promising concept was a two-bladed propeller driving a synchronous AC generator. He developed a preliminary design and cost estimates. Dr. Vannevar Bush, Dean of Engineering at MIT, reacted favorably when shown these calculations in 1937. Bush introduced Putnam to a vice president of General Electric Company, Mr. T. Knight. From this point on Putnam was able to enlist the services of some very talented people which included Theodore von Karman, a world-famous authority on aerodynamics, to assist in the design, parametric studies, cost analyses, site selection, and determination of wind characteristics.
In 1939, the Guggenheim Aeronautical Laboratories of the California Institute of Technology (GALCIT) was approached by Palmer C. Putnam, to design the turbine. Theodore von Kármán had William Rees Sears and W. Duncan Rannie carry out the aerodynamic design.[8] Unfortunately, Rannie's analytical findings regarding the stability of the giant windmill were not incorporated in the prototype that was built and tested on the mountain.[9]
Putnam obtained the financial and technical backing of the S. Morgan Smith Company of York, Pennsylvania. The Smith Company manufactured hydroelectric hydraulic turbines. Since the number of feasible sites for hydroelectric development was felt to be declining, the Smith company sought diversification into a new but related product line. The S. Morgan Smith Co. agreed to take on the project as general contractor and financed construction of a pilot turbine.
Construction
The site chosen for the prototype turbine was a previously unnamed 2000 foot (600 m) elevation, named "Grandpa's Knob"; this mountain was not so high as to have excessive ice build up, but had high wind speeds. Access to the site required construction of a road with 12 to 15% grade. Due to the impending entry of the United States into World War II, some of the fundamental research and testing process was skipped so that major components could be made before wartime material shortages occurred.
Operation and failures
No-load testing of the unit began in August 1941 to verify mechanical operation of the turbine and the blade control system. The generator was first synchronized to the local electrical grid on the evening of October 19, 1941, and tested under load varying from zero to 700 kW. The unit operated for about 1000 hours between startup and February 1943, when a shaft bearing failed. Due to wartime material priorities, the bearing was not replaced until March 3, 1945, when the unit achieved another three weeks of operation.
In the early morning of March 26, 1945, the operator on duty in the nacelle of the turbine was thrown down by vibrations. He stopped the turbine. On investigation, it was found one turbine blade had broken off and fallen about 750 feet (229 m) away. The blade had failed at a previously repaired weak point in the spar; due to wartime shortages, it had been impractical to complete a full repair and reinforcement of the blade root.[6]
Aftermath
A study completed in 1945 suggested that a block of six turbines similar to the prototype, producing 9 MW, could be installed in Vermont for around US$190 per kilowatt. However, the economic value to the power utility was only $125 per kilowatt, and the wind turbine was not considered economically viable by a factor of 1.5.[10] Although the S. Morgan Smith company had spent more than US$1.25 million on the prototype turbine, entirely private funding, it concluded that there was insufficient prospect for profit on further development. Repairs were never done after the March 1945 failure. The prototype turbine was dismantled in 1946, leaving only concrete footings and a marker plaque at the site today. In the introduction to Putnam's book, Vannevar Bush stated that the project achieved proof of the concept of synchronous generation of wind power, and projected future commercial use of wind-generated electricity.[6]
See also
Notes
- National Geodetic Survey datasheet for GRANDPAS KNOB WIND TURBINE horizontal control station (adjusted May 1998, accessed June 2013; search for PID OD1352 and check the box for "Include Destroyed Marks").
- The History and State of the Art of Variable-Speed wind turbine Technology in WIND ENERGY 2003 P.W.Carlin, A.S.Laxson and E.B.Muljadi
- A Pioneer is Vindicated in Kiplinger's Personal Finance Jan 1981, page 24, available at Google Books
- Daniel Behrman, Solar energy: the awakening science Taylor & Francis, 1979 ISBN 0-7100-8939-2 pages 227–230
- Peter Asmus, Reaping the Wind: How Mechanical Wizards, Visionaries, and Profiteers Helped Shape Our Energy Future, Island Press, 2001 ISBN 1-55963-707-2, page 45
- "Archived copy". Archived from the original on 2011-06-04. Retrieved 2009-11-21.CS1 maint: archived copy as title (link) A Bold Effort in Vermont: The 1941 Smith–Putnam Wind Turbine, C. Sulzberger, retrieved 2009 Nov 21
- Beauchamp E. Smith Smith–Putnam Wind Turbine Experiment in Joseph M. Savino (ed), Wind energy conversion systems: workshop proceedings, Washington, D. C., June 11–13, 1973, National Science Foundation (U.S.)/ National Aeronautics and Space Administration, 1973 page 6
- "W. Duncan Rannie – Memorial Tributes: National Academy of Engineering, Volume 4 – The National Academies Press". doi:10.17226/1760.
- https://ntrs.nasa.gov/archive/nasa/casi.ntrs.nasa.gov/19740026427.pdf Joseph M. Savino, A Brief Summary of the Attempts to Develop Large Wind-Electric Generating Systems in the U.S., NASA TM X-71605, August 29–30, 1974
- Erich Hau, Wind turbines: fundamentals, technologies, application, economicsBirkhäuser, 2006 ISBN 3-540-24240-6, page 36
Further reading
- Palmer C. Putnam, Power from the Wind, 1948
- Robert W. Righter, Wind energy in America: a history, University of Oklahoma Press, 1996 ISBN 0-8061-2812-7
- TIME magazine, Harnessing the Wind, September 1941, retrieved 2009 Nov 21
- Engineering and Technology History Wiki, Palmer Putnam's 1.5 MW Wind Turbine, retrieved 2016 Jan 23
- Paul Gipe, Wind-Works.org, Smith–Putnam Industrial Photos, 8 January 2014, retrieved 2016 Jan 23