Ruswarp Hydro
Ruswarp Hydro or Whitby Esk Energy, is a Hydroelectric generation scheme that operates on the River Esk at Ruswarp, North Yorkshire, England. The project uses an Archimedes Screw in a reverse direction to generate electricity and was funded by people in the community.[1] Around 4 tonnes (4.4 tons) of water pass along the screw per second, which generates enough electricity to power 45–48 homes.
Ruswarp Hydro | |
---|---|
Ruswarp Hydro plant on the River Esk | |
Official name | Whitby Esk Energy |
Country | England |
Location | Ruswarp |
Coordinates | 54°28′05.6″N 0°38′01.3″W |
Status | Operational |
Construction began | May 2012 |
Commission date | 12 December 2012 |
Owner(s) | Whitby Esk Energy |
Power generation | |
Units operational | One |
Nameplate capacity | 50kW |
Annual net output | 150,000–160,000 kWh |
External links | |
Website | whitbyeskenergy |
History
Esk Energy (Yorkshire) was formed as an industrial and provident society in 2008 to explore the idea behind a green energy scheme in Eskdale. Initially, windpower was researched but it was decided that a wind turbine would be visually intrusive in the North York Moors National Park. After a river survey and an approval was made by the Environment Agency, the collective pressed ahead with the hydro scheme.[2]
Provisional planning for the scheme was given the go-ahead in October 2009 and a co-operative was formed to raise the capital needed for the project.[3] The money raising culminated in a share option to raise extra funding of the £450,000 that was required for the scheme.[4][5] With the funding secured, construction started in May 2012 with the plant being commissioned into service on 12 December 2012.[6]
The Archimedes Screw that was built for the scheme arrived on site in September 2012 and was installed by October of the same year. The screw is 2.9 metres (9 ft 6 in) wide, 11 metres (36 ft) long and will allow a maximum 4 tonnes (4.4 tons) of water to pass through a second.[7] The screw is wide enough to allow fish to move through downstream without coming to harm.[8][9] At the same time that the project was being built, the North Yorks Moors Park Authority re-built the fishpass adjacent to the turbine.[5] The screw generates up 160,000 Kilo-watt hours per year which is enough electricity to power 45–48 homes,[10] and reduces carbon emissions by up to 70 tonnes (77 tons) per year.[11]
Even though the National Park Authority was satisfied that the development would have no detriment to the ecology or hydrology to the river,[12] some in the community were upset that they were not fully informed as to the prospect and possible ramifications of the hydro scheme. Parts of the local community were unaware that when the river was in low flow, the water would not go through the screw, but go over the weir or through the fish pass as normal, as they claim, this had not been communicated to them.[13]
References
- "Community spirit harnesses water power to save energy". The Independent. 16 July 2011. Retrieved 19 September 2017.
- Pilkington, Martin (20 January 2015). "Linton Falls is bringing renewable energy back to the Yorkshire Dales". yorkshirelife.co.uk. Retrieved 19 September 2017.
- "Turbine plan gets go-ahead". The Whitby Gazette. 16 October 2009. Retrieved 18 September 2017.
- "National park villagers raise cash to make hydro-electric power". The Yorkshire Post. 16 July 2011. Retrieved 19 September 2017.
- "Watershed day for river power scheme". The Yorkshire Post. 5 September 2012. Retrieved 19 September 2017.
- "Esk Energy (Yorkshire) Limited; Annual Report April 2012 - March 2013" (PDF). whitbyeskenergy.org.uk. p. 1. Retrieved 21 September 2017.
- "Screw to harness river's energy". BBC News. 4 September 2012. Retrieved 19 September 2017.
- "11 Tonne Turbine Arrives on Site at Community Hydropower Scheme in Ruswarp". jnbentley-news.co.uk. Retrieved 18 September 2017.
- "Screw to harness river's energy". BBC News. 4 September 2012. Retrieved 18 September 2017.
- "Esk Case Study" (PDF). co2sense.co.uk. Retrieved 18 September 2017.
- "The project". Whitby Esk Energy. 15 April 2012. Retrieved 19 September 2017.
- Branagan, Mark (21 September 2010). "Salmon river power plans stepnearer as wildlife fears refuted". The Yorkshire Post. Retrieved 19 September 2017.
- Bracken, L J; Bulkeley, H A; Maynard, C (2014). "Micro-hydro power in the UK: the role of communities in an emerging energy resource" (PDF). dur.ac.uk. Durham University. pp. 21–24. Retrieved 19 September 2017.