North–South line (MRT Jakarta)

The North–South line is a rapid transit line of the Jakarta MRT. Coloured red on the map, the line is currently 15.7 km long and serves 13 stations. It is the first line of the Jakarta MRT.

North–South line
Overview
TypeRapid transit
SystemJakarta MRT
StatusOperational (Phase 1)
Under Construction (Phase 2A)
LocaleJakarta, Indonesia
TerminiLebak Bulus
Bundaran HI
Stations13
Services1
Operation
Opened24 March 2019 (2019-03-24)
OwnerMinistry of Transportation
Operator(s)PT MRT Jakarta
CharacterElevated
Underground
Depot(s)Lebak Bulus
Ancol Barat (future)
Rolling stock16 six-car MRTJ 1000 series trainsets
Technical
Line length15.7 km (9.8 mi)
Track gauge1,067 mm (3 ft 6 in)
Electrification1,500 V DC overhead catenary
Operating speedlimit of 100 km/h (62 mph)
Route map
North–South line
↑ Phase 2 
 
Ancol Barat Depot
Ancol
Mangga Dua
↑ Phase 2B
Kota
Glodok
Mangga Besar
Sawah Besar
Harmoni
Monas
Thamrin
 M2 
↑ Phase 2A: opening 2025
Bundaran HI
Dukuh Atas BNI
 L1 
Setiabudi Astra
Bendungan Hilir
Istora Mandiri
Senayan
ASEAN
Blok M BCA
Blok A
Haji Nawi
Cipete Raya
Fatmawati
Lebak Bulus Grab
Lebak Bulus Depot

History

Jakarta MRT underground section between Dukuh Atas station and Bundaran HI, in March 2018

Phase 1

A total of eight contracts were awarded.

  • CP 101 (Construction of Lebak Bulus Depot, Lebak Bulus station and related elevated works) awarded to Tokyu Corporation - Wijaya Karya consortium.
  • CP 102 (Construction of Cipete Raya and Fatmawati stations and related elevated works) awarded to Tokyu Corporation - Wijaya Karya consortium.
  • CP 103 (Construction of Haji Nawi, Blok A, Block M and ASEAN stations and related elevated works) awarded to Obayashi Corporation - Shimizu Corporation - PT Jaya Konstruksi JV.
  • CP 104 (Construction of Senayan and Istora stations and related tunnelling works awarded to Shimizu Corporation - Obayashi Corporation - PT Wijaya Karya - PT Jaya Konstruksi JV.
  • CP 105 (Construction of Bendungan Hilir and Senayan stations and related tunnelling works awarded to Shimizu Corporation - Obayashi Corporation - PT Wijaya Karya - PT Jaya Konstruksi JV.
  • CP 106 (Construction of Dukuh Atas and Bundaran HI stations and related tunnelling works awarded to Sumitomo Mitsui Construction Company - PT Hutama Karya consortium.
  • CP 107 (Construction of railway systems and trackworks) awarded to Metro One consortium.
  • CP 108 (Construction of rolling stock) awarded to Sumitomo Corporation - Nippon Sharyo consortium.

On 1 June 2013, the first three civil contracts for the 9.2 km (5.7 mi) underground section were signed. Three civil engineering contracts for the elevated section were signed in the third quarter of 2013. Construction work began in October 2013.[1]

Tunnelling was completed on 23 February 2017, meeting the target completion date.[2] By October 2017, the construction of both elevated and underground line sections were completed.[3]

Ahead of its official opening, a limited public trial run was conducted from 12 March 2019 to 23 March 2019. The official opening ceremony was held on 24 March 2019 by the Indonesian president, Joko Widodo.[4][5]

Phase 2

A total of six contracts were put up.

  • CP 200 (Construction of underground electrical substation near Monas station) awarded to PT Trocon Indah Perkasa.
  • CP 201 (Construction of Thamrin and Monas stations and related tunnelling works) awarded to Shimizu Corporation - PT Adhi Karya JV.
  • CP 202 (Construction of Harmoni, Sawah Besar and Mangga Besar stations and related tunnelling works).
  • CP 203 (Construction of Glodok and Kota stations and related tunnelling works).
  • CP 204 (Construction of depot at Ancol Barat).
  • CP 205 (Construction of railway systems and trackworks).
  • CP 206 (Construction of 12 sets of rolling stock).

Groundbreaking for Phase 2 was initially planned to begin on 19 December 2018. However, due to land acquisition issues, it was pushed back a month, to January 2019. On 30 January 2019, President Director of PT MRT Jakarta, William Sabandar announced that the groundbreaking ceremony is delayed again as the State Secretariat has yet to issue a land-use permit for the area near Medan Merdeka.[6]

The groundbreaking ceremony for Phase 2 was finally held on 24 March 2019. Advanced works began in June 2019 near the future Monas station.[7]Site works were originally planned to begin in March 2020. However, due to the COVID-19 pandemic, it was pushed back three months, to June 2020.[8]

Network

Jakarta MRT set 11 departing from Lebak Bulus station

Stations

Region Station Name Transfers/Notes
Phase 2B (planned)
North Jakarta Ancol BaratFuture terminus
Ancol
Mangga Dua
Phase 2A (under construction, operational by 2025)
West Jakarta KotaPlanned transfer with
Glodok
Mangga Besar
Central Jakarta Sawah Besar
Harmoni
Monas
ThamrinPlanned transfer with  M2 
Phase 1
Central Jakarta Bundaran HITerminus until the completion of Phase 2.
Dukuh Atas BNIUnpaid transfer with  ARS 

Planned transfer with  LA   L1 

Setiabudi Astra
Bendungan Hilir
Istora Mandiri
Senayan
South Jakarta ASEAN[9]Initially named 'Sisingamangaraja'
Blok M BCA
Blok A
Haji Nawi
Cipete Raya
Fatmawati
Lebak Bulus GrabTerminus
gollark: Interesting idea.
gollark: What did you want me to do when you pinged me?
gollark: No.
gollark: Your point is?
gollark: <@319753218592866315> You muted HelloBoi. This is NOT acceptable.

References

This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.