Koldam Dam
The Koldam Hydropower Station commonly known as Koldam, is an embankment dam on the Satluj River upstream of the Dehar Power House. It is 18 km from Bilaspur off the Chandigarh-Manali Highway (NH-21) near Barmana, Himachal Pradesh. The main purpose of the dam is hydroelectric power generation and it will support an 800 MW power station. The dam was constructed by National Thermal Power Corporation (NTPC).[4]
Koldam | |
---|---|
Location of Koldam in India | |
Official name | Koldam Hydro Power Station
|
Country | India |
Location | Bilaspur district and Mandi district |
Coordinates | 31°22′59″N 76°52′16″E |
Status | Operational |
Construction began | 2004 |
Opening date | 2015 |
Owner(s) | NTPC Limited |
Dam and spillways | |
Type of dam | Embankment, rock-fill with clay core |
Height (foundation) | 167 m (548 ft) |
Height (thalweg) | 153 m (502 ft) |
Length | 474 m (1,555 ft) |
Elevation at crest | 648 m (2,126 ft) |
Width (crest) | 14 m (46 ft) |
Dam volume | 12,000,000 m3 (15,695,407 cu yd) |
Spillway type | Chute with flip bucket, six radial gates |
Spillway capacity | 16,500 m3/s (582,692 cu ft/s) |
Reservoir | |
Total capacity | 576,000,000 m3 (466,971 acre⋅ft)[1] |
Maximum length | 40 km (25 mi) |
Normal elevation | 642 m (2,106 ft)[2] |
Power Station | |
Commission date | 2015[3] |
Hydraulic head | 131.2 m (430 ft) (static) |
Turbines | 4 x 200 MW Francis-type |
Installed capacity | 800 MW |
Annual generation | 3055 million units (3055 3055GWh) |
The foundation stone for the dam was laid on 5 June 2000 by Prime Minister Atal Bihari Vajpayee. On 14 January 2004, main construction on the dam began.[2] Due to problems associated with habitat and forest loss, the project has been delayed. Attempts to impound the reservoir first failed in December 2013 due to problems with sealing the diversion tunnels. By 18 March 2014, a fourth attempt to seal the tunnels and fill the lake was underway.[5] Repairs were made and another unsuccessful impounding was reached in April 2014 as the diversion tunnel continued to leak.[6] Another period of impounding began on 3 November 2014 and finished on 3 January 2015. A tunnel still leaked though but authorities were confident they would have the power station operational by April.[7] Generator commissioning was originally scheduled for 2009 but was rescheduled to 2015.[3][8][9]
Power Generation Capacity
Its installed capacity is of 800 MW (4x200 MW). The first 200 MW Francis turbine-generator was commissioned on 30 March 2015 and the third on 10 April 2015.[10][11]
Unit Number | Capacity (MW) | Date of Commissioning | Status |
---|---|---|---|
1 | 200 | 31 March 2015 | commissioned.[12] |
2 | 200 | 30 March 2015 | commissioned |
3 | 200 | 10 April 2015 | commissioned |
4 | 200 | 12 June 2015 | commissioned |
TOTAL | 800 |
References
- Heard, S.P.; Gardron, P.; Senan, R.C.; Agarwal, M. "Koldam hydroelectric Project a new hydroelectric project on the Satluj river in India". Retrieved 23 November 2011.
- "Kol Dam Hydro Electric Power Project". Italian-Thai Development PLC. Retrieved 23 November 2011.
- "Kol Dam HEP commissioning now slated for 2013". Asian Power. 24 June 2011. Retrieved 23 November 2011.
- "BHEL starts NTPC's 800-MW Koldam hydro power plant - The Economic Times". The Economic Times. Retrieved 9 January 2016.
- "Impounding of water in NTPC's Koldam hydel project begins". Power Business View. 18 March 2014. Retrieved 1 April 2014.
- "NTPC conducts reservoir impounding for Kol dam project". The Times of India. 9 April 2014. Retrieved 13 May 2014.
- "2nd phase of impounding over, but leakage continues". The Tribune. 12 January 2015. Retrieved 17 January 2015.
- "Koldam Project of NTPC suffers major setback in Himachal". Jagran Post. 5 June 2011. Retrieved 23 November 2011.
- "800 MW Koldam project commissioning extended to April 2014". MoneyControl. 15 December 2012. Retrieved 2 August 2013.
- "NTPC's First Hydropower Project Starts in Himachal". NDTV Convergence. Press Trust of India. 30 March 2015. Retrieved 1 April 2015.
- "NTPC Ltd commissions Unit 3 of 200 MW of Koldam Hydro Power Project". Equity Bulls. 19 April 2015. Retrieved 13 May 2015.
- http://www.indiainfoline.com/article/news-top-story/bhel-commissions-4-sets-of-200-mw-each-at-koldam-hydro-electric-project-115061500230_1.html