Bison Wind Energy Center
The Bison Wind Energy Center is a 496.6 megawatt (MW) wind farm spanning southwest Oliver County and north-central Morton County in the U.S. state of North Dakota. It became the largest wind generating facility in the state upon completion of the fourth construction phase in early 2015. The facility allowed the investor-owned utility company, Minnesota Power, to obtain more than 25% of its electricity generation from renewable sources, exceeding Minnesota's 2025 renewable portfolio standard requirement.[1][2]
Bison Wind Energy Center | |
---|---|
Official name | Bison Wind Energy Center |
Country | United States |
Location | Morton County and Oliver County, North Dakota |
Coordinates | 46°58′48″N 101°33′17″W |
Status | Operational |
Construction began | June 2010 |
Commission date | gradually thru Jan 2015 |
Construction cost | $800 million |
Owner(s) | Minnesota Power |
Operator(s) | Minnesota Power, Siemens |
Wind farm | |
Type | Onshore |
Power generation | |
Units operational | 165 turbines |
Make and model | 16 Siemens SWT-2.3 MW 85 Siemens SWT-3.0 MW 64 Siemens SWT-3.2 MW |
Nameplate capacity | 496.6 MW |
Capacity factor | 40.6% (average 2016–2017) |
Annual net output | 1,766 GW·h |
Details
The project was developed by Minnesota Power, and its parent company Allete Inc., to harvest the highly productive wind resources in the adjacent state of North Dakota. The utility provides electricity to several energy-intensive industrial customers which dominate consumption within northern Minnesota's mostly rural economy.[2] In 2009, the company prepared for the first construction phase with the purchase and upgrade of a 465 mile high-voltage direct current transmission line that would efficiently transport the electricity from the Square Butte Substation near Center, North Dakota to the Arrowhead Substation near Duluth, Minnesota. The company's plan also called for reducing it's purchases of electricity from the coal-fired generating units feeding the Square Butte Substation as the Bison wind facility grew.[3]
Construction of the first phase of 33 wind turbines began in June 2010. It included 16 Siemens SWT-2.3 MW and 17 Siemens SWT-3.0 MW turbines.[4] The nacelle and hub components were transported by ship from Siemen's manufacturing facilities in Denmark to Allete's headquarters in Duluth, then trucked to the facility site about 40 miles west of Bismarck. The blades and the 80 meter tower sections were manufactured Fort Madison, Iowa and West Fargo, North Dakota, respectively.[3] A new 22 mile 345 kV transmission connects the new Bison facility substation to the Square Butte Substation. Phase 1 began sending power to Minnesota by the end of 2010, and was fully commissioned in February 2012, with a total capital cost of about $177 million.[5]
Construction phases 2 and 3 each consist of 35 Siemens SWT-3.0 MW turbines.[4] Two phase 1 turbines were transferred to an initial phase 1B grouping which was ultimately included in phase 3. Phases 2 and 3 both came online at the end of 2012.[5][6]
The latest and largest construction phase 4 began in the fall of 2013 and consists of 64 Siemens SWT-3.2 MW turbines.[4] These more powerful turbines enable direct drive of the generator unit, thus reducing the number mechanical components and increasing reliability.[7] The 92 meter tower sections were manufactured in Manitowoc, Wisconsin, a portion of the generator units in Hutchinson, Kansas, and the blades in Fort Madison, Iowa.[2] A new 11 mile 345 kV transmission line and substation were constructed to connect the west side of the facility to an expansion of original Bison substation. The cost of this expansion phase was about $345 million, bringing the total investment in the facility to nearly $800 million. Phase 4 came online at the beginning of 2015.[1][5]
In September 2015 Siemens announced that it had been contracted to provide operational and maintenance (O&M) support for the 3.0 MW and 3.2 MW turbines (total of 149 units) at the Bison Wind Energy Center for their first 10 years of operation. Minnesota Power is continuing to provide O&M support for the remaining 2.3 MW turbines (total of 16 units).[7]
Electricity production
Year | Bison 1 81.8 MW [8] | Bison 2 105 MW [9] | Bison 3 105 MW [10] | Bison 4 204.8 MW [11] | Total Annual MW·h |
---|---|---|---|---|---|
2010 | 10,274* | – | – | – | 10,274 |
2011 | 128,163* | – | – | – | 128,163 |
2012 | 280,347 | 4,441* | – | – | 284,788 |
2013 | 232,623 | 272,699 | 274,477 | – | 779,799 |
2014 | 269,839 | 324,088 | 326,727 | – | 920,654 |
2015 | 239,495 | 294,291 | 293,756 | 712,056* | 1,539,598 |
2016 | 268,839 | 328,831 | 326,999 | 832,159 | 1,756,828 |
2017 | 271,815 | 328,922 | 333,816 | 840,920 | 1,775,473 |
Average Annual Production (years 2016–2017) ---> | 1,766,150 | ||||
Average Capacity Factor (years 2016–2017) ---> | 40.6% |
(*) partial year of operation
References
- "Minnesota Power wind farm in North Dakota is complete". The Duluth News Tribune. January 19, 2015.
- "Minnesota Power expands Bison Wind power project". Electric Light and Power. January 19, 2015.
- "ALLETE's Bison wind energy project well underway in North Dakota" (PDF). Allete Inc. Newsletter, The Allete Investor. September 1, 2010.
- "Bison Wind Project". thewindpower.net. Retrieved April 12, 2019.
- "Bison Wind Energy Center". Minnesota Power. Retrieved April 12, 2019.
- "70 new wind turbines up and running in N. Dakota". The Star Tribune. December 19, 2012.
- "Siemens to provide long-term service at Bison Wind Energy Center in North Dakota". Siemens Power Generation Services. September 24, 2015.
- "Bison 1, Annual". Electricity Data Browser. Energy Information Administration. Retrieved April 12, 2019.
- "Bison 2, Annual". Electricity Data Browser. Energy Information Administration. Retrieved April 12, 2019.
- "Bison 3, Annual". Electricity Data Browser. Energy Information Administration. Retrieved April 12, 2019.
- "Bison 4, Annual". Electricity Data Browser. Energy Information Administration. Retrieved April 12, 2019.