Metrotrén Asturias

Metrotrén Asturias is a project that consists of the creation of a suburban rail transport network through the homogenization of the lines currently existing in the Spanish autonomous community of Asturias. It consists of a unification of the lines of both operators (Renfe Operadora and Renfe FEVE), the reduction of travel times and transfers, the burying of railway lines and the creation of new stations.[1]

Metrotrén Asturias
Overview
TypeCommuter rail
SystemCercanías Asturias
StatusPart constructed, abandoned
LocaleAsturias, Spain
TerminiGijón railway station
Cabueñes
Stations6
Technical
Line length3.858 km (2.397 mi)
Track gauge1,668 mm (5 ft 5 2132 in) Iberian gauge
1,000 mm (3 ft 3 38 in) metre gauge

History

The project for the renovation of the suburban railway network of Asturias was presented in August 2000 by the Ministry of Development. It consisted mainly in the creation of a new tunnel of 3,858 meters in length in Gijón between the Humedal station and the roundabout of Viesques, which included three new stations: Begoña, El Bibio and Viesques.[2] The construction of this tunnel began on June 10, 2003 and ended in December 2006, although only the El Bibio station and a technical station were built on Avenida Justo del Castillo.[3]

The project, by increasing the density of rail transport in Gijón and being buried, was known as the "Gijón metro".[4]

During the construction of the tunnel, the Ministry of Development changed its criteria regarding the rest of the project's actions, deciding that it be extended to reach the Cabueñes area, thus doubling the length of the section. In addition, the construction of two new stations, an interchange, and the replacement of the planned Begoña station by another in the Plaza de Europa were included.

This second phase remained paralyzed from the end of the previous phase, with the tunnel remaining unused for the whole time. The complete definition of the second phase ended in 2009, with the remaining cost estimated at €360 million, with an action along 7 km between the Humedal and Cabueñes.[5] The development of this second part began in 2011 through public-private financing, and involves the provisional diversion of the FEVE lines from the Humedal station to the provisional station of Sanz Crespo, which was started in February 2011.[6] This section will have dual-gauge tracks to be used by both Ibergian-gauge Renfe Operadora and metre-gauge Renfe FEVE trains.

The project also consists of improvements at other railway stations in Asturias, such as those located in Avilés.

Current situation

In 2017, it was announced that work on the Metrotrén tunnel is due to resume in 2019 and conclude in 2023.[7]

References

  1. Todotrenes: «Metrotrén, la revolución en las cercanías»
  2. La Nueva España, [«http://www.lne.es/gijon/2011/01/14/destiempos-metrotren/1019380.html Los destiempos del Metrotrén]»
  3. La Voz de Asturias: «El túnel de metrotrén ve la luz»
  4. La Voz de Asturias, «El Metro de Gijón»
  5. RTPA: «Fomento anuncia una inversión de 360 millones para el metrotrén Archived 2016-03-04 at the Wayback Machine»
  6. La Voz de Asturias: «El metrotrén tendrá doble ancho»
  7. "El "metrotrén" llegará a Cabueñes en 2023". La Nueva España. 22 June 2017. Retrieved 14 March 2019.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.