Ajaokuta Steel Mill

Ajaokuta Steel Company Limited (ASCL) popularly known as Ajaokuta Steel Mill is a steel mill in Nigeria, located in Ajaokuta, Kogi State, Nigeria.[1] Built on a 24,000 hectares (59,000 acres) site starting in 1979,[1] it is the largest steel mill in Nigeria, and the coke oven and byproducts plant are larger than all the refineries in Nigeria combined.[2] However, the project was mismanaged and remains incomplete 40 years later. Three-quarters of the complex have been abandoned, and only the light mills have been put into operation for small-scale fabrication and the production of iron rods.[3]

Ajaokuta Steel Mill Company
State-owned enterprise
IndustrySteel
FateIn minimal operation
Founded1979 (1979)
Headquarters,
Area served
Nigeria
Websitewww.ajaokutasteel.com 

History

The contruction project was first awarded to the British, and later undertaken by the Soviet Union under a cooperation agreement with Nigeria. In 1967, Soviet experts recommended prospecting for iron ore in Nigeria, as the known deposits were of poor quality for steelmaking. In 1973, iron ore of the required quality was discovered in Itakpe, Ajabanoko, and Oshokoshoko. The Ajaokuta Steel Company Limited was incorporated in 1979, and the steel mill reached 98% completion in 1994, with 40 of the 43 plants at the facility having been built.[2] To supply the Ajaokuta Steel Mill with raw materials and connect it with the world market, a contract was awarded in 1987 for the construction of Nigeria's first standard gauge railway, from the iron mines at Itakpe to the steel mill at Ajaokuta and continuing to the Atlantic Ocean at Warri.[4]

However, both projects have been mismanaged. The Ajaokuta Steel Mill was still unfinished four decades after construction began.[2] After several failed attempts at privatisation, the Nigerian government took back control in 2016.[5] The Ajaokuta Steel Mill still had not produced a single sheet of steel by December 2017.[2] The light mills were finally put into operation in 2018 for small-scale fabrication and the production of iron rods. However, three-quarters of the plant have been abandoned, including the large-scale equipment and the internal railway.[3]

The Itakpe–Warri Railway fell into disrepair, and part of the track was vandalised. In 2016, the Nigerian government awarded contracts to the China Civil Engineering Construction Corporation and Julius Berger to repair and complete the railway.[4] Test runs began in November 2018,[6] and the railway is expected to be completed by the end of 2019.[7]

References

  1. Robson, Lorna (2005). Nigeria. London: Evans Brothers. p. 27. ISBN 9780237527563.
  2. Oluyole, Francisca (26 December 2017). "How Nigeria's Largest Industrial Project Failed". Premium Times (Abuja).
  3. "Nigeria: Steel factory will open after 40 years". Al Jazeera English. 16 June 2018.
  4. "Itakpe-Ajaokuta-Warri rail line to start operation in June 2018 - Rotimi Amaechi". Vanguard News. 7 August 2017.
  5. "Ownership crisis ends, Nigeria retakes Ajaokuta Steel Company". Premium Times Nigeria. 1 August 2016.
  6. Ejike, Ejike (26 November 2018). "Itakpe Train Service Begins Operation Today". Leadership.
  7. "Keeping up with the Lagos-Ibadan Standard Guage Railway Project". This Day (Nigeria). 23 May 2019.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.