Ross Dam

Ross Dam is a 540-foot (160 m)-high, 1,300-foot (400 m)-long concrete thin arch dam across the Skagit River, forming Ross Lake. The dam is in Washington state, while Ross Lake extends 23 miles (37 km) north to British Columbia, Canada. Both dam and reservoir are located in Ross Lake National Recreation Area, is bordered on both sides by Stephen Mather Wilderness and combined with Lake Chelan National Recreation Area they make up North Cascades National Park Complex.

Ross Dam
Ross Dam during the Skagit River floods of 2003.
LocationRoss Lake National Recreation Area, Whatcom County, Washington, USA
Coordinates48°43′54″N 121°04′02″W
Construction began1937
Opening date1949
Dam and spillways
ImpoundsSkagit River
Height540 feet (160 m)
Length1,300 feet (400 m)
Reservoir
CreatesRoss Lake
Total capacity1,435,000 acre feet (1.770 km3)
Surface area11,700 acres (4,700 ha)
Power Station
Turbines4
Installed capacity460 MW
Annual generation619,120,000 KWh[1]
Website
http://www.seattle.gov/light/FuelMix/

Built as part of the Skagit River Hydroelectric Project by Seattle City Light, the dam is part of a series of three dams through the Skagit Gorge that were built primarily to generate hydroelectricity from the massive elevation drop of over 1,000 feet (300 m) from the Canada-U.S. border to Newhalem. The other two dams are Diablo Dam, directly below Ross Dam, and Gorge Dam, further downstream. Ross Dam can generate up to 460 MW of electricity. Hydro-electric dams provide approximately 92 percent of the electricity used in Seattle.

History

Planning and early construction

Prior to construction of the dam the Skagit Gorge upstream of the dam was a wild, free flowing, completely undeveloped area. The canyon held an intact ancient forest of Douglas Fir, Western Hemlock and Western Redcedar, estimated to be millable into up to 340 million usable board feet of timber. With the creation of the Skagit River Hydroelectric Project in the 1910s, the first two dams, Gorge Dam and Diablo Dam, were constructed downstream of the Ross Dam site. In 1937, construction began on the dam, originally slated to be called Ruby Dam, on the first two of four planned construction phases. The name originates from Ruby Creek, a Skagit River tributary that flows southwest to meet the Skagit just upstream of the dam site.[2] By 1940, phases 1 and 2 of the dam were complete, and the dam stood 305 feet (93 m) above the river. While the reservoir filled, the Decco-Walton Logging Company was formed in 1945 with the awarding of a contract from Seattle City Light. Decco-Walton logged the Skagit Gorge as Ross Lake slowly rose, and floated logs up the river to British Columbia, where it was hauled to the Fraser River. By the time Ross Lake filled, only 30 million board feet remained in the basin, less than 10% of the original timber.[2][3][4]

Third phase

Ross Dam third construction phase, 1947

In 1939, superintendent of the Skagit Hydroelectric Project James Delmage Ross has died, so Ruby Dam was renamed Ross Dam in his memory. In 1943 a consortium of contractors including Morrison-Knudsen, which had previously participated in construction of Hoover Dam, began new construction on the dam ultimately raising its height to 475 feet (145 m).[5] Energy demands during World War II coincided with an energy shortage in Seattle, requiring that the dam be constructed quickly, but the dam did not generate any power until many years after the war ended.[6] This third phase was finished in 1949, to 540 feet (160 m). This height would cause the reservoir at full pool to extend slightly past the Washington-British Columbia border. The reservoir, however, did not fill past the national border until 1954. As compensation for the flooded land, which totals about 500 acres (2.0 km2), Seattle City Light paid the Province of British Columbia $250,000, as well as an annual payment of $5,000. Two years prior to the reservoir reaching full pool, construction of the Ross Dam power plant began, and two turbines first went on line in 1956, generating 360 MW of power. Another two generators were added later, increasing the capacity to its current 460 MW.[2]

High Ross Dam

The upper map shows what the dimensions of the reservoir would have been if the high dam had been built. The lower map shows the existing dimensions of the reservoir. Dam is at left in both maps.

A controversy later arose over the planned fourth stage of the construction of Ross Dam. This argument over land became known as the High Ross Dam Controversy. The dam was built with the potential to be raised 125 feet (38 m) further, bringing the total height of the dam to 665 feet (203 m) and raising the reservoir to approximately 1,725 feet (526 m) above sea level. The stepped "concrete waffle" facing on the front of the dam was designed to accommodate this addition to the height.[6] This would have flooded land into Canada approximately 3 miles (4.8 km) further, also extending up the Klesilkwa River, a Skagit River tributary, and provided the opportunity to generate about 272 MW of extra power, bringing the generating capacity to 732 MW.[4][6] It wasn't until the 1970s when the High Ross project was finally ended. On the US side, the North Cascades Conservation Council inventoried the ancient forest of Big Beaver Creek which would have been flooded, and showed that City Light's statements that no unique forest environments would be lost were not true. On the Canadian side the raising of the dam was halted primarily by the extensive work by Curley Chittenden - logger turned environmentalist, who worked tirelessly to rally opposition to this additional flooding of the upper Skagit River basin. Ultimately a treaty was signed between the City of Seattle and Province of British Columbia to supply Seattle with the equivalent amount of power from other, existing dams in British Columbia in exchange for Seattle not raising the dam. The Skagit Environmental Endowment Commission was created at this time to oversee joint USA/Canada stewardship of the upper Skagit River watershed.

Description

The Ross Dam is situated in the gorge of the Skagit River about midway along its 150-mile (240 km) length, and 23 miles (37 km) south of the Canada–US border. It is a concrete thin arch dam 540 feet (160 m) high and about 1,300 feet (400 m) long, stretching across one of the narrowest spots in the Skagit Gorge.

The North Cascades mountains rise nearly 5,000 feet (1,500 m) vertically from the floor of the canyon and surround it on both sides. Directly upstream of the dam, Ruby Creek flows into the reservoir, forming the Ruby Arm of Ross Lake. Directly downstream, Diablo Dam forms Diablo Lake, much smaller than Ross Lake. Other creeks that flow into Ross Lake include Little Beaver Creek and Big Beaver Creek from the west, and Lightning Creek from the east. North Cascades Highway, also known as Washington State Route 20, follows the Skagit River to where it turns away from the river at Ross Dam and follows Ruby Creek instead.

The power plant of Ross Dam is located just downstream of its base and produces 460 MW of power from four hydroelectric turbines. The dam has two over-the-crest spillways on its flanks, each with six individual spillway bays. The capacity of each individual spillway bay at full pool is rated at 10,600 cubic feet per second (300 m3/s), for a total discharge capacity of just over 127,000 cubic feet per second (3,600 m3/s).[7]

gollark: Besides, this is, like all my stuff, *not very serious*.
gollark: Also I have no clue where to look.
gollark: Thus I am not permitted to do it.
gollark: That would be EFFICIENT and SENSIBLE.
gollark: > simon says "neoliberalism commodifies parasocial relationships"Who is Simon? Do I know Simon?

See also

  • List of world's tallest dams
  • List of dams in the United States

References

  1. http://carma.org/plant/detail/38012
  2. Pattee, Scott (2004). "A History of the Skagit River Basin Snow Surveys and Hydroelectric Project" (PDF). Western Snow Conference. Retrieved 2009-10-18.
  3. "Dam Construction". Timber Resources: Logging. U.S. National Park Service. Retrieved 2009-10-19.
  4. Louter, David (1998). "North Cascades: Contested Terrain". North Cascades National Park Service Complex, Washington: An Administrative History. U.S. National Park Service. Retrieved 2009-10-19.
  5. Nations, Pauul (January 1945). "Ross Dam Makes Good Progress". The Em Kayan: 20.
  6. Simmons, Terry Allan (1968). "The Damnation of a Dam: The High Ross Dam Controversy" (PDF). Simon Fraser University. Retrieved 2009-10-20.
  7. "Hydraulic Model Studies to Determine Spillway Discharge Curves for Ross Dam" (PDF). U.S. Bureau of Reclamation. 1953-06-10. Retrieved 2009-10-20.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.