Metropolitan Water Board v Dick, Kerr & Co Ltd

Metropolitan Water Board v Dick Kerr and Co Ltd [1918] AC 119 is an English contract law case, concerning the frustration of an agreement.

Metropolitan Water Board v Dick Kerr and Co Ltd
CourtHouse of Lords
Decided26 November 1917
Citation(s)[1918] AC 119
Transcript(s)
Court membership
Judge(s) sittingLord Atkinson, Lord Dunedin, Lord Parmoor, Lord Finlay
Keywords
Frustration

Facts

In July 1914, Dick, Kerr & Co agreed to build a reservoir in six years for the Metropolitan Water Board (London). The contract said that Dick, Kerr & Co should apply to the engineer for an extension of time in the event of delay ‘whatsoever and howsoever occasioned’.

Two years later on 21 February 1916, due to the war, the Ministry of Munitions ordered Dick, Kerr & Co to stop work and sell their plant. The MWD subsequently sued Dick Kerr to complete the reservoir.

Judgment

The House of Lords held that the contract was frustrated, because the delay clause was intended to cover temporary difficulties, and not such fundamental changes in the contract’s nature.

gollark: Basically, I've set it up (well, theoretically, I don't think it works that well) to use an FTS5 table and to insert stuff into that whenever a row is inserted into `revisions`, so I can do full text search.
gollark: No, 'twas a bug in one of my TRIGGER thingies.
gollark: Anyway, it's... fixed now? Partly?
gollark: Oh I see, for some... strange reason... it was picking up an error in a *trigger* as being there.
gollark: FOOLISH DATABASE, THAT IS THREE COLUMNS AND THREE VALUES!

See also

Notes

    References

        This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.