Line 4 (Mumbai Metro)

Line 4 of the Mumbai Metro, currently under construction, is part of the metro system for the city of Mumbai, India and is being developed by MMRDA and a consortium of international companies.[2]

Mumbai Metro Line 4 (Green Line)
Overview
TypeRapid Transit
SystemMumbai Metro
Status
  • Line 4 (under construction)
  • Line 4A (under construction)[1]
LocaleMumbai and Thane, Maharashtra, India
TerminiKasarvadavali
Wadala
Stations32 + 2 extended 34
Daily ridership2021 0.8 million 2031 1.2 million
Line number4
WebsiteLine 4
Operation
Commenced25 July 2018 (2018-07-25)
Planned openingOctober 2022 (2022-10)
OwnerMMRDA
Operator(s)Mumbai Metro
CharacterElevated
Depot(s)Owale
Godrej
Technical
Line length32.32 km (20.08 mi)
Number of tracks2
Track gauge1,435 mm (4 ft 8 12 in) standard gauge
Operating speed90 km/h (56 mph)
Highest elevation3.90 m (12.8 ft)
Mumbai Metro (Line 4)
(Connects to Line 10)
Gaimukh
Gowniwada
(Connects to Line 4A)
Kasarvadavali
Vijay Garden
Dongari Pada
Tikuji-Ni-Wadi
Manpada
Kapurbawdi
(Connects to Line 5)
Majiwada
Cadbury Junction
Mahapalika Marg
RTO Thane
Thane Teen Haath Naka
(Connects to Thane)
Mumbai Suburban Railway
(Connects to Mumbai Suburban)
Maharana Pratap Chowk
Mulund Fire Station
Dr Hedgewar Chowk
Shangrila
Bhandup Metro
Bhandup Mahapalika
Naval Housing
Gandhi Nagar
(Connects to Line 6)
Surya Nagar
Vikhroli Metro
Godrej Company
Amar Mahal Junction
(Connects to Line 2)
Siddharth Colony
Suman Nagar
Anik Nagar Bus Depot
Wadala TT
(Connects to Line 11)
Bhakti Park Metro

The 32.32 km (20.08 mi) line is planned to be fully elevated, and is expected to consist of 32 stations from Wadala (Mumbai) to Kasarvadavali (Ghodbunder road, Thane) via Ghatkopar, Mulund and Teen Hath Naka, a popular traffic crossing in Thane. It is estimated to cost ₹14,549 crore.[3] Its construction was expected to begin by June 2018.

It is expected to be completed in 2022 and is expected to provide interconnectivity among the existing Eastern Express Highway, Central Railway, Mono Rail, the ongoing Metro Line 2B (D N Nagar to Mandale), and the proposed Metro Line 5 (Thane to Kalyan), Metro Line 6 (Swami Samarth Nagar to Vikhroli) and Metro Line 11 (Wadala to CSMT). It will provide rail based access to the commercial, government bodies and geographical landmarks in Mumbai. Dedicated depots are planned in Owale land in up to an extent of 20 ha. and in Godrej Land in up to 15.50 ha. area. It will reduce the current travel time by between 50% and 75% depending on road conditions.

Planning

The Maharashtra Cabinet approved the Metro 4 corridor on 27 September 2016. Half of the project cost will be funded by the Centre and the State Government, while the remaining will be financed through loans from the AIIB[4] and the World Bank.[5][6] The foundation stone for Metro 4 was laid by Prime Minister Narendra Modi on 24 December 2016.[7] The Maharashtra Coastal Zone Management Authority granted Coastal Regulation Zone (CRZ) to the project in February 2017. Over 1 km of the line passes over water bodies in Bhakti Park and Wadala, both areas classified as Coastal Regulation Zone II where CRZ rules limit construction activities. 48 piers are proposed to built in the CRZ II. The MMRDA will construct metro car depots for the line on a 30 hectare plot at Owala village in Thane district and another in Vikhroli.[8]

The MMRDA utilized a drone to carry out survey work for Metro 4. The drones were fitted with 360 degrees camera that provide up to 3 millimeter accuracy. The aerial survey takes less time than a regular survey, achieves greater accuracy and helps protect against false claims for compensation.[9] In March 2017, the MMRDA stated that it was conducting a pre-feasbility study on extending the line from Wadala to Mumbai General Post Office in South Mumbai, via the Mumbai Port Trust. The proposed 8 km extension is estimated to cost 300 crore per km.[10][11]

In October 2018, the MMRDA announced that it would construct Metro 4 along with three flyovers to ensure smooth flow of traffic, with the metro running on the upper deck of the flyover. The three flyovers will be built at Bhayander Pada, Kasarvadavli and Anandnagar near Ghodbunder.[12][13]

In May 2019, MMRDA Metropolitan Commissioner R.A. Rajeev announced a modified plan to use Siddharth Colony as the interchange station with Line 2. The original plan had proposed to use the Eastern Express Highway station on Line 2B and Siddharth Colony on Line 4 as the interchange stations. However, the two stations are approximately 480 metres away from Siddharth Colony and the change was made to simplify passenger transfers.[14]

Construction

A consortium of DB Engineering, Louis Berger and Hill International was awarded a project management and construction management services contract for the Metro 4 project in April 2018.[15][16] The MMRDA invited bids for civil work on the corridor on 4 January 2017.[17][18][19] The tenders for construction of viaducts and stations were divided into five packages - Wadala to Amar Mahal Junction, Garodia Nagar to Surya Nagar, Gandhi Nagar to Sonapur, Mulund Fire Station to Majiwada and Kapurbawdi to Kasarvadavali.[20][21] Metro 4 was tendered alongside Metro 2B. L&T, Afcons Infrastructure, Tata, NCC and JMC, Reliance Infrastructure-RdE, JKumar Group, ITD Cementation, CHEC-TPL bid for packages on both Metro 2B and Metro 4. A total of 10 firms and/or consortia submitted bids for the two lines, two of whom (Simplex Infrastructures and a consortium of GHEC-RCC-JV-China) bid exclusively for Metro 2B packages.[22][23]

The construction work was divided into five packages and awarded through the engineering, procurement and construction (EPC) model in April 2018. A joint venture between Reliance Infrastructure and Italian firm Astaldi S.P.A was awarded three packages between Kasarwadavali and Wadala worth 1,584 crore (US$220 million).[24] The contract for the remaining two packages, worth a combined 1,048 crore (US$150 million), was awarded to a joint venture between Tata Projects Limited and China Harbour Engineering Company.[25] The civil work is expected to be completed in 30 months.[26]

Sl No.ContractContractor
1General ConsultantDB Engineering & Consulting GmbH[27] with M/s. Louis Berger Pvt. Ltd[28] and Hill International[29]
2Rolling StockYet to be awarded (tenders invited in Dec 2019)[30]
3 Signalling & Screen Doors Yet to be awarded (tenders invited in April 2020)[31]
4Detailed Design Consultant (DDC)M/s. SYSTRA MVA Consulting (India) Pvt. Ltd.[32]
5Wadala to Amar Mahal

(6.2 km Viaduct & 6 Stations)

Reliance-Astaldi JV
6Garodia Nagar-Surya Nagar

(6.4 km Viaduct & 7 Stations)

TPL-CHEC JV
7Gandhi Nagar-Sonapur

(6.7 km Viaduct & 6 Stations)

Reliance-Astaldi JV
8Mulund Fire Station-Majiwada

(7.1 km Viaduct & 7 Stations)

TPL-CHEC JV
9Kapurbawdi-Kasarvadavali

(6.8 km Viaduct & 6 Stations)

Reliance-Astaldi JV

Current status

Sr. No.Name of Work Description Status for year 2019-20[33]
21 May 2019 3 June 2019 14 June 2019 4 July 2019 6 August 2019 21 October 2019 29 November 2019 29 January 2020
1Soil Investigation Works Soil Investigation Work For Pier Foundation Completed 78% 80.5% 81.0% 82.0% 83.0% 85% 87%
2Utility Works Works Completed 64% 66.4% 68.2% 70% 71.36% 76%
3Piling Works Piling Work For

Foundations Completed

17% 21.2% 22.7% 25.25% 33% 37% 42.56% 47%
4Pile Cap Works Pile Cap Work Completed 6.5% 10.1% 12.4% 14.7% 18.60% 21% 24.75% 27.3%
5Pier Works Piers Cast 3.5% 5.71% 8.0% 10.2% 15.70% 18.3% 29.23% 23.6%
6 Pier Cap Works pier caps cast Nil Casting of Pier Cap is started

at casting yard and 0.075% casting completed till May 2019.

Casting of Pier Cap is started

at casting yard and 0.063% casting completed till June 2019

Casting of Pier Cap is started

at casting yard and 0.068% casting completed till July 2019

6% Casting completed. 10% 17.98% 22%
pier caps erected Nil 0.80% Erection completed. 2.4% 23.34% 12%
7 U Girder Works Casting yard works are in progress Nil Nil Casting of U Girder started

at casting yard and 0.21% casting completed till June 2019

Casting of U Girder started

at casting yard and 0.41% casting completed till July 2019

2.33% 6% 11.83% 16%
U Girder erected Nil 0.9% 4%
8Station work Station work in progress Nil Pile Foundation works Started since last month Works are in Progress.
Mumbai Metro 4 DreamLine

Stations

32 stations are being planned on Line 4. Most of them were either in the stage of planning or under early stages of construction (as of November 2018) [34]

# Station Grade Connections Status
1KasarvadavaliElevatedLine 4A (Mumbai Metro),

Line 10 (Mumbai Metro)

Under Construction
2Vijay GardenElevatedNoneUnder Construction
3Dongari PadaElevatedNoneUnder Construction
4Tikuji-Ni-WadiElevatedNoneUnder Construction
5ManpadaElevatedNoneUnder Construction
6KapurbawdiElevatedLine 5 (Mumbai Metro)Under Construction
7MajiwadaElevatedNoneUnder Construction
8Cadbury JunctionElevatedNoneUnder Construction
9Mahapalika MargElevatedNoneUnder Construction
10RTO ThaneElevatedNoneUnder Construction
11Thane Teen Haath NakaElevatedNoneUnder Construction
12Maharana Pratap ChowkElevatedNoneUnder Construction
13Mulund Fire StationElevatedNoneUnder Construction
14Dr Hedgewar ChowkElevatedNoneUnder Construction
15ShangrilaElevatedNoneUnder Construction
16Bhandup MetroElevatedNoneUnder Construction
17Bhandup MahapalikaElevatedNoneUnder Construction
18Naval HousingElevatedNoneUnder Construction
19Gandhi NagarElevatedLine 6 (Mumbai Metro)Under Construction
20Surya NagarElevatedNoneUnder Construction
21Vikhroli MetroElevatedNoneUnder Construction
22Godrej CompanyElevatedNoneUnder Construction
23Shreyes CinemaElevatedNoneUnder Construction
24Lakshmi NagarElevatedNoneUnder Construction
25Pant NagarElevatedNoneUnder Construction
26Garodia NagarElevatedNoneUnder Construction
27Amar Mahal JunctionElevatedLine 2 (Mumbai Metro)Under Construction
28Siddharth ColonyElevatedNoneUnder Construction
29Suman NagarElevatedNoneUnder Construction
30Anik Nagar Bus DepotElevatedNoneUnder Construction
31Wadala TTElevatedLine 11 (Mumbai Metro)Under Construction
32Bhakti Park MetroElevatedLine 1 (Mumbai Monorail)Under Construction

The car depot will be located at Owale.[3]

2 stations are being planned on Line 4A. Connected to word Gaimukh to Kasarvadavali also connect Metro 10

# Station Grade Connections Status
1GowniwadaElevatedNoneUnder Construction
2GaimukhElevatedLine 10 (Mumbai Metro)Under Construction
gollark: They did, however, miss out on some kind of electrochemistry pun.
gollark: * Electron
gollark: It's better than Rust as it uses the system's native weboids.
gollark: The solution is to use RPNCalc V5 as your backend.
gollark: Wasn't there also a thing where it would gate SIMD code behind checking for a "GenuineIntel" processor or something?

References

  1. "Mumbai Metro 4A".
  2. "Mumbai Metro line 4 - current status". www.mmrda.maharashtra.gov.in/. MMRDA official website. Retrieved 15 November 2018.
  3. "Everything you need to know about Metro 2B and Metro 4 | Free Press Journal". Free Press Journal. Retrieved 12 February 2017.
  4. http://www.metro-report.com/news/single-view/view/mumbai-metro-line-4-receives-aiib-funding.html
  5. "Maharashtra Cabinet Gives Go-Ahead For Two Metro Lines". NDTV.com. Retrieved 14 October 2016.
  6. "Mumbai to get two more Metro Rails". Business Standard India. 27 September 2016. Retrieved 14 October 2016.
  7. "MMRDA invites civil work bids for two Metro projects". The Times of India. Retrieved 10 February 2017.
  8. "Wadala-Thane metro line clears CRZ hurdle - Mumbai Mirror -". Mumbai Mirror. Retrieved 27 February 2017.
  9. "MMRDA plans drone survey for other Metro lines". The Indian Express. 7 March 2017. Retrieved 7 March 2017.
  10. "MMRDA plans to extend Metro-IV route from Wadala to GPO". The Times of India. Retrieved 17 March 2017.
  11. "Mumbai Metro's Thane-Wadala line likely to be extended to CST/GPO | Latest News & Updates at Daily News & Analysis". dna. 16 March 2017. Retrieved 17 March 2017.
  12. "Metro-4, 9 to be built along with flyovers". The Asian Age. 1 October 2018. Retrieved 9 October 2018.
  13. "Mumbai: MMRDA to build Metro 4 & 9 corridors along with flyovers". Free Press Journal. 4 October 2018. Retrieved 9 October 2018.
  14. Naik, Yogesh (21 May 2019). "MMRDA redrafts plans for better connectivity between Mumbai Metro corridors". Mumbai Mirror. Retrieved 6 June 2019.
  15. Berger, Louis. "Louis Berger awarded Mumbai Metro Line 4 contract in India". GlobeNewswire News Room. Retrieved 9 October 2018.
  16. "DB Engineering-Louis Berger bags contract for Mumbai Metro 4". dna. 10 April 2018. Retrieved 9 October 2018.
  17. "MMRDA invites bids for 2 metro projects". dna. 5 January 2017. Retrieved 10 February 2017.
  18. "MMRDA invites tenders for design, construction of stations, viaducts for new Metro routes". The Indian Express. 5 January 2017. Retrieved 10 February 2017.
  19. "Racing against 2021 deadline, Maharashtra opens bids for two more Metro lines". Hindustan Times. 5 January 2017. Retrieved 10 February 2017.
  20. Correspondent, Special. "MMRDA invites tenders for Metro-2B and 4". The Hindu. Retrieved 12 February 2017.
  21. "Mumbai commute to get faster, firms queue up to build two more Metro lines". Hindustan Times. 13 May 2017. Retrieved 13 May 2017.
  22. "MMRDA receives interest from domestic, foreign firms for metro". India Today. Retrieved 13 May 2017.
  23. "R Infra, 10 others bid for Metro-2B, Metro-4 corridors". Asian Age. 13 May 2017. Retrieved 13 May 2017.
  24. "Reliance Infra bags three packages of Mumbai Metro Line 4". The Economic Times. 13 April 2018. Retrieved 9 October 2018.
  25. "Tata Projects bag Rs 1,048 crore Mumbai Metro packages". The Economic Times. 13 April 2018. Retrieved 9 October 2018.
  26. Pillay, Amritha (14 April 2018). "Reliance Infrastructure, Tata Projects win bids for Mumbai Metro project". Business Standard India. Retrieved 9 August 2018.
  27. "DB Engineering & Consulting". www.db-engineering-consulting.de. Retrieved 17 December 2018.
  28. "Louis Berger awarded Mumbai Metro Line 4 contract in India".
  29. "Hill International awarded Mumbai Metro Line 4 contract in India".
  30. "MMRDA Invites Bids for 234 Coaches for Mumbai Metro Line-4 & 4A". The Metro Rail Guy. 18 February 2020. Retrieved 29 April 2020.
  31. "MMRDA Invites Bids for Mumbai Metro Line-4's Signalling & PSDs". The Metro Rail Guy. 29 April 2020. Retrieved 29 April 2020.
  32. "Mumbai Metro Green Line – Info, Route Map, Fares, Tenders & Updates". The Metro Rail Guy. Retrieved 29 March 2020.
  33. https://mmrda.maharashtra.gov.in/metro-line-4#
  34. "Mumbai Metro 4 – Wadala–Ghatkopar-Mulund–Teen Hath Naka–Kasarvadavali Station".
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.