Kozjak Hydro Power Plant
Kozjak Hydro Power Plant is a large hydroelectric power plant on the river Treska which creates an artificial lake Kozjak, the largest in North Macedonia. The dam which creates the reservoir, Kozjak Dam is the tallest in the country at 130 m (430 ft). It is located in the western part of the country in the municipality of Makedonski Brod. The primary purpose of the dam is flood control but it also serves for power generation.[1]
Kozjak Dam | |
---|---|
Kozjak dam and lake, as seen from the Fojnik peak | |
Location of Kozjak Dam in Republic of North Macedonia | |
Country | North Macedonia |
Location | Kozjak |
Coordinates | 41°52′40.37″N 21°11′33.59″E |
Purpose | Flood control, power |
Status | Operational |
Construction began | 1994 |
Opening date | 2000 |
Dam and spillways | |
Type of dam | Embankment, rock-fill |
Impounds | Treska |
Height (foundation) | 130 m (430 ft) |
Height (thalweg) | 114 m (374 ft) |
Reservoir | |
Total capacity | 380,000,000 m3 (310,000 acre⋅ft) |
Surface area | 13.5 km2 (5.2 sq mi) |
Maximum length | 32 km (20 mi) |
Maximum width | 400 m (1,300 ft) |
Commission date | 2004 |
Turbines | 2 x 41 MW Francis-type |
Installed capacity | 82 MW |
The power plant has two turbines with a nominal capacity of 41 MW each[2] having a total capacity of 82 MW.
The lake is 32 km (20 mi) long, with maximum depth of 130 m (430 ft). The maximum elevation of the lake is 469.9 m and it has a capacity of about 380 million m³ of water. There is an abundance of fish in the lake.
The construction of the dam started in August 1994 and it was complete in 2000. The reservoir started filling in May 2003, and the two power generators finally operated in July and September 2004.[3]
References
- Dams and Appurtenant Hydraulic Structures, 2nd edition. CRC Press. 2014. p. 344. ISBN 113800006X.
- Kozjak Hydro Power Plant
- Dams And Reservoirs, Societies And Environment in The 21st Century, Luis Berga; Taylor & Francis, 2006; ISBN 0-415-40423-1, ISBN 978-0-415-40423-5