Heartland Corridor

The Heartland Corridor is a public-private partnership between the Norfolk Southern Railway (NS) and the Federal Highway Administration and three U.S. states to improve railroad freight operations.[1]

Heartland Corridor

The $150 million plan was developed to facilitate more efficient travel on NS rail lines between the Norfolk, Virginia port region and two Midwest destinationsChicago, Illinois and Columbus, Ohio.[2] One of the project goals was to increase clearances in tunnels to permit the operation of double-stack intermodal trains,[1] increasing the capacity of rail lines, shortening rail journeys and reducing tractor-trailer traffic. New shipping terminals for intermodal connections are also planned for key locations.[3]

Construction began in 2007,[4][5][6] and the route opened for double stack service on September 9, 2010.[1]

The project involved raising clearances in 28 tunnels and 24 other overhead obstacles. A total of around 5.7 miles (9.2 km) of tunnels were modified. When completed, the new routing was expected to reduce travel times from port facilities in Virginia to Chicago to three days, improving on the previous four-day travel time and to reduce the distance traveled by 250 miles (400 km).[7]

In June 2010, NS announced that it had reached an agreement with Ohio to extend a leg of the Heartland Corridor southwesterly from Columbus to Cincinnati, which is located on the Ohio River near the border where Ohio, Kentucky and Indiana converge. The $6.1 million cost will be funded with federal economic stimulus funds and the Ohio-Kentucky-Indiana Regional Council of Governments, plus money from NS.[8]

See also

NS corridor growth map

References

  1. "Norfolk Southern opens Heartland Corridor". Railway Gazette International. 2010-09-09.
  2. "Norfolk Southern extends Heartland Corridor's reach". Trains Magazine. 23 June 2010. Retrieved 27 June 2010.
  3. Dennis Cauchon (2006-10-09). "Rail project goes through the roof". USA Today. Retrieved 2009-12-05.
  4. Norfolk Southern's Heartland Corridor rail route to Columbus finishes final link
  5. Norfolk Southern Corporation (2007)."Raising the Roof: Norfolk Southern Begins Work on Heartland Corridor Tunnels." Press release. 2007-11-14.
  6. Port of Virginia (2010-02-18). "Heartland Corridor on Target for Summer Opening." Norfolk, VA.
  7. "Norfolk Southern opens Heartland Corridor". Trains Magazine. 9 September 2010. Retrieved 11 September 2010.
  8. "NS Extends Intermodal Heartland Corridor in Ohio". The Journal of Commerce Online. 2010-06-23.


This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.