MS Project - task is 365 days, but calendar dates are less

0

I am working on a file in MS Project. I have a task that is auto-scheduled and the duration is 365 days. The start date is 7/5 and the calculated finish date is 5/24 which is obviouslby not correct. I have my calendar set to 7 day working week. Thank you for any help!

LindseyT

Posted 2015-02-18T23:33:38.557

Reputation: 1

1Can you [edit] and use an international format for those dates? However I read them, it appears to have more than 365 days, not less. – Paul – 2015-02-18T23:58:35.393

If you have created a calendar that sets 7 working days (change to Work Week) and the task starts on July 5, 2015 (Sunday) - 365 days later should be July 3, 2016.

Can you give us year as well as date data? Do you have resource's assigned with a different working time definition? In File > Options, Schedule - what is your definition of hours per day? – JulieS – 2015-02-23T19:24:10.150

Answers

0

Create a calendar based on the 24 hr calendar, with the following customisation:

Hours per day: 7.3

Hours per week: 51

Days per month: 100

Duration is entered in: Months

Default task type: Fixed Duration

jwamiza

Posted 2015-02-18T23:33:38.557

Reputation: 1