0
I am creating a schedule with two types of tasks:
a) overhead tasks
b) normal work tasks
Simplified this is what I want:
- Task a - overhead X, 1 hour/day - remaining work 20 hours
- Task b - overhead Y, 2 hours/day - remaining work 20 hours
- Task c - Work, 4 hours/day - remaining work 60 hours
- Task d - work, 8 hours/day - remaining work 60 hours
I would like the following schedule (hours per day):
a 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
b 2 2 2 2 2 2 2 2 2 2
c 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
d 1 1 1 1 1 1 1 1 1 1 3 3 3 3 3 7 7 7 7 7
Can anybody help my out with how to achieve this in Project?
NB. I tried assigning task a a 10% rsc, b 20%, c 50% and d 100%
This results in task d to start after task a (the longest one) is finished :-(