0
In Microsoft Project 2007, I can't work out why my tasks are scheduled to finish later than I would expect for the Duration I put in.
I enter a task with a start date on a Monday and a 1-day duration, and it shows the Finish as Tuesday.
Task Name Duration Start Finish
Do Something 1 day 12/04/2010 13/04/2010
How can I set this up so a one-day task takes one day, and not one-and-a-bit? I want a one-day task that starts on a Monday to finish on the Monday.