How can I change the duration of tasks in a Visio 2010 Gantt chart into hours instead of days?

0

I am trying to create a Gantt chart with lots of smaller tasks which often last for only 3 to 4 hours. Is there a way of having the duration column in hours and not days? Thanks!

Max Schumann

Posted 2016-01-03T15:40:54.273

Reputation: 1

Answers

0

On the Gantt Chart Options menu set the Time Units -> Minor Units to Hours and the Duration Units Format to Hours.

If the rest of the chart is in weeks or months then it might be best to have a separate chart for these tasks. You can't mix time units in one chart.

P.S. If you have a bunch of "that's just a five minute job" tasks, you can guarantee that you can only get a maximum of three of these completed in one working day!